Villas at Packer Condo Assn. v. JPG Group, Inc.

CourtSuperior Court of Pennsylvania
DecidedMay 14, 2019
Docket827 EDA 2018
StatusUnpublished

This text of Villas at Packer Condo Assn. v. JPG Group, Inc. (Villas at Packer Condo Assn. v. JPG Group, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Villas at Packer Condo Assn. v. JPG Group, Inc., (Pa. Ct. App. 2019).

Opinion

J-A01034-19

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

VILLAS AT PACKER PARK : IN THE SUPERIOR COURT OF CONDOMINIUM ASSOCIATION : PENNSYLVANIA : Appellant : : : v. : : : No. 827 EDA 2018 JPC GROUP, INC., JPG GENERAL : CONTRACTORS, LENICK : CONSTRUCTION, INC. D/B/A : LENICK CARPENTERS III, INC., DEL : SERVICES, MID ATLANTIC : MECHANICAL, CIMORELLI : CONSTRUCTION A/K/A CIMORELLI : CONSTRUCTION & FENCE. CO., DALE : CORPORATION, DJM CONSTRUCTION : A/K/A DJM CONSTRUCTION CO., : INC., CRINITI CONSTRUCTION, INC., : G.L. WOLFGANG CONSTRUCTION : COMPANY, HANCOCK BUILDING : ASSOCIATES, INC., UNION : ROOFING, INC., VOEGELE : MECHANICAL, INC., LPI : MECHANICAL, LLC, AND PROBUILD : EAST, LLC,

Appeal from the Order Entered April 7, 2017 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 03103 February Term, 2013

BEFORE: OTT, J., STABILE, J., and McLAUGHLIN, J.

MEMORANDUM BY McLAUGHLIN, J.: FILED MAY 14, 2019

In this appeal, Villas at Packer Park Condominium Association (“Villas”)

maintains that the trial court improperly applied the gist of the action doctrine

and erroneously concluded that the statute of limitations barred its contract

and warranty claims. We affirm. J-A01034-19

The trial court aptly summarized the facts and procedural history of this

case as follows:

Villas is a condominium development consisting of 23 multifamily building with four units in each building. Lenick Construction, Inc. (“Lenick”) was hired by the general contractor, Westrum Urban Construction, LLC (“Westrum”), to install windows and French doors at the Villas in or about May 1, 2006. In 2006, Villas unit owners began to complain of water infiltrating their individual units. Specifically, on November 21, 2006, homeowners wrote to Westrum representatives, including the superintendent, project manager, and vice president of operations and complained as follows:

It has been two weeks since the consultant looked at our French doors, and nearly a week since we e- mailed you to let you know that the door continued to leak after the new strip was installed.

I was just going through my files and this will be the ninth e-mail I have sent you about the French doors since October 28. We first made you aware of the problem last summer.

Westrum investigated the complaints and informed the unit owners that upgraded doors were to be provided to eight homeowners. In September 2009, Westrum once again began receiving complaints of leaking roofs and sliding glass doors from homeowners. On September 15, 2009, counsel on behalf of two homeowners forwarded a letter to Westrum concerning the leaks, Westrum’s responsibility for defects concerning the construction and suggesting that Westrum investigate the construction and design defects.

On February 28, 2013, Villas filed a complaint against Westrum Park Place L.P., Westrum Urban G.P., LLC, Westrum Construction LLC, John Westrum and John O. Mershon (“Westrum”) alleging deficiencies in the construction of the Villas’ development. On September 16, 2013, Westrum filed a writ to join Lenick and other subcontractors as additional defendants. The joinder complaint was filed on October 7, 2013 and amended on November 25, 2013, December 9, 2013 and January 14, 2014. Westrum’s

-2- J-A01034-19

joinder complaints alleged that Lenick and the other subcontractors breached their contracts with Westrum, breached the express and implied warranties within the contract and owed Westrum contractual and common law indemnity and contribution.

From June 24, 2014 to August 30, 2014, the action was stayed by joint request of all the parties. During this period, Villas entered into a settlement agreement with the Westrum defendants wherein Westrum assigned its claims against Lenick to the Villas. On December 4, 2015, Villas amended the complaint as an assignee of Westrum and alleged claims for breach of contract, breach of implied warranty of workmanship, negligence and contribution and indemnity against Lenick.

