VISHAL PATEL VS. UNIQUE BUILDERZ, LLC (L-6167-16. MIDDLESEX COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedApril 29, 2020
DocketA-1436-18T1
StatusUnpublished

This text of VISHAL PATEL VS. UNIQUE BUILDERZ, LLC (L-6167-16. MIDDLESEX COUNTY AND STATEWIDE) (VISHAL PATEL VS. UNIQUE BUILDERZ, LLC (L-6167-16. MIDDLESEX COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VISHAL PATEL VS. UNIQUE BUILDERZ, LLC (L-6167-16. MIDDLESEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1436-T1

VISHAL PATEL,

Plaintiff-Appellant,

v.

UNIQUE BUILDERZ, LLC,

Defendant-Respondent,

and

ASIM MIR,

Defendant. ______________________________

Submitted February 13, 2020 – Decided April 29, 2020

Before Judges Nugent and Suter.

On appeal from the Superior Court of New Jersey, Law Division, Middlesex County, Docket No. L-6167-16.

Frank Craig Fusco, attorney for appellant.

Richard J. Mongelli, attorney for respondent.

PER CURIAM Following a bench trial, plaintiff Vishal Patel appeals the October 19,

2018 final order that entered judgment against him for $60,656.58 in favor of

Unique Builderz, LLC (defendant) for breach of contract under defendant's

counterclaim and then dismissed plaintiff's complaint. The claims arise from a

contract between the parties for the construction of a house in Edison. We affirm

the final judgment.

I.

Plaintiff owned the property where the house was to be constructed. The

parties met in April 2014 through plaintiff's realtor. Defendant, a construction

company formed in 2012, was licensed as a contractor but needed to obtain a

license as a new home builder. They agreed to include H&A Contracting as a

contracting party because it had an active general contractor's license and New

Home Warranty and Builders Registration Card. In addition, the other member

of defendant, also was a member of H&A.

Plaintiff drafted the contract. Defendant wanted changes to the payment

terms and timeline according to the work being requested, but plaintiff would

not agree to include the changes in the written contract. However, defendant

Asim Mir testified that plaintiff "left the contract open for changes . . . which

says that in the contract." Defendant Mir testified plaintiff agreed "verbally that

A-1436-18T1 2 as we progressed, and as we go, he will look into it . . . . And we would revise

as we progressed through the job." Defendant Mir testified plaintiff agreed

verbally before the contract was signed to change the payment terms as the job

progressed.

The May 16, 2014 contract was signed by plaintiff as "homeowner" and

by defendant Mir as "president and owner." The contracting parties included

plaintiff, defendant and H&A. The "contractor," defined as defendant and H&A,

represented it had the "necessary qualifications, experience and abilities" for the

job. The contract provided the contractor would provide the labor and materials

to build a single-family home for plaintiff in accord with the specifications in

the plans. Payment terms in Section C listed specific benchmarks and dollar

amounts for a total contract price of $535,000. The contract provided the work

was to be "complete[d] . . . on time and on budget" by the contractor. It added

that "[t]he authorized person signing the contract on behalf of the contractor

gives personal guarantee to complete the work on-time, within budget and abide

by this contract." The contractor was to provide warranties. A twenty-four-

week schedule was included, but the contract expressly provided that the

"[t]imeline can change or vary by [two] months due to weather permitting,

delayed materials and change orders." The contract specified who would pay

A-1436-18T1 3 for fees and permits and the insurance to be carried by the contractor. Only

plaintiff could terminate the contract. The contract stated this could be "for any

reason, upon notifying the [c]ontractor. Should [plaintiff] exercise this right,

the contractor shall be paid as per the work completed."

Defendant Mir testified the contract was not a "fixed-bid" contract

because there would be a need for payment revisions as the contract progressed.

The contract provided for the selection of various features; the timeline included

benchmarks and could vary "due to weather permitting, delayed materials and

change orders." It contemplated that additional shop drawings and professionals

were needed. Another portion allowed plaintiff to determine during the

construction that the kitchen and bathroom interior arrangement could be

different from the plan. The plan was changed to add a bathroom in the

basement.

