Village of Barrington Hills v. Life Changers International Church

820 N.E.2d 1068, 354 Ill. App. 3d 415, 290 Ill. Dec. 1, 2004 Ill. App. LEXIS 1446
CourtAppellate Court of Illinois
DecidedDecember 3, 2004
Docket1-03-0140 Rel
StatusPublished
Cited by3 cases

This text of 820 N.E.2d 1068 (Village of Barrington Hills v. Life Changers International Church) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Barrington Hills v. Life Changers International Church, 820 N.E.2d 1068, 354 Ill. App. 3d 415, 290 Ill. Dec. 1, 2004 Ill. App. LEXIS 1446 (Ill. Ct. App. 2004).

Opinion

JUSTICE O’MARA FROSSARD

delivered the opinion of the court:

Defendant, Life Changers International Church (Church), was found in violation of two provisions of the Village of Barrington Hills Municipal Code (the Code). Based on those violations, the trial court fined the Church $100,000. The trial court denied the Church’s motion to reconsider and this appeal followed. The only issue presented by the instant appeal is whether the imposition of a $100,000 fine was an abuse of discretion by the trial court.

BACKGROUND

On September 16, 1999, the engineer and the zoning enforcement officer for the Village of Barrington Hills (Village) observed large amounts of earth, gravel, and asphalt on the Church property at 180 North Hawthorne Road, Barrington Hills. Additionally, the property reflected excavations from several areas as well as substantial areas of plant cover that had been disturbed or removed. The Village informed the Church by letters beginning on September 20, 1999, that it was not in compliance with section 4 — 3—4 of the Code. Section 4 — 3— 4(A)(1) of the Code provides that a site development permit is required before “land is cleared, graded, transported or otherwise disturbed,” and “excavation, fill, or any combination thereof will exceed 300 (300) cubic yards” or plant cover is to be removed from an area exceeding either 20,000 square feet or 10 acres depending upon whether the parcel of land is vacant. Village of Barrington Hills Municipal Code § 4 — 3—4(A)(1) (eff. 1982). The original September 20, 1999, letter sent by the Village to the Church regarding these issues notified the Church that failure to comply with the Code could result in a fine up to $500 per day.

Numerous written communications occurred between counsel for the Village and the Church. The November 11, 1999, letter from the Village to the Church states “this letter will set forth the current status regarding the various violations by the church,” and asserts “[n]o building permit application has ever been made to the Village regarding the excavation, fill, and removal of plant cover by the church.” The Church’s November 19, 1999, letter responding to the Village’s letter states the Church’s belief that it had, to the best of its knowledge, complied with all of the provisions of the Code and the requirements of the building permit issued for the construction of the Church.

On March 22, 2000, the Village filed its complaint alleging the Church violated section 4 — 3—4 by placing in excess of 300 cubic yards of fill on the property, by improperly clearing and disturbing substantial areas of plant cover, and by improperly excavating several areas without applying for and obtaining a site development permit. The Village attached an exhibit to the complaint consisting of photos of the west, east, and north sides of the Church. The complaint alleges that the photos reflect the earth fill, plant cover removal, and excavation as of September 16, 1999.

The Church filed a motion for summary judgment on June 21, 2000. In its motion, the Church argued that the notices of violation and related letters demonstrated it received no notice of, and the Village never intended to prosecute, any alleged violations other than those related to the location and placement of soil on the Church’s property. The Church further argued that if the Village intended to prosecute other activities as Code violations, it should have complied with due process by giving the Church sufficient notice of such additional alleged violations. The motion noted that the Village was seeking fines “in an amount up to $500 per day from September 20, 1999 and continuing through the date of judgment.” The trial court denied the Church’s motion for summary judgment.

On May 10, 2001, the trial court entered an order finding the Church in violation of section 4 — 3—4 of the Code regarding site development and in violation of section 6 — 4—4 of the Code regarding storm water management. The order states in relevant part:

“1. Defendant is currently in violation of Sections 4 — 3—4 and 6 — 4—4 of the [Code], Such violations have existed since September 16, 1999 and continue to exist to this day.
2. Based on the aforesaid violations, Defendant is hereby ordered to file with this Court and submit to the [Village] on or before June 11, 2001 engineering calculations and plans prepared by a registered professional civil engineer in the state of Illinois. Said calculations and plans must adhere to the storm water management standards as set forth in Section 6 — 4—4 of the [Code]. Any detention basins designed and constructed pursuant to the aforesaid engineering calculations and plans shall provide one foot of free-board above the design high-water level. Detention basins adjacent to the state right-of-way shall have a minimum of two-feet free-board.
Defendant shall also file with this Court and submit to the [Village] on or before June 11, 2001 a site development plan and building permit application pursuant to the requirements of Section 4 — 3—4 of the [Code].
3. Once Defendant’s engineering calculations, plans and site development plan are reviewed and approved and the building permit issued, Defendant shall commence work within fourteen (14) days of the approval and issuance.
4. All work shall be completed within twenty-eight (28) days after being commenced.
5. Within twenty-one (21) days after completion of the work Defendant shall file with this Court and submit to the [Village] ‘As Constructed’ drawings of the storm water management facilities prepared by a registered professional civil engineer or registered professional land surveyor in the state of Illinois and calculations, prepared by a registered professional civil engineer in Illinois based on the ‘As Constructed’ drawings demonstrating that the storm water management facilities have been constructed in accordance with the approved plans. Said engineer shall also provide a certification to this effect.
6. Finally, this matter is set for 9/21/01 at 9:00 a.m. for the Court’s consideration and imposition of fines pursuant to Section 4 — 3—10 of the [Code] based on the aforesaid violations.”

The trial court entered an agreed order on September 21, 2001, which reflected the Church had not yet completed and filed all required building permit applications and had not issued payment to the Village for the fees as required by the May 10, 2001, order. The court did, however, find that the Church had “complied with appropriate *** plans and specifications for the improvements/corrections required by the Village” and stated that “upon approval by the Village authorities *** Defendant shall without undue delay cause the required [C]ode compliance work to be undertaken.” The case was continued by agreed order to November 30, 2001, to review the status of the Church’s compliance and to entertain the Village’s motion for fines.

The record includes a “Civil Engineer’s Field Report” prepared by the Village’s civil engineer which is dated November 28, 2001, two days before the November 30, 2001, status hearing. The “Observations” section of that report notes as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County of Du Page v. Arjmand
2025 IL App (3d) 240408-U (Appellate Court of Illinois, 2025)
CITY OF McHENRY v. Suvada
920 N.E.2d 1173 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
820 N.E.2d 1068, 354 Ill. App. 3d 415, 290 Ill. Dec. 1, 2004 Ill. App. LEXIS 1446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-barrington-hills-v-life-changers-international-church-illappct-2004.