Vinyard v. North Side Canal Co., Ltd.

274 P. 1069, 47 Idaho 272, 1929 Ida. LEXIS 115
CourtIdaho Supreme Court
DecidedFebruary 4, 1929
DocketNo. 5012.
StatusPublished
Cited by12 cases

This text of 274 P. 1069 (Vinyard v. North Side Canal Co., Ltd.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vinyard v. North Side Canal Co., Ltd., 274 P. 1069, 47 Idaho 272, 1929 Ida. LEXIS 115 (Idaho 1929).

Opinion

GIVENS, J.

A history of this case and the issues are set forth in Vinyard v. North Side Canal Co., 38 Ida. 73, 223 Pac. 1072, wherein the court reversed and remanded the ease for the trial court to find whether there was any surplus storage water, holding that if there was, appellant and his class would be entitled to their pro rata share.

The principal point in the appeal herein is that the trial court, instead of making specific findings on the question of surplus, set forth a conclusion that there was no surplus. A specific finding should have been made but since it was not, if the facts show that no finding conflicting with the conclusion reached could have been made, the action will not be reversed. (Tage v. Alberts, 2 Ida. 271, 13 Pac. 19; Wood v. Broderson, 12 Ida. 190, 85 Pac. 490; Berlin Machine Works v. Dehlbom Lumber Co., 29 Ida 494, 160 Pac. 746; Storey & Fawcett v. Nampa & Meridian Irrigation District, 32 Ida. 713, 187 Pac. 946; Basinger v. Taylor, 36 Ida. 591, 211 Pac. 1085; Pleasants v. Henry, 36 Ida. 728, 213 Pac. 565; Erickson v. Winegar, 41 Ida. 1, 236 Pac. 870.)

The original contracts of the settlers of the second and third segregations with the Carey Act construction company gave them respectively l/80th and l/100th of a cubic foot per second to be supplied under the terms of the contract between the state and the construction company in part from the natural flow of Snake River and in part from storage in the Jerome and Wilson reservoirs, measured within one-half mile of their respective lands. (Collins v. Twin Falls Co., 28 Ida. 1, 152 Pac. 200; Ricker v. Twin Falls Co., 39 Ida. 93, 226 Pac. 167.)

*275 When it was found and determined from the attempted actual operation thereof that the Jerome and Wilson reservoirs would not hold water, a supplemental contract was made March 27, 1913, between the state and the construction company providing that the company should acquire storage rights in the Jackson Lake reservoir to take the place of the storage in the Jerome and Wilson reservoirs until such time, if any, within certain time limits, that they could be made serviceable.

The part of this supplemental contract of March 27, between the state and the company, which is material is as follows:

“That the company shall procure to be stored.at the Jackson Lake Reservoir in the State of Wyoming or elsewhere, at the option of the second party, an amount of water in excess of 170,000 acre feet in accordance with the resolutions of the Land Board adopted December 27, 1912, it being understood that the said party of the second part may procure such storage to be provided by the government of the United States, or by some other person or corporation, it being understood that if water is procured from Jackson Lake or some other Government Reservoir, that it will be subject to terms and conditions of the Act of Congress commonly known as the Warren Act [43 U. S. C. A., secs. 523-525], and other laws relating thereto.
“2. That water stored at Jackson Lake Reservoir, or such other reservoir as may be provided under the terms hereof, may be used on the lands under the irrigation canals of the Twin Falls North Side Land and Water Company in Lincoln and Elmore counties, State of Idaho, in lieu of water stored in Wilson Lake or Jerome Reservoirs, and the said party of the second part is authorized and empowered to procure such storage elsewhere than at the last named reservoirs.
“3. That waters stored at Jackson Lake or elsewhere shall be delivered proportionately until final dedication authorized in paragraph seven hereof at the intake of Wilson Lake and Jerome reservoirs, the amount so furnished at such points, together with the amounts that may be *276 stored in said Jerome and Wilson Lake reservoirs, shall equal the amount for each acre sold under the reservoir system which said reservoirs were originally designed to hold for each acre originally under said system, State lands and private lands within the general limits of any segregation to be included herein and to be considered as a part of the project as of the date of the segregation within the general limits of which they are included. It is the intent hereof not to change the existing contractual relations of the parties so far as the water supply to which the settlers are entitled is concerned, it being the purpose only to provide for the storage of water elsewhere so far as the same may be necessary and to provide the proper proportionate amount of water in accordance with the terms of the contracts by the parties of the second part with the State and with the settlers for each acre of land to be delivered at Wilson Lake and Jerome Reservoirs in proportion to the capacity of said reservoirs as originally planned; that is to say, as if fifteen-seventeenths of said water was stored at Jerome and two-seventeenths at Wilson Lake reservoirs.
******** * * * *
“8. It is anticipated that the said party of the second part will procure more water to be impounded at Jackson Lake than is called for by the terms of this agreement and any additional water so impounded may be used for the irrigation of other lands, or for other purposes.”

