Veterans Electrical Service, Inc. v. Robley J. Gelpi & Sons, Inc.

369 So. 2d 736, 1979 La. App. LEXIS 3636
CourtLouisiana Court of Appeal
DecidedMarch 22, 1979
DocketNo. 9572
StatusPublished

This text of 369 So. 2d 736 (Veterans Electrical Service, Inc. v. Robley J. Gelpi & Sons, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Veterans Electrical Service, Inc. v. Robley J. Gelpi & Sons, Inc., 369 So. 2d 736, 1979 La. App. LEXIS 3636 (La. Ct. App. 1979).

Opinion

REDMANN, Judge.

This appeal by defendant cost-plus contractor and its answer by plaintiff electrical subcontractor question the measure of payment due for wiring a building using wire of lower current-carrying capacity than that specified, in virtually every one of the 200 or so circuits, requiring either replacement of wire (and sometimes of conduit) to raise capacity or else replacement of circuit breaker to make the circuit safe.

Defendant’s principal argument is that this is not a case of substantial performance, in which plaintiff recovers contract price less cost of remedying deviations from the contracted performance. Defendant argues that plaintiff should recover nothing (beyond the progress payments already made) because of lack of proof of quantum of unjust enrichment, if any. Alternatively, defendant argues that it is entitled to deduct from the contract price the full cost of bringing the circuitry up to specified [737]*737capacities notwithstanding that in half the circuits it did not do so.

Plaintiff’s principal argument is that its written bid did not form the basis for the final contract, which was only for a safe electrical system; the original plans were for a two-story building and they were not revised for the one-story building that was built, and the electrical circuitry had other changes, affecting even the service connections to the public source. Plaintiff contends that it did in all respects supply the safe system bargained for, as well as electrical design services in some instances, and that it should collect the contract price. We disagree, and affirm the trial judge’s conclusion that the contract was embodied in the written bid and acceptance.1

[738]*738We agree with defendant that this is not a case of substantial performance, and therefore plaintiff is not entitled to contract price less cost of curing defects. Yet we agree with the trial judge that, because of the absence of more direct evidence of the value of the installed circuitry and, more important, because the contract price was so remarkably low (about two-thirds of the bid of defendant’s usual electrical subcontractor), contract price less certain adjustments is a fair mechanism for fixing the quantum of unjust enrichment in this case. The reasonable value of plaintiff’s performance^ — -to which alone plaintiff is entitled on the theory that otherwise defendant would be unjustly enriched, La. C.C. 1965 — would necessarily exceed that concededly low contract price less adjustments for defects.

We also agree with defendant that the correct measure of reduction of the price of a defectively performed contract would ordinarily be the cost of curing defects. There can be, however, a serious problem of unjust enrichment when the “defect,” howsoever pervasive, is a noncompliance in a nonessential term and the obligee elects not to cure the defect yet wants credit for the cost of cure. Suppose a painter contracts to paint a house yellow, or with a certain quality paint, but paints it white, or with a different quality: can the owner both (1) elect not to repaint and (2) refuse to pay on the ground that the cost to repaint equals the contract price? Or suppose a builder agrees to build a house with a specified color or quality brick exterior and builds with another brick: could the owner elect to keep the wrong brick and also claim credit for the cost of rebricking? Would such an owner not be taking the benefit of the contractor’s work and material without paying its reasonable value? Is that not unjust enrichment? If we add that the contractor had deliberately used the wrong brick, does that aggravating circumstance change the fundamental unfairness of keeping the substitute work without paying for it? Does that circumstance make the enrichment not unjust?

Our situation is similar to the case last supposed in some respects. The contractor and apparently the owner, working with a cost-plus contract, having concluded that certain circuits were specified at a higher amperage than necessary, have elected to keep the lower-amperage wiring supplied for certain circuits (changing only their circuit-breakers); yet the contractor asks credit for the cost of replacing the wiring. Perhaps it is fairer to say that the contractor asks that the subcontractor be denied recovery because of deliberately using aluminum instead of twice-as-expensive copper in a calculated and substantial breach of contract.

We reply that the choice of remedy was the contractor’s. The contractor might have elected the equivalent of performance of the contract, by replacing all circuitry to upgrade it to specifications and deducting the reasonable cost of replacement from the contract price. But our cost-plus contractor (apparently with the consent of the owner) elected instead to forego performance of the contract by electing to retain many of the circuits the subcontractor supplied that are substantially below contract specifications. The result may well be that the contractor did not owe the contract price because of the subcontractor’s substantial breach; but it does owe the reasonable value of the subcontractor’s retained work because otherwise it (or the owner) would be unjustly enriched. It is just that an owner should have, and pay only once for, work that he has contracted for, and thus he does not pay for both the original misperformed work and the redoing of it. It is thus just that the loss of the misperformed work fall on the misperformer. But it is not just, if an owner elects to keep the misperformed work, that he should not pay at all, not for the misperformed (but accepted) work and [739]*739not for redoing it (because he does not have it redone). It is not just that the misper-former be charged with the loss of the misperformed work when there is no loss. The same considerations exist as to the 94 circuits plaintiff agreed to wire with copper wire but deliberately wired instead with copper-clad aluminum. We therefore conclude that defendant contractor (who is being paid cost-plus by the owner, who in turn receives the benefit of plaintiff’s work) must pay the reasonable value of plaintiff’s retained work, and is not entitled to credit for the cost of redoing work that was not and is not to be redone.

The evidence in the record is not wholly satisfactory for a determination of the reasonable value of the retained work. One who contracted for a copper 20-ampere circuit but receives an aluminum 15-ampere circuit is not enriched by the contract price less the difference in cost of the wire. That measure would give the bad performer a great percentage profit than the good performer. The contract price includes an element for overhead and profit usually based on a percentage of total cost of labor and material; thus, for example, 20% for overhead and profit would add $200 to a price based on $1,000 cost of copper wire, but only $100 to the $500 cost of the much cheaper aluminum wire. If the bad performer retained the $200, he would make 40% on the $500 instead of the 20% bargained for. Thus the subcontractor is not only not entitled to the price of copper, but also not entitled to overhead and profit percentages applied to the price of copper.

In our case we conclude that, because the original contract price here was already as low as one could hope to find, the elimination of the extra cost of copper or other wire specified but not provided (including extra overhead and profit) brings the price down to a price that any reasonable party would pay for the lower-capacity, aluminum-wired circuits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul M. Davison, Etc. v. Lt Brown, Etc.
364 So. 2d 583 (Supreme Court of Louisiana, 1978)
Louisiana Power & Light Co. v. Smith
343 So. 2d 367 (Louisiana Court of Appeal, 1977)
Succession of Butler
294 So. 2d 512 (Supreme Court of Louisiana, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
369 So. 2d 736, 1979 La. App. LEXIS 3636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/veterans-electrical-service-inc-v-robley-j-gelpi-sons-inc-lactapp-1979.