In September 2016, Lenick filed a partial motion for judgment on the pleadings and a partial motion for summary judgment. On February 7, 2017, the court granted the partial motion for judgment on the pleadings and dismissed the claim for negligence. Additionally, the court denied Lenick’s motion for summary judgment finding that Villas’ claims for breach of contract and breach of implied duty of workmanship as an assignee of Westrum were timely filed. Lenick filed a motion for reconsideration of the order denying the motion for summary judgment. Upon review of the motion for reconsideration, the court vacated its February 7, 2017 order in part denying the partial motion for summary judgment based on the issue of statute of limitations and ordered oral argument. . . After oral argument and a review of the papers and record, the court on April 7, 2017, granted Lenick’s motion for partial summary judgment and dismissed the claims for breach of contract and breach of the implied warranty of workmanship as barred by the statute of limitations.

Trial Court Pa.R.A.P. 1925(a) Opinion (“TCO”), filed June 29, 2018, at 1-3

(footnotes omitted). This timely appeal followed.

Villas presents the following issues for our review:

I. Did the trial court commit an error of law in granting Lenick[’s] Motion for Judgment on the Pleadings where neither the gist of the action doctrine nor the economic loss doctrine barred [Villas] negligence claims?

-3- J-A01034-19

II. Did the trial court commit an error of law when it ruled that the statute of limitations on the first party defendants’ joinder claims began to run before plaintiff initiated its original action and, therefore, before the first party defendant suffered a harm?

III. Did the trial court commit an error of law or abuse its discretion in ruling that there were no material facts in dispute and that evidence was clear and free from doubt as to when the statute of limitations on the third party joinder claims began to run?

IV. Did the trial court err in granting summary judgment on a deficient evidentiary record based on unauthenticated emails, letters, and inadmissible hearsay evidence?

Villas’ Br. at 8-9 (suggested answered omitted).

First, Villas maintains that the trial court erred in granting Lenick’s

motion for partial judgment on the pleadings and challenges the trial court’s

application of the gist of the action doctrine.

Entry of judgment on the pleadings is permitted under Pennsylvania Rule of Civil Procedure 1034, which provides that “after pleadings are closed, but within such time as not to unreasonably delay trial, any party may move for judgment on the pleadings.” Pa.R.C.P. 1034(a). A motion for judgment on the pleadings is similar to a demurrer. It may be entered when there are no disputed issues of fact and the moving party is entitled to judgment as a matter of law.

Appellate review of an order granting a motion for judgment on the pleadings is plenary. The appellate court will apply the same standard employed by the trial court. A trial court must confine its consideration to the pleadings and relevant documents. The court must accept as true all well pleaded statements of fact, admissions, and any documents properly attached to the pleadings presented by the party against whom the motion is filed, considering only those facts which were specifically admitted.

-4- J-A01034-19

We will affirm the grant of such a motion only when the moving party’s right to succeed is certain and the case is so free from doubt that the trial would clearly be a fruitless exercise.

Sw. Energy Prod. Co. v. Forest Res., LLC,

Related

Romeo & Sons, Inc. v. P.C. Yezbak & Son, Inc.
652 A.2d 830 (Supreme Court of Pennsylvania, 1995)
Botkin v. Metropolitan Life Insurance
907 A.2d 641 (Superior Court of Pennsylvania, 2006)
Bank of America, N.A. v. Gibson
102 A.3d 462 (Superior Court of Pennsylvania, 2014)
Bruno, D., Aplts. v. Erie Insurance
106 A.3d 48 (Supreme Court of Pennsylvania, 2014)
Coleman v. Duane Morris, LLP
58 A.3d 833 (Superior Court of Pennsylvania, 2012)
Southwestern Energy Production Co. v. Forest Resources, LLC
83 A.3d 177 (Superior Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Villas at Packer Condo Assn. v. JPG Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/villas-at-packer-condo-assn-v-jpg-group-inc-pasuperct-2019.