Village of Port Clinton v. Cleveland Stone Co.

6 Ohio Cir. Dec. 218
CourtOttawa Circuit Court
DecidedJune 15, 1892
StatusPublished

This text of 6 Ohio Cir. Dec. 218 (Village of Port Clinton v. Cleveland Stone Co.) is published on Counsel Stack Legal Research, covering Ottawa Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Port Clinton v. Cleveland Stone Co., 6 Ohio Cir. Dec. 218 (Ohio Super. Ct. 1892).

Opinion

TenteEY, J.

The petition in this case was filed September 16, 1891, in the court of common pleas. It sets forth generally that in the summer of 1890, by due and proper proceedings, the plaintiff let a contract to one Philip Sullivan to improve Second street in this village, between two certain streets mentioned in the petition; that Sullivan gave bond for the performance of this work that he had contracted to do; entered upon the performance of the work; did some portion of it, and finally in October of that year, 1890, abandoned the work. That certain of the sureties upon his bond,'after the abandonment of the contract by Mr. Sullivan, gave notice that they would complete the contract as provided in the original specifications, as sureties upon Sullivan’s bond. That they thereupon, and with the assent of the village, completed the work, which was accepted by the "village.

The petition states that no estimate had been given to Sullivan up to the "time that he had abandoned the work. About the 31st day of October, 1890, •plaintiff caused an estimate to be made of everything done in pursuance of the •contract up to the time of abandonment by Sullivan, which estimate amounted to $2,414.58. _

_ The petition further says that on completion of the contract by the sureties, the village paid the sureties all the contract price except $2,414.58, and it makes •defendants to the petition the various parties who claim to have liens upon the fund in question, and Mr. Sullivan himself. It asks that the court adjudge how this fund shall be distributed; that the validity and priority of allliens and claimsbe determined ; that the plaintiff may be directed in the payment of the same out of the funds; that the defendant, Sullivan, and the other defendants herein may be estopped from asserting any further liens or claims against plaintiff arising under said contract; and for all proper relief.

The petition, however, after alleging that the amount of $2,414.58 was the balance of the original contract price after the payment to the sureties, sets up that the village has in fact paid out a portion of that amount, so that the whole sum of $2,414.58 is not in its hands. _ ..

[219]*219The allegation is this: “Plaintiff says that soon after said Sullivan entered upon the performance of his said contract, being unable to go on with said work, jplaintiff, to enable him to do so, in consideration that he would not abandon said work, in good faith, made a payment to said Sullivan of $200.00 on said contract, without any estimate having been furnished therefor as required by the terms of said contract; also that the plaintiff, with the assent of said Sullivan, he being still unable to complete said work for want of means, bound itself to the defendant, Geo. E. St. John, to the amount of $496.27, in consideration that if he would ■contribute labor and materials for the completion of said work, plaintiff would pay him for moneys advanced on that account, without any estimate having been made to said Sullivan as provided by the terms of said contract.”

There is scarcely any contest regarding the payment of this $200.00. While it was made in advance of the time provided for in the contract, yet it seems to have been made in good faith, and for the purpose named in the petition; and under the. holding of the court in Schneidhorst v. Luecking, 26 Ohio St., 47, it seems that there could be no question about the pajmient of that item — that • the village had a right to make the payment, and the sum, $2,414.58, should be diminished by $200.00. y

There is, however, a spirited contest about deducting the $496.27, it being ■claimed that the village had no power or right to make the contract set forth in the petition, and even if it had, it would have no right to deduct this sum from the above amount to the detriment of the creditors of Sullivan and the sureties. It is contended that there was no resolution or ordinance by the council regarding the payment of this sum; that, in fact, no binding agreement was made with the council regarding it; that at best it was a dealing of the members of the council with St. John, and was not binding on the village, whatever effect it would have on the members of the council.

It will be noticed in the case I have mentioned in the ,26 Ohio St., that this was done and approved by the supreme court: “A contractor after entering upon the performance of his contract, being unable for want of means to go on with the work, the owner, to enable him to do so, in consideration that he would not abandon the contract, in good faith made payments to the contractor faster than he was required to do by the original contract, for which he was to be allowed interest; and also with the assent of the contractor, bound himself to other parties, in consideration that if they would contribute labor or materials towards the completion of the work, he 'would pay them therefor. Held, that the money thus paid, and the liabilities thus assumed, were not payments in advance of the sums due, within the section of the mechanics’ lien law.” The defendants claim that there was no obligation entered into by the council of the village, or by the village, in the form prescribed by the statute for paying out the money of the treasury. It is contended that the council had no power to make such agreement.

The proof upon that subject shows that upon a regular meeting of the council, with a majority, if not all the members of the council present, it was made to .appear by statements there that Sullivan had certain stone shipped to him here for the purpose of this improvement; that the railroad company required him to pay the freight; that he would have to abandon the contract unless' something was done to help him pay the demands of the railroad company. Thereupon, St. John being present, and being treasurer of the corporation, a suggestion was made that he advance the money for this purpose, it being said that he had the money in his hands, and that as the contractor consented that out of the first estimate made he should be repaid, St. John would be safe, and it would be proper for him to pay this money in advance to pay the freight. St. John declined to do this unless he was sure of getting his money. He was assured there by the members of the council that he wou Id be safe in so doing. The proof also shows that St. John, relying upon the statements made and the situation there shown, in order that the contract might not be abandoned and the work [220]*220might proceed,' advanced or paid through the contractor himself, all the freight-due to the railroad corppany to whom tbe freight was coming, amounting to-$496.27.

It is said that the proof of the application of these payments was not very clear. But whatever proof there was is not contradicted. The village, after all the time elapsed, sets up that it obligated itself for freight to the amount of $496.27,- and we think that this $496.27 was thus paid. .

The question is whether it should be deducted from this sum claimed to be due. Sullivan makes no ciaim that this money is coming to him. It seems to-us clearly, under the authority in the 26 Ohio St. and perhaps one qr two other cases, that if the village had made this $496.27 payment, the village would have-been entitled to it as against the parties to this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
6 Ohio Cir. Dec. 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-port-clinton-v-cleveland-stone-co-ohcirctottawa-1892.