Vincent Partin v. Superior Energy Services, Inc.

CourtCourt of Appeals of Texas
DecidedMay 25, 2018
Docket01-17-00629-CV
StatusPublished

This text of Vincent Partin v. Superior Energy Services, Inc. (Vincent Partin v. Superior Energy Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vincent Partin v. Superior Energy Services, Inc., (Tex. Ct. App. 2018).

Opinion

ACCEPTED 01-17-00629-CV FIRST COURT OF APPEALS HOUSTON, TEXAS 5/25/2018 1:21 PM CHRISTOPHER PRINE CLERK

Martin, Disiere, Jefferson&Wisdom L.L.P. __________________________________________ __________________________________________ ATTORNEYS AT LAW FILED IN 808 Travis Street • 20th Floor • Houston, Texas 77002 • Phone: 713-632-1700 • Fax: 713-222-0101 • www.mdjwlaw.com 1st COURT OF APPEALS HOUSTON, TEXAS 5/25/2018 1:21:53 PM Robert T. Owen CHRISTOPHER A. PRINE PARTNER Clerk Direct: 832-333-1627 e-mail: owen@mdjwlaw.com

May 25, 2018

Christopher A. Prine Clerk, First Court of Appeals First Court of Appeals 301 Fannin Street Houston, Texas 77002-2066 Via e-file

Re: Partin v. Superior Energy Services, Inc., No. 01-17-00629-CV, In the First Court of Appeals, Houston, Texas

Dear Mr. Prine,

Please distribute this post-argument letter to Chief Justice Radack and Justices Jennings and Lloyd. This letter provides the Court with additional information regarding the factual issues the Court explored with the parties during the May 22, 2018 argument.

The Record Demonstrates There Are Genuine Issues Of Material Fact On Each Of The Grounds Upon Which The District Court Granted Summary Judgment

At oral argument, Justice Jennings asked Mr. Tillery to show the Court the “rock solid” evidence conclusively establishing that Superior Energy was entitled to summary judgment. There is no such evidence, and the record demonstrates there are, at the least, genuine issues of material fact regarding the Arctic Challenger’s status as a “vessel” and Mr. Partin’s status as a “seaman.”

1 The Arctic Challenger’s Status As A Vessel

Mr. Partin suffered his accident in August 2013. See CR 115-18, 139. To be entitled to summary judgment on the ground that the Arctic Challenger was not a “vessel,” Superior was required to conclusively establish that the Challenger was not a “vessel” on that date. In support of that position, at oral argument Mr. Tillery argued (1) that the Arctic Challenger was incomplete because it had not completed its sea trials and had not been delivered to Shell, and (2) that, even if the Challenger was complete, it had been removed from navigation due to Shell’s requests for major modifications.

The Arctic Challenger Was Complete And Delivered To Its Owner/Operator

The evidence demonstrates that the Arctic Challenger was “fully operational and functional, and ready to be deployed” in March 2013, after the Challenger received its Certificate of Inspection from the Coast Guard on October 11, 2012 and completed its March 2013 sea trial for the government and Shell. See CR 269, 487.

Moreover, because it is undisputed, and indisputable, that Shell did not own or operate the Arctic Challenger (see CR 269), Superior’s focus on the date the Challenger was delivered to Alaska for use in Shell’s Arctic drilling operations is not relevant to the Arctic Challenger’s status as a vessel. Indeed, the record establishes that Greenberry Industrial, the contractor charged with constructing the oil containment system for the Arctic Challenger, completed its work in 2012 and delivered the Challenger to Superior, the Challenger’s lessor and operator. See CR 350-51, 618-19.

