Vial v. South Central Bell Telephone

423 So. 2d 1233, 1982 La. App. LEXIS 8524
CourtLouisiana Court of Appeal
DecidedNovember 10, 1982
Docket5-143
StatusPublished
Cited by10 cases

This text of 423 So. 2d 1233 (Vial v. South Central Bell Telephone) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vial v. South Central Bell Telephone, 423 So. 2d 1233, 1982 La. App. LEXIS 8524 (La. Ct. App. 1982).

Opinion

423 So.2d 1233 (1982)

Dr. David J. VIAL
v.
SOUTH CENTRAL BELL TELEPHONE COMPANY.

No. 5-143.

Court of Appeal of Louisiana, Fifth Circuit.

November 10, 1982.
Rehearing Denied January 17, 1983.

*1235 Leon C. Vial, III, Hahnville, for plaintiff-appellee.

R. Patrick Vance, Jones, Walker, Waechter, Poitevent, Carrere & Denegre, New Orleans, for defendant-appellant.

Before BOUTALL, BOWES and CURRAULT, JJ.

CURRAULT, Judge.

This appeal arises from a trial court judgment rendered in favor of plaintiff-appellee, Dr. David J. Vial, and against defendant-appellant, South Central Bell Telephone Company, for damages pursuant to an action in trespass.

The facts reveal that in 1956 appellant obtained from appellee's predecessor-in-title a twelve-foot wide right-of-way on the subject property. The servitude extends along two contiguous boundary lines. In 1972, appellant entered the property and installed several conduits and cables outside of the right-of-way. Appellee subsequently purchased the land in 1973. Several years later, in 1976, appellants again entered the property to install five underground manholes for access to the conduits. These installations were also placed on appellee's property outside of the servitude. In both instances appellant acknowledged that the installations were constructed out of the servitude unknowingly and mistakenly. Sometime in 1976, after observing appellant's activity on the property, appellee hired a surveyor to determine his legal rights. The survey commenced on July 15, 1976, and was completed on August 3, 1976. It revealed that appellant's constructions were located beyond their servitude boundaries. On August 6, 1976, appellee's attorney notified South Central Bell of the problem. Following appellant's failure to either relocate the manholes or compensate appellee for the trespass, suit was filed on May 23, 1977.

After denying appellee's exception of prescription, the case was tried on the merits. Judgment was rendered on April 27, 1981, awarding appellee, Dr. Vial, $24,312 for damage to land taken for the manholes, $30,200 for damage to land lying between the manholes, and $15,000 for mental anguish, pain and suffering with legal interest from date of judicial demand plus all costs.

South Central Bell Telephone Company appeals that judgment.

*1236 ISSUES PRESENTED ON APPEAL

(1) Whether the trial court erred as a matter of law in failing to find that an action for trespass has prescribed.

(2) Whether the trial court erred as a matter of law in refusing to apply the St. Julien Doctrine.

(3) Whether the trial court erred in assessing damages to the land taken for the manholes.

(4) Whether the trial court erred as a matter of law and/or abused its discretion in its award of $30,200 in damages for the land between the manholes.

(5) Whether the trial court erred as a matter of law and/or abused its discretion in awarding appellee $15,000 for damages for mental anguish and pain and suffering.

ISSUE NO. 1

Did the trial court err in failing to find the action in trespass had prescribed?

An action in trespass prescribes one year from the date knowledge of damages is received by the owner. LSA-C.C. art. 3537. The jurisprudence has long recognized that knowledge may be actual or constructive. Poirier v. Burton-Swartz Cypress Co., 127 La. 936, 54 So. 292 (La.1911); Reymond v. Sumrall, 67 So.2d 925 (La.App. 1st Cir.1953). Constructive knowledge occurs where plaintiff has been put on sufficient notice to require investigation. He must file suit within the year from the date he received such knowledge. Poirier, supra; Reymond, supra. Where the trespass is a continuing one, however, prescription does not begin to run until the offending object is removed. Joseph A. Neyrey, Gen. Cont. v. Louisiana Power and Light Co., 347 So.2d 266 (La.App. 4th Cir.1977), application denied, 350 So.2d 897 (La.1977). The record clearly reveals that the conduits and manholes, mistakenly placed outside the servitude, continued to illegally occupy appellant's property at least until the date of trial. It is further indisputably evidenced by the record that appellant began construction on the manholes in January, 1976, but that appellee did not commission a survey until July, 1976. The results of that survey became available in August, 1976, and apprised appellee of the trespass.