Appellants contend that by this contract only 170,000 acre-feet measured at the intake of the Jerome and Wilson reservoirs were given to the settlers on the second and third segregations. Respondents take the position that sufficient storage within the total amount secured, namely, 312,007 acre-feet (that is, above elevation 6752 in the Jackson Lake reservoir, the only amount in controversy) sufficient to fill the settlers’ rights of l/80th and l/100th acre-feet was intended to be so supplied. Respondents further contend that appellants and their class are entitled, and the court so found, to none of the surplus, if any, from this storage. The previous opinion decided otherwise (Vinyard v. North Side Canal Co., supra) and such is therefore the *277 law of this case (Hall v. Blackman, 9 Ida. 555, 75 Pac. 608; Steve v. Bonners Ferry Lumber Co., 13 Ida. 384, 92 Pac. 363; Gerber v. Nampa etc. District, 19 Ida. 765, 116 Pac. 104; Nampa v. Nampa etc. District, 23 Ida. 422, 131 Pac. 8; Williams v. Sherman, 36 Ida. 494, 212 Pac. 971), and the portion of the findings, conclusions and judgment entered thereon by the trial court is erroneous.

The decisive question is what amount of this storage now belongs exclusively and primarily to the second and third segregations. If only 170,000' acre-feet measured at the Jerome and Wilson reservoirs, there is in the average year a surplus, of some 10,820 acre-feet; if, however, they are entitled to their full water right of l/80th and l/100th acre-feet measured within one-half mile of their lands, there is in an average year a deficit of from 155,030 acre-feet to 77,098 acre-feet dependent upon the different calculations of the engineers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shrum v. Wakimoto
215 P.2d 991 (Idaho Supreme Court, 1950)
North Side Canal Co. v. Idaho Farms Co.
96 P.2d 232 (Idaho Supreme Court, 1939)
Shepherd v. Dougan
83 P.2d 468 (Idaho Supreme Court, 1938)
Henderson v. Twin Falis County
80 P.2d 801 (Idaho Supreme Court, 1938)
Creem v. Northwestern Mutual Fire Ass'n
74 P.2d 702 (Idaho Supreme Court, 1937)
In Re Appeal From the Department of Reclamation
300 P. 492 (Idaho Supreme Court, 1931)
Garvin v. First National Bank
298 P. 359 (Idaho Supreme Court, 1931)
Weigle v. Salmino
290 P. 552 (Idaho Supreme Court, 1930)
Union Grain & Elevator Co. v. McCammon Ditch Co.
288 P. 157 (Idaho Supreme Court, 1930)
McClung v. Twin Falls North Side Land & Water Co.
33 F.2d 478 (Ninth Circuit, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
274 P. 1069, 47 Idaho 272, 1929 Ida. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vinyard-v-north-side-canal-co-ltd-idaho-1929.