The Arctic Challenger Had Completed Its Sea Trials, Was Fully Functional, And Ready To Deploy

At oral argument, Mr. Tillery contended that the Arctic Challenger was not a “vessel” because it was still undergoing sea trials in August 2013, pointing to a sea trial occurring in 2015. However, the Superior corporate representatives repeatedly testified that the Arctic Challenger was capable of being deployed following its March 2013 sea trial and that the reason it was not actually deployed was because Shell cancelled the 2013 and 2014 arctic drilling seasons. See, e.g., CR 487, 704. Moreover, as the evidence shows Superior’s contracts with Shell required the Arctic Challenger to complete annual sea trials to continue to operate

2 (see CR 768), under Superior’s theory the Arctic Challenger would never acquire “vessel” status because there would always be another sea trial required to be conducted in the future.

The Arctic Challenger Was Not “Out Of Navigation” At The Time Of Mr. Partin’s Accident

There is also a genuine issue of material fact regarding Superior’s position that the Arctic Challenger was taken “out of navigation” at the time of Mr. Partin’s accident. Superior’s corporate representatives testified that Shell did not ask Superior to take the Arctic Challenger out of “deployable readiness stage” until July 2014, nearly one year after Mr. Partin’s August 2013 accident. CR 712. Superior’s corporate representative also testified the modifications requested by Shell following the March 2013 sea trial were not “major,” and again, Superior repeatedly testified that the Arctic Challenger was capable of being deployed after it completed its March 2013 sea trial. See, e.g., CR 487, 491.

Indeed, there is an abundance of evidence in the record showing that the Arctic Challenger qualified as a “vessel” at the time of Mr. Partin’s accident. Superior’s corporate representatives testified:

Q. What was the deadline [to complete the Arctic Challenger]? A. I don’t recall the exact date, but it was the start of the . . . drilling season in the Arctic. So from the moment we got our certificate of inspection from the Coast Guard [on October 11, 2012], we were eligible to mobilize.

CR 523, 269.

Q. . . . In a general sense, these systems [referencing various systems on the Arctic Challenger] became operational at different points in time; would that be correct? . . . A. So all of the systems came operational during the construction phase. All of the systems were operational by September 2012.

CR 684.

3 Q. Your testimony is that as of – as of December 2012, the Arctic Containment System was fully functional and could do exactly what it was designed to do; is that correct? A. Yeah. . . . Q. But – well, that’s to the satisfaction of Shell? A. That’s what I said, yes.

CR 705.

Q. . . . So then you got 12-12 and everything goes smoothly? A. So we got our stamp from the government in March of 2013. Q. So when you say “government stamp”? A. So BSEE [Bureau of Safety and Environmental Enforcement] signed off that the system was operational and met their requirements.

CR 706.

Q. Okay. Is it [the Arctic Challenger] capable of being deployed to an emergency? A. Yes. Q. And when did that capability first manifest itself; when was that? What did that first? A. Well, we got our first Coast Guard certificate of inspection in late 2013. 1 But prior to that, it made several nonresponse deployments. But when we get out certificate of inspection . . . we are deemed ready to deploy to an emergency.

CR 423-24.

Q. When did it [the Arctic Challenger] become fully operational? A. In December 2012 . . . the dome was damaged. We rebuilt the dome, did a deployment test for Shell, and did that successfully. And then they called off their drilling season, but we demonstrated it for them and BSEE.

CR 704.

1 Superior’s corporate representative misspoke; it is undisputed, and indisputable, that the Coast Guard issued its certificate of inspection on October 11, 2012. CR 269.

4 Q. Mr. Peyton, earlier, if I understood your testimony, you said that the Challenger was fully operational and functional, ready to be deployed for spills sometime in the 2013, right? A. Correct. That’s correct. Q. Where there any major modifications to the system after that, after that point in time? A. I don’t know if you would consider any modifications major, but there were modifications made on Shell’s request, our customer.

CR 487.

Q. So Shell didn’t want it to be deployed until all this stuff [requested modification] was taken care of? A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chandris, Inc. v. Latsis
515 U.S. 347 (Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Vincent Partin v. Superior Energy Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/vincent-partin-v-superior-energy-services-inc-texapp-2018.