Vine v. Robert W. Kennedy Co.

2 N.J. Misc. 774, 1924 N.J. Ch. LEXIS 92
CourtNew Jersey Court of Chancery
DecidedAugust 7, 1924
StatusPublished

This text of 2 N.J. Misc. 774 (Vine v. Robert W. Kennedy Co.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vine v. Robert W. Kennedy Co., 2 N.J. Misc. 774, 1924 N.J. Ch. LEXIS 92 (N.J. Ct. App. 1924).

Opinion

Buchakan, V. C.

Complainants, owners of a recently erected pair of houses, being sued, by several stopmotice claimants and by the contractor Sweeny, filed bill in the nature of interpleader, tendering payment into court of the sum of $1,284 (which they admitted to be clue from them to the contractor) and such additional sum, if any, as might be determined to be due from them to the contractor. After the proofs at the hearing they admit liability of $1,424.

The first issue (there being no contest as to complainants’ right to relief) is as to the amount for which complainants are liable. The contract (which, with the specifications, was duly filed under the Mechanics’ Lien act) binds Sweeny to erect the two houses for complainants, for which they were to pay him $12,600 in four installments, as follows: (1) $2,000 -when first floor joists are on; (2) $3,000 when tile roof is on; (3) $3,000 when plastering is done; (4) $4,600 when buildings are completed.

There is a further clause that “If the owners do not have the $3,000 for third payment, the said Frank L. Sweeny will have to furnish the same by getting someone to take a ($7,600) mortgage on property unless owners can get same.”

The contract, which is on a printed form, contains no other unusual provisions. No architect rvas named therein (nor intended so to lie), so that the printed provisions as to the architect are surplusage. The contract was made April 21st, 1922, and specified October 1st, 1922, as the date when the house should be completed.

The first and second payments were made: the third payment was not made. It is not seriously disputed that it became due and payable, though there is a conflict as to just when it became due. There is no doubt in my mind but that it was due on October 1st, at least. On October 7th the contractor abandoned the job, as he himself admits (although he, of course, claims he was justified in so doing). [776]*776Complainants, oil October 19th, proceeded to have the houses completed by others, and paid therefor (omitting payments for some minor alterations and extras) $6,226. Deducting this from $7,650 (the $7,600 unpaid under the contract, plus $50, which they say they agreed to pay Sweeny for drawing the plans), leaves the $1,424, which they admit to be due.

It is, of course, undisputed that, unless'Sweeny had legal justification for abandoning the contract, complainants were entitled to have it completed by others, and (as against Sweeny, at least) to deduct the reasonable cost thereof from the unpaid balance of the contract price. Herein lies the crux of the case.

There was considerable argument as to the clause about raising the $7,600 on mortgage, but I am unable to see that •this is of any great materiality. Whether or not it ever was Sweeny’s duty to procure a mortgage for complainants, the proofs show that he did procure two parties able and willing to make the mortgage loan — first, the Hanover Trust Compaiw, and secondly, after being1 told by complainant they preferred a private individual as mortgagee, a client of Dickinson & Company. Complainants, after finding that they would be required to pay the usual broker’s commission to Dickinson & Company, went back to the TIanover 'Trust Company. Sweeny performed all that the contract required him to do in this behalf.

The important question is whether or not Sweeny was legalty justified in abandoning the job on .October 7th.

The evidence is conflicting as to the occurrences that took place at that time. The contract required the owners to make a payment of $3,000 when the plastering was done. I am satisfied from the entire evidence that on October 1st (and probably for a little while before that) the progress of construction had substantially reached that point.

A few square feet of one wall in the bathroom in each house remained unplastered, but it appears that this was customary, and was done so as to permit certain work to be done by the plumbers. The “dashing’’ of a cellar wall had [777]*777not been done, nor certain outside stucco work, but these were not part oí what is meant by builders as “plastering.” Moreover, a little of the trim had been put on in one house, and most of it in the other, so that in this respect it had progressed beyond the plastering. Complainants, who were foreigners and unfamiliar with building, evidently had too literal an idea of the meaning of “when the plastering is done,” and thought that Sweeny was not entitled to the $3,000 as long as the unplastered holes in the bathroom wall remained and the dashing and stucco was not completed, and from this arose some argument between them and Sweeny as to his being entitled to the $3,000.

It further appears by Sweeney’s own admission that for some time prior to October 7th he had been proceeding very slowly with the work. He says this was because the owners had been dilatory in making the prior pajonent (which was not contradicted). On October otli, Philip Vine, as attorney for the owners, wrote Sweeny a letter that “unless you resume active work” on the buildings and “complete same very soon” (the contract date for completion was October 1st), the owners would have the work completed by another contractor and charge loss or damage to Sweeny. Sweeny admits getting this letter on October Gth.

This was the situation on October 7th, On that day Sweeny says he asked Vine (one of the owners) “what he was going to do about some money; I thought it was time to come through. They said they were not going to pay any until I was done. * *. * When they told me they were not going to paj' me any money I quit.” After that date lie did no more work. And. at another point in the hearing, Sweeny said, “Mr. Vine told me he wasn’t going to pay me no money till the job was complete,” and that was the reason Sweeny didn’t get lien releases for the intending mortgagee. Chris Wagner, a workman then and now in Sweeny’s employ, also testified that Vine asked him (Wagner) “a week or so before we quit” why Sweeny didn’t go ahead with the job, and said “he would pay him the money [778]*778when he gets the work done, what was coming to him,” that he would pay him when “the whole job was completed.”

On the other hand, Berkowitz, one of the owners, says “I asked Sweeny what’s the matter. He said he wanted the other $3,000. We said we would give it to you near time it is due. He said, To hell with the houses” he was mad at that time; that is the way he went out.” Vine, the other owner, says that a day or two before Sweeny quit he had a conversation with him, Sweeny asking for the $3,000 payment, and he (Vine) saying that it wasn’t due yet, and that Sweeny had agreed to get the money (evidently referring to the clause as to procuring a mortgagee), and further reminding Sweeny that in the negotiations for the contract they had told him that they had only $5,000, and hence he would have to wait for the. balance of the contract price until the job was completed, which resulted in the insertion of the clause for the third payment of $3,000 and the clause that Sweeny should procure the mortgagee. Sweeny replied, “If I don’t get any money I’m going to quit.” A day or two later (Vine testifies) he said to Sweeney that he would give him enough money for men and materials for the few days until Sweeny could furnish lien releases to the intending mortgagee, so that Sweeny could proceed with the work; that Sweeny replied he didn’t need it, “but when I went he said T want $3,000; that was the last thing. I seen I couldn’t, do nothing with him.”

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
2 N.J. Misc. 774, 1924 N.J. Ch. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vine-v-robert-w-kennedy-co-njch-1924.