While appellant raised several issues in the trial of the matter, the trial court found as a matter of fact that appellee did not receive actual notice of the trespass until August and further that appellant's activities did not cease until July rather than April, 1976, as contended by appellant.

Our review of the record and the law pertinent to these facts leads this court to conclude that appellant's arguments are without merit for several reasons.

Under the standard elucidated in Neyrey, supra, appellant's continuing occupation of land belonging to the property owner constitutes a continuing trespass, and as such prescription is inapplicable. Furthermore, even absent a finding of continuing trespass, we fail to perceive the necessary elements required for prescription in those cases where the trespass has ceased. The trial court found, and we cannot find manifest error in its findings, that both actual knowledge and cessation of the activities occurred within the prescriptive period. In the absence of manifest error, we are restrained from disturbing those factual findings. Arceneaux v. Domingue, 365 So.2d 1330 (La.1978); Canter v. Koehring, 283 So.2d 716 (La.1973). In addition, our review leads this court to conclude that constructive knowledge cannot be imputed to appellee since appellant owned a legal servitude giving them the right to be in the area that their employees were working. Absent a survey, no trespass could have been determined due to the fact that the servitude was only twelve feet wide. Thus, we affirm the trial court's holding that as the suit was filed timely, the action was not prescribed.

ISSUE NO. 2

Did the trial court err in failing to apply the St. Julien Doctrine?

The St. Julien Doctrine developed jurisprudentially as an adjunct to and deviation from Louisiana's expropriation laws. LSA-C.C. arts. 2626-2641. Dating back to St. Julien v. Morgan's Louisiana & Texas Railroad *1237 Co., 35 La.Ann. 924 (1883), the doctrine provided public or quasi-public corporations possessing the power of expropriation a method of acquiring servitudes or rights-of-way over the land of another without resort to expropriation proceedings. However, it was necessary that the landowner had knowledge of the construction and consented to it or acquiesced in it. Allowing the structures to remain, it granted the landowner damages only for their presence. Lake, Inc. v. Louisiana Power and Light Co., 318 So.2d 911, 912 (La.App. 4th Cir. 1975); reversed 330 So.2d 914 (La.1976). The Louisiana Supreme Court in Lake, supra, overruled the doctrine prospectively as it related to acquisition of discontinuous apparent servitudes; however, in October of the same year, the legislature enacted the Doctrine in LSA-R.S. 19:14. Appellant urges and we agree that neither the Lake decision nor the legislative pronouncement are applicable here since the conduct in question began in January, 1976 and ended in July, 1976. Thus, if the facts dictate, the case herein is subject to the original jurisprudential requirements.

Implicit in the St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bayou Fleet Partnership v. Clulee
150 So. 3d 329 (Louisiana Court of Appeal, 2014)
Aertker v. Placid Holding Co.
874 F. Supp. 2d 585 (M.D. Louisiana, 2012)
Lonatro v. Orleans Levee District
809 F. Supp. 2d 512 (E.D. Louisiana, 2011)
McNeill v. Rice Engineering & Operating Inc.
2006 NMCA 015 (New Mexico Court of Appeals, 2005)
Succession of Harvey v. Dietzen
716 So. 2d 911 (Louisiana Court of Appeal, 1998)
Sellers v. St. Charles Parish
655 So. 2d 367 (Louisiana Court of Appeal, 1995)
Howard v. Louisiana Power & Light Co.
583 So. 2d 503 (Louisiana Court of Appeal, 1991)
Dykes v. Peabody Shoreline Geophysical
482 So. 2d 662 (Louisiana Court of Appeal, 1985)
Smith v. Louisiana Power & Light Co.
638 F. Supp. 361 (E.D. Louisiana, 1984)
Vial v. South Central Bell Telephone Co.
432 So. 2d 265 (Supreme Court of Louisiana, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
423 So. 2d 1233, 1982 La. App. LEXIS 8524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vial-v-south-central-bell-telephone-lactapp-1982.