When defendant obtained its new home builder's license, the parties

signed a contract addendum on June 12, 2014, that removed H&A from the

contract. The addendum stated that defendant Mir was to "personally guaranty

all terms of the [c]ontract." It added the construction of custom closets. The

addition of custom closets did not include a cost nor adjustment to the

construction timeline. Also, defendant agreed under the addendum to finish

A-1436-18T1 4 construction in eight months or less from the date the permits were issued and

if not, defendant would be responsible for a $200 penalty per day.

Defendant Mir testified that once construction began, he provided plaintiff

with copies of all invoices of expenses and spoke or emailed plaintiff every day.

Plaintiff visited the job site daily but did not raise any issues about project delay

or costs.

By August 18, 2014, plaintiff had made two payments under the contract :

a check for $26,750 on June 23, 2014, and another check on July 8, 2014, for

$53,500. Plaintiff also made a partial payment of $21,418 for windows on July

11, 2014.

By mid-August 2014, defendant contended it had incurred $245,859.19 in

labor and material costs under the contract but had been paid only $155,168.

Some of this was for changes by plaintiff and some for items called for by the

contract. By then the framing was nearly complete. Defendant asked plaintiff

to revise the payment schedule because it had incurred a number of costs and

paid for extras. Defendant Mir testified he gave plaintiff a copy of all the

invoices.

Plaintiff contended defendant was asking for advance payments under the

contract and he had paid what the contract required. He testified there had been

A-1436-18T1 5 delays in construction. Plaintiff made two other payments: on August 19, 2014,

a check in the amount of $36,000 for framing and on August 24, 2014, a check

for $17,500 also for framing.

On August 30, 2014, at plaintiff's request, defendant emailed a revised

payment schedule to plaintiff. Plaintiff claimed defendant would not proceed

further on the house without additional money from plaintiff.

On September 5, 2014, plaintiff sent defendant an email that terminated

the contract, claiming defendant stopped work on August 29, 2014, because

defendant wanted to "revis[e] the payment terms and the contract price."

Plaintiff directed defendant to stop work and not to go to the work site.

Defendant sent plaintiff an invoice for $90,691.19 on September 9, 2014

for work completed under the contract that was not paid. Plaintiff contracted

with another contractor, R.A. Puran Construction, to complete the job for

$325,000. By September 2014, defendant returned to the jobsite to retrieve his

equipment but could not do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
Cruz-Mendez v. ISU/Insurance Services
722 A.2d 515 (Supreme Court of New Jersey, 1999)
Chance v. McCann
966 A.2d 29 (New Jersey Superior Court App Division, 2009)
Harker v. McKissock
96 A.2d 660 (Supreme Court of New Jersey, 1953)
Atlantic Northern Airlines, Inc. v. Schwimmer
96 A.2d 652 (Supreme Court of New Jersey, 1953)
Feigenbaum v. Guaracini
952 A.2d 511 (New Jersey Superior Court App Division, 2008)
Estate of Hanges v. Metropolitan Property & Casualty Insurance
997 A.2d 954 (Supreme Court of New Jersey, 2010)
Green v. New Jersey Manufacturers Insurance
734 A.2d 1147 (Supreme Court of New Jersey, 1999)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
Garfield Trust Co. v. Teichmann
95 A.2d 18 (New Jersey Superior Court App Division, 1953)
CUMBERLAND CTY. IMP. AUTH. v. GSP Recycling Co.
818 A.2d 431 (New Jersey Superior Court App Division, 2003)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Onderdonk v. Presbyterian Homes of NJ
425 A.2d 1057 (Supreme Court of New Jersey, 1981)
Driscoll Const. Co., Inc. v. State
853 A.2d 270 (New Jersey Superior Court App Division, 2004)
Conway v. 287 Corporate Center Associates
901 A.2d 341 (Supreme Court of New Jersey, 2006)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
Krosnowski v. Krosnowski
126 A.2d 182 (Supreme Court of New Jersey, 1956)
Pascale v. Pascale
549 A.2d 782 (Supreme Court of New Jersey, 1988)
Schenck v. HJI ASSOCIATES
685 A.2d 481 (New Jersey Superior Court App Division, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
VISHAL PATEL VS. UNIQUE BUILDERZ, LLC (L-6167-16. MIDDLESEX COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/vishal-patel-vs-unique-builderz-llc-l-6167-16-middlesex-county-and-njsuperctappdiv-2020.