Virginia Bridge & Iron Co. v. Camp

298 F. 510, 1924 U.S. Dist. LEXIS 1645
CourtDistrict Court, S.D. Florida
DecidedApril 14, 1924
DocketNo. 197
StatusPublished
Cited by2 cases

This text of 298 F. 510 (Virginia Bridge & Iron Co. v. Camp) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Virginia Bridge & Iron Co. v. Camp, 298 F. 510, 1924 U.S. Dist. LEXIS 1645 (S.D. Fla. 1924).

Opinion

CADE, District Judge.

Complainant filed its bill oí complaint against the defendants, seeking recovery on three contracts for furnishing steel, and for constructing steel on a certain phosphate handling plant at Fernandina, Fla., and a lien on the land upon which the structure stands, under the statutes of Florida. The three contracts and the lien are set out as the basis for recovery. The first, called contract A, is dated December 4, 1919. This contract provides for [511]*511furnishing and erecting the structural steel work for the plant, including a shop coat of superior graphite paint before shipment and an additional coat after election, also to furnish f. o. b. cars at factory, but not erect, the anchor bolts and sagrods supporting wood purlins, the work to be performed according to plans and specifications made a part of the contract. The price to be paid was 6% cents per pound.

The second, called contract B, was entered into January 13, 1920, to furnish, hut not erect, the structual steel work for a stationary loading tower, three track hoppers, including beams in connection thereto, and conveyor supports, as specified in a certain proposal, required in connection with the phosphate handling plant, f. o. b. cars at Roanoke, Va., according to certain plans and specifications made a part of the contract.. The pric'e agreed upon is 8% cents per pound from date of final invoice. The times for performance of the acts by the owner and contractor were named in contract-A.

On August 10, 1920, the two contracts A and B not having been performed according to the terms of each, the parties met and entered into a third contract, called C, and called a supplemental agreement, as follows:

“Supplemental Agreement.
“Whereas, the Virginia Bridge & Iron Company, a corporation, of Roanoke, Virginia, referred to, for convenience, as the ‘Bridge Company,’ and C. & J. Camp, of Ocala, Florida, jointly and individually, referred to, for convenience, as the ‘owner,’ entered into an agreement, (a) dated December 4, 1919, wherein the Bridge Company, in consideration of certain payments to be made by the owner, obligated itself to furnish, deliver, and erect certain structural steel work as more specifically defined therein, and (b) dated January 13, 1920, wherein the Bridge Company, in consideration of certain payments to be made by the owner, obligated itself to furnish and deliver f. o. b. cars Roanoke, Virginia, freight allowed to Fernandina, Florida, certain structural steel work as more specifically defined therein; and whereas, subsequent difficulties have developed of a nature to prevent completion of the work within the time specified; and whereas, the owner now desires the Bridge Company to procure materials from other sources than originally contemplated, with a view of expediting delivery, and further to erect as well as furnish and deliver the steel work referred to in the agreement of January 13, 1920: Now, therefore, witnesseth that:
“Article I. For and in consideration of the additional payments to be made and obligations to be performed by the owner as hereinafter provided, the Bridge Company hereby agrees to erect, upon a site and foundations, together with ingress thereto and egress therefrom, furnished by the owner, the structural steel work to be furnished under the agreement of January 13,1920.
“Article II. The Bridge Company agrees to conform to the following sequence in the fabrication and erection of materials furnished under the aforementioned agreement, viz.: First storage buildings; second, receiving end, commencing with the track hoppers; third, loading end. Erection of materials furnished under contract of January 13, 1920, to be performed during erection of the main structures, or immediately following, as conditions may warrant.
“Article III. The Bridge Company shall make immediate specific request for such additional data as is necessary for the preparation of its detail shop drawings and the efficient prosecution of the work covered by this agreement, and the owner agrees to deliver such lacking information to the Bridge Company not later than September 1, 1920.
“Article IV. The owner will complete and deliver to the Bridge Company ready for erection, the' foundations for the storage buildings not later than September 20, 1920, and additional foundations at such time and in such man[512]*512ner as will allow continuous and complete erection of all the steel work covered by this agreement, not later than December 1, 1920.
“Article V. Should the owner fail to provide the information referred to in article III, or deliver the foundations, within the time specified, then and in that event the Bridge Company shall be allowed an extension of time, for completion of the erection, equivalent to such delay in receipt of information, or foundations, provided the Bridge Company notifies the owner in writing at the time such delay occurs.
“Article VI. The Bridge Company agrees to complete the work covered by this agreement not later than December 1, 1920, with extension, if any, mutually agreed upon, for delays incident to articles III and IV. All other risks of delivering, due to strikes, transportation delays, etc., to be assumed by the Bridge Company.
“Article VII. The owner agrees that, if the Bridge Company shall well and faithfully fulfill this agreement, and the covenants herein contained, and faithfully fulfill same, then the owner hereby binds himself pr itself, and heirs, successors, executors, administrators, or assigns, to pay to the Bridge Company in funds current at par in New York City, over and above the consideration stipulated in the aforementioned agreement of December 4, 1919, and January 13,1920: (a) Bor completion December 1, 1919, or such extension of that date as may be mutually agreed upon, one and one-half cents ($0,015^) per pound of material furnished, in addition to the prices and in the manner, specified in the above-mentioned agreements; If completion date, or extension of that date mutually agreed upon, is not adhered to by the Bridge Company, this provision is void and the prices specified in the original contracts shall apply, the owner retaining out of the final estimate, such increased cost as has been previously paid; and (b) for the erection of material furnished under contract dated January 13, 1920, cost plus ten per centum (10%), in which cost shall be included all pay rolls, foreman’s salary,- liability insurance, fuel and sundry supplies, together with a proportionate part of the cost of transporting men and equipment to and from the work and an arbitrary charge, not exceeding ten per cent. (10%) of the pay roll, for the use of tools and equipment. Payments to be made monthly to the amount of eighty per cent. (80%) of estimated value of work performed to date, with final estimate plus any retained percentage on completion.
“In witness whereof, the parties to these presents have duly executed this agreement in duplicate this 10th day of August, 1920.
“Virginia Bridge & Iron Co.,
“By [Signed] H. A. Davies, Contracting Engineer.
“Witness for Bridge Company:
“[Signed] J. C. Senter.
“C. & J. Camp.
“By [Signed] Jack Camp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Bldg. Corp. v. Hillis
66 S.W.2d 597 (Court of Appeals of Tennessee, 1933)
State ex rel. La Follette v. Kohlee
200 Wis. 518 (Wisconsin Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
298 F. 510, 1924 U.S. Dist. LEXIS 1645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/virginia-bridge-iron-co-v-camp-flsd-1924.