Vincent C. Carter v. Eagles Landing Restaurants

CourtCourt of Appeals of South Carolina
DecidedAugust 24, 2022
Docket2019-001062
StatusUnpublished

This text of Vincent C. Carter v. Eagles Landing Restaurants (Vincent C. Carter v. Eagles Landing Restaurants) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vincent C. Carter v. Eagles Landing Restaurants, (S.C. Ct. App. 2022).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA In The Court of Appeals

Vincent C. Carter d/b/a Elite Construction Co., Respondent,

v.

Eagles Landing Restaurants, LLC, Appellant.

Appellate Case No. 2019-001062

Appeal From Florence County Eugene Preston Warr, Jr., Special Referee

Unpublished Opinion No. 2022-UP-347 Heard April 12, 2022 – Filed August 24, 2022

AFFIRMED AS MODIFIED

Brooks Roberts Fudenberg, of Law Office of Brooks R. Fudenberg, LLC, of Charleston, for Appellant.

Gary Ivan Finklea and Patrick Buel Ford, both of Finklea Law Firm of Florence, for Respondent.

PER CURIAM: In this breach of contract and quantum meruit action between Vincent Carter d/b/a Elite Construction Co. and Eagles Landing Restaurants, LLC (Eagles Landing), Eagles Landing argues the special referee erred in (1) denying Eagles Landing a properly calculated setoff, (2) declining to award Eagles Landing damages for lost profits, and (3) applying an improper standard in reviewing the parties' Rule 59(e), SCRCP, motions. We affirm as modified.

Facts and Procedural History

Mohammed Makawi owns several IHOP restaurants and manages them through a limited liability company, Eagles Landing. In 2015, Makawi sought to open a new IHOP in Charleston. The building, a former Ruby Tuesday restaurant, had been vacant for ten to twelve years and required extensive renovations.

Carter, a general contractor and friend of Makawi, submitted a bid to renovate the building for $624,354.00. The bid proposed a ninety-day construction schedule and included an itemized "bid breakdown" listing the costs for various aspects of the project. Carter and Makawi executed a lump sum contract (the Contract) providing, "The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract. The Contract Sum shall be Six Hundred Twenty Four Thousand Three Hundred Fifty Four ($624,354.00), subject to additions and deductions as provided in the Contract Documents."

The Contract required Eagles Landing to make progress payments to Carter, with final payment due after the City of Charleston issued a certificate of occupancy to the contractor, net 10 days, and specified:

Contractor is to be paid $100,000 from this contract as a Project Management Fee. Payments to be made to contractor as progress of work begins. Payment and amount requested shall be at the discretion of contractor. Typically, payment draws to contractor for payment shall be made 1/3 after start net 2 weeks. Another 1/3 half way into project progress and final 1/3 at or near completion.

After executing the Contract, Makawi had difficulty obtaining financing and was unable to get a traditional loan to finance the project. Ultimately, Eagles Landing borrowed approximately $500,000, and Makawi anticipated proceeds from the sale of North Carolina real estate would help fund the renovation.

After demolition began, Carter discovered mold in the building and immediately halted work. Due to the additional work and cost of the mold remediation, Carter executed a change order. Carter recorded several additional change orders reflecting both Makawi's requests to amend the scope of the work and Carter's crediting of Eagle's Landing on certain cost savings.

During the course of construction, Jimmy Free, Eagles Landing's former Chief Financial Officer, paid Carter when he requested a draw, until at some point, Makawi instructed Free not to pay Carter. Then, when Eagles Landing did pay, it did not cover the full draw—instead, Carter had to "prove" what he spent on labor and materials, and he was paid only enough to cover those costs. This placed Carter in the position of being unable to pay his subcontractors. Eagles Landing began paying subcontractors directly due to filed mechanic's liens. In all, Eagles Landing paid Carter only $229,900 on the $624,354.00 Contract.

On October 23, 2015, the City issued a temporary certificate of occupancy; a permanent certificate of occupancy followed in late November. On February 10, 2016, Carter notified Eagles Landing of the remaining amount due under the Contract, which Carter calculated to be $438,306.50. On March 17, 2016, electrical contractor Carolina Construction Solutions filed an action against both Carter and Eagles Landing seeking payment for its work on the project.

Carter then filed this action for breach of contract and unjust enrichment/quantum meruit. Eagles Landing timely answered and counterclaimed for breach of contract, fraud, quantum meruit, negligence, and indemnification.

Following a nonjury trial, the special referee found Eagles Landing breached the Contract with Carter. The special referee further held that even if certain change orders were not part of the Contract, Eagles Landing was unjustly enriched based on the labor and materials Carter furnished pursuant to the change orders. The special referee acknowledged the parties agreed Eagles Landing paid $390,888.33 to third-party vendors and subcontractors for work related to the project. The order then broke down these payments into two itemized lists: one delineating Eagles Landing's $212,195.26 in third-party payments for work within the scope of the Contract, and another listing $97,607.74 in payments for work performed outside the scope of the Contract. After accounting for the previous payments to Carter, payments to third parties, and certain project-related credits, the special referee calculated Eagles Landing owed Carter $160,130.83.

Eagles Landing and Carter filed motions to alter or amend the special referee's order. While these motions were pending, Eagles Landing reached a $50,000 settlement with Carolina Construction Solutions. By supplemental order, the special referee denied the post-trial motions and increased the award to Carter "from $160,130.83, to 176,794.99, plus additional interest due" in light of Carter's own $16,664.16 confession of judgment to Carolina Construction Solutions.

Law and Analysis

I. Setoff for Carolina Construction Solutions Payments

"An action for breach of contract seeking money damages is an action at law." McCall v. IKON, 380 S.C. 649, 658, 670 S.E.2d 695, 700 (Ct. App. 2008). "In an action at law tried without a jury, an appellate court's scope of review extends merely to the correction of errors of law. The Court will not disturb the trial court's findings unless they are found to be without evidence that reasonably supports those findings." Miller Constr. Co., LLC v. PC Constr. of Greenwood, Inc., 418 S.C. 186, 195, 791 S.E.2d 321, 326 (Ct. App. 2016) (quoting Temple v. Tec–Fab, Inc., 381 S.C. 597, 599–600, 675 S.E.2d 414, 415 (2009)). With respect to setoff requests, "South Carolina courts have consistently held 'there can be only one satisfaction for an injury or wrong.'" Stoneledge at Lake Keowee Owners' Ass'n, Inc. v. IMK Dev. Co., LLC, 435 S.C. 109, 133, 866 S.E.2d 542, 555 (2021) (quoting Smith v. Widener, 397 S.C. 468, 471, 724 S.E.2d 188, 190 (Ct. App. 2012)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCall v. IKON
670 S.E.2d 695 (Court of Appeals of South Carolina, 2008)
Branche Builders, Inc. v. Coggins
686 S.E.2d 200 (Court of Appeals of South Carolina, 2009)
Vortex Sports & Entertainment, Inc. v. Ware
662 S.E.2d 444 (Court of Appeals of South Carolina, 2008)
Elam v. South Carolina Department of Transportation
602 S.E.2d 772 (Supreme Court of South Carolina, 2004)
Temple v. Tec-Fab, Inc.
675 S.E.2d 414 (Supreme Court of South Carolina, 2009)
Smith v. Widener
724 S.E.2d 188 (Court of Appeals of South Carolina, 2012)
Miller Construction Co. v. PC Construction of Greenwood, Inc.
791 S.E.2d 321 (Court of Appeals of South Carolina, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Vincent C. Carter v. Eagles Landing Restaurants, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vincent-c-carter-v-eagles-landing-restaurants-scctapp-2022.