This text of Village Associates Act 250 LU Permit (Village Associates Act 250 LU Permit) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village Associates Act 250 LU Permit, (Vt. Ct. App. 2009).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Village Associates Act 250 Land Use Permit } Docket No. 6-1-08 Vtec (Appeal of Village Associates, LLC) } }

Decision and Order

Appellant Village Associates, LLC appealed from a decision of the District 4

Environmental Commission, granting Appellant’s Act 250 permit for an affordable

housing development, but requiring an off-site mitigation fee under 10 V.S.A.

§§ 6086(a)(9)(B)(iv) and 6093. Appellant is represented by Heather R. Hammond, Esq.;

and the Agency of Agriculture, Food and Markets is represented by Assistant Attorney

General Diane E. Zamos, Esq. The Land Use Panel of the Natural Resources Board has

informational status through John H. Hasen, Esq. but did not file memoranda or

otherwise participate in the merits of this appeal.

The project proceeded during the pendency of this litigation, as the only issue

was whether or not an off-site mitigation fee would be required to be paid. An

evidentiary hearing was held in this matter before Merideth Wright, Environmental

Judge. A site visit was taken by Judge Wright alone, by agreement of the parties,

including, at the request of the parties, driving to or past a number of area agricultural

operations mentioned in evidence. The parties were given the opportunity to submit

written memoranda and requests for findings. Upon consideration of the evidence as

illustrated by the site visit, and of the written memoranda and requests for findings

filed by the parties, the Court finds and concludes as follows.

1 Appellant-Applicant proposed1 a multi-unit affordable housing development, to

be known as Brookside Village, on the 25.8-acre parcel of property that is the subject of

this appeal. The project was granted an Act 250 permit; the only issue in this appeal is

whether the project site contains primary agricultural soils as defined in Act 250, 10

V.S.A. § 6001(15), which in turn governs whether the project must pay an off-site

mitigation fee.2 See 10 V.S.A. §§ 6086(a)(9)(B)(iv), 6093.

The roughly triangular property is located in the towns of Colchester and

Winooski. It is bordered on its westerly side by the Winooski River and on its northerly

side by Morehouse Brook. The long southeasterly side of the property has access to the

surrounding street network via its frontage on a cul-de-sac turnaround at the end of

West Street, a residential street in Winooski. A hammerhead turnaround ends near the

property at the end of Hickok Street, another residential street one block north of West

Street, but the project plans do not propose any access from the project property onto

Hickok Street. West Street has access to Malletts Bay Avenue, the primary through

street in the area, via Pine Street. Pine Street is relatively steep at its intersection with

Malletts Bay Avenue.

In addition to the West Street access, the northeasterly corner of the property has

two segments of frontage on Malletts Bay Avenue, from two existing residential lots

that became part of the project property as a whole. The property has a total of

approximately 300 feet of frontage onto Malletts Bay Avenue. The proposed project

roadway to serve more than forty dwelling units will have access directly onto Malletts

Bay Avenue via the longer, more easterly segment of that frontage; the project has a

secondary access onto the West Street turnaround.

1 The project and project property has since been transferred to Housing Vermont, which has not entered an appearance. 2 The parties have also agreed as to the amount of that fee, if this decision concludes that it must be paid. 2 The parties do not dispute that 12.88 acres of the property contain soils that are

classified on the Natural Resources Conservation Service soil maps as farmland of

“statewide importance.”3 The parties do not dispute that 2.03 acres of such soils are

located so that they are unusable, and therefore do not constitute primary agricultural

soils. The parties agree that that 10.85 acres of the 12.88 acres of quality soils, on a

plateau above the floodplain of the Winooski River, will be affected by the project. That

is, Applicant does not dispute the quality of the soils on the project property, their

physical and chemical characteristics, or their soil map classifications. Rather,

Applicant disputes whether other factors, in particular the property's existing forest

cover, surrounding land uses, and access issues, have already reduced its agricultural

potential so that no mitigation fee should be required under 10 V.S.A.

§§ 6086(a)(9)(B)(iv) and 6093.

The 10.85 acres of the project property now contains a healthy eastern woodland,

including some stands of mature trees as well as regenerating eastern woodland of

predominantly hardwood species. The mature trees have value if harvested for timber;

the dollar value of that timber was not established in evidence. The regenerating forest

and the stumps and slash from the mature trees would have value if harvested for

wood chips to supply the nearby McNeil electric generating plant; the dollar value of

the wood chips was not established in evidence. There is no technical or physical

impediment to the removal of trees from the 10.85-acre portion of the project property.

The 10.85 acres of the project property was farmed in the past, but is too small to

house a livestock operation such as a dairy farm. Daily or near-daily access to the

property for milk trucks, manure spreaders, or large tractors via West Street through

the adjacent residential neighborhood would be incompatible with the residential use of

3 To some extent, the soil map classifications themselves account for whether the soils are too rocky, too steep, or have too shallow a depth to bedrock, to be good agricultural soils. 3 that neighborhood. The 10.85 acres of the project property could be used to grow hay,

or to grow vegetables and fruits, all of which require far less frequent access to the site

for large machinery.

A working equine facility with an indoor riding ring is located on Malletts Bay

Avenue in Colchester less than a mile north of the project property. A working dairy

farm is located on Malletts Bay Avenue in Colchester approximately a mile-and-a-third

north of the project property. The dairy farm works land on both sides of the road. A

large successful diversified fruit and vegetable farming operation, including a retail

farm store, is located in Colchester approximately 2½ miles north of the project

property. A community garden, located less than half a mile to the south in downtown

Winooski, is not a commercial agricultural operation.

Over the last four years, a small diversified vegetable farming operation in

Shelburne has succeeded in two successive locations, farming on three to four-and-a-

half acres, with the assistance of greenhouses and polyethylene tunnels or cold frames

to extend the growing season. The farmer had previously run a similar small operation

in Massachusetts that also included soft fruits such as blueberries and raspberries. The

Shelburne farming operation is successful through a combination of retail sales at

farmers’ markets, specialty sales to restaurants, and sales of CSA (Community

Supported Agriculture) shares, in which each member pays a share price in advance of

the growing season and is entitled to a share of the produce each week during the

growing season.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Miller
2009 VT 36 (Supreme Court of Vermont, 2009)
State v. Stell
182 Vt. 368 (Supreme Court of Vermont, 2007)
State v. Brennan
775 A.2d 919 (Supreme Court of Vermont, 2001)
Wright Ex Rel. Hood v. Bradley
2006 VT 100 (Supreme Court of Vermont, 2006)
In re Estate of Cote
2004 VT 17 (Supreme Court of Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Village Associates Act 250 LU Permit, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-associates-act-250-lu-permit-vtsuperct-2009.