Virginia Electric & Power Co. v. Farrar

135 S.E.2d 807, 205 Va. 244, 1964 Va. LEXIS 173
CourtSupreme Court of Virginia
DecidedApril 27, 1964
DocketRecord No. 5675
StatusPublished
Cited by4 cases

This text of 135 S.E.2d 807 (Virginia Electric & Power Co. v. Farrar) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Virginia Electric & Power Co. v. Farrar, 135 S.E.2d 807, 205 Va. 244, 1964 Va. LEXIS 173 (Va. 1964).

Opinion

Buchanan, J.,

delivered the opinion of the court.

Virginia Electric and Power Company appeals from an order confirming the reports of condemnation commissioners assessing com[245]*245pensation and damages for land in Mecklenburg county taken in eminent domain proceedings from three adjoining tracts owned respectively by Alice Young Farrar, Eula Young and John Thomas Williams, and from a tract owned by William R. Baskerville, Jr., and others, herein referred to as defendants.

The property sought by the Company was the fee simple title to tbe bed and the banks of Allens Creek to a stated height as it flowed along the borders of the Farrar, Young and Williams tracts, and of Miles Creek as it flowed along the border of the Baskerville tract, together with a small additional area of that tract.

Both of these streams empty into the Roanoke River and the property sought to be condemned was alleged to be needed by the ..Company in connection with a dam it proposed to construct on Roanoke River, know as its Gaston Hydroelectric Project, to be locatéd downstream from the Kerr Dam. The Gaston Dam, it was alleged,, might raise the waters to a height at the dam not exceeding 204 feet above mean sea level.

, The Young tract, which contains about 212 acres,' fronts some 5740 feet on the west side of Allens Creek and lies 8.1 miles from the mouth of that creek at the Roanoke River. The area taken from that tract was 3.14 acres, for which the commissioners awarded $628 for the land taken arid $4694 for damages to the residue, a total of $5322.

’ The Farrar tract, adjacent to the Young tract, containing 214 acres, fronts about 6640 feet on the West side of Allens Creek and lies 7.1 miles from the mouth of' that creek. The area taken from that tract was 6.3 acres, for which the commissioners awarded $1260 for the land taken and $2020 for damages to the residue, a total of $3280.

The Williams tract contains 403 acres and fronts some 8820 feet on the east side of Allens Creek. It lies 6.8 miles from the mouth of that creek. The area taken from this tract was 3.6 acres, for which the'commissioners awarded $720 for the land taken arid $5540 for damages to the residue, a total of $6260. . .

The Baskerville.tract contains about 336 acres and is sitriated on Miles Creek, which flows into Roanoke River at a poirit a few miles downstream from the mouth of Allens Creek, the exact distance not being shown. The distances of the Baskerville farm from.the mouth of Miles Creek and from the site of the proposed Gaston Dam are also not shown by the evidence. The aréa • taken- from this tract is 49.4 acres, -for -which the cómiriissionérs -awarded $1940' for the -land •taken and $6460 for damages to the residue, a total of: $8400. .

[246]*246The Farrar, Young and Williams cases were heard by the same commissioners in one proceeding on May 4 and 5, 1962. The Baskerville case was heard on May 7 and 8 by a commission which included three of the commissioners who served in the first proceeding.

The Power Company contends that these awards were grossly excessive as a result of the court’s allowing the owners’ witnesses to testify that the taking of the property so acquired would cause the remaining lands of the owners to be flooded to their great damage. The Company contends that such flooding is an impossibility, that the right to cause it is neither sought nor given in these proceedings, and if caused in the future by the construction and operation of its Gaston project, it would be liable therefor and would have to make coihpensation for it if it happened.

According to the record the Company acquires title to the bed of Allens Creek on the lands of the defendant owners and to its banks or slopes up to a contour level of 214, i.e., to 214 feet above sea level; and it acquires title to the bed of Miles Creek on the Baskerville property and to its banks or slopes up to a contour level of 210.

James M. Hagood, a Senior Engineer for the Power Company, and conceded by the defendants to be “a fully qualified engineer,” testified that about 1957 the Company began preparing to apply to the Federal Power Commission for a license for this Gaston project; that for two years prior to receiving the license he had worked almost continuously on various aspects of the project and that he knew the amount of water released from the Kerr Dam under various conditions; that under normal operating conditions of the Kerr Dam the elevation of the water in the Gaston reservoir at the mouth of Allens Creek will be between 200 and top 204; that for most of the time the elevation will be substantially below 204. This, he said, was because 204 is the elevation point with a maximum power discharge at Kerr Dam of 40,000 cubic feet of water per second; that only once since Kerr Dam was built in 1953 has that much been discharged for a longer period than an hour or so and that was under a test condition, and at that time the recorded elevation at the mouth of Allens Creek was 201.

On the basis of the average discharge from Kerr Dam, said Hagood, the difference in the height of the water under the present conditions and after the dam is built will be not more than two feet, and this [247]*247would have no effect at all on these properties located on the headwaters of the creek. He was then asked why the Power Company was acquiring this land, and this is the substance of his reply:

The Company seeks to acquire title in fee to all land that would be flooded by the discharge from Kerr Dam under maximum flood conditions; that back in 1940, some thirteen years before the Kerr Dam was built, rain coupled with a hurricane caused the greatest flood in that area in recorded history; that under such maximum flood conditions the water released by Kerr Dam would raise the water elevation at the mouth of Allens Creek to 213 or 214. Even that, he thought, would not affect the properties here involved because the maximum discharge from Kerr Dam would not coincide with the peak flow down at Allens Creek.

Hagood further testified that the slopes of Allens Creek would be cleared back along contour 206 for about half way to the downstream boundary of the Williams land, which would clear up the logs and debris now blocking the mouth of the creek and substantially increase the carrying capacity of the stream.

He testified that the slope of Miles Creek on the Baskerville property would be cleared up to 204 or a little more, and that the construction of the Gaston Dam would not have any effect on the Baskerville property under normal conditions which, according to his study, would prevail 99.95 percent of the time. He explained that at a time of maximum flood conditions the release of the water by the Kerr Dam and the operation of the Gaston Dam would bring the elevation of the water at Miles Creek to 210, and that was the reason for acquiring title to the Baskerville land to that point; but he pointed out that such was a very rare occurrence and had happened only once before in a recorded period of fifty years, and never before that so far as could be ascertained. He added that it would be physically impossible to keep the water at the 204 clearing line or at the 210 taking line, which could only be reached under the maximum flood condition described.

There is no contradiction in the record of the testimony given by Hagood as to the various elevations involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jennings v. Commonwealth Transportation Commissioner
83 Va. Cir. 184 (Wythe County Circuit Court, 2011)
Dietz v. Dietz
436 S.E.2d 463 (Court of Appeals of Virginia, 1993)
Virginia Natural Gas, Inc. v. Kipps
29 Va. Cir. 196 (Spotsylvania County Circuit Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E.2d 807, 205 Va. 244, 1964 Va. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/virginia-electric-power-co-v-farrar-va-1964.