Vermillion Construction Co. v. Fidelity & Deposit Co. of Maryland

526 S.W.2d 744, 1975 Tex. App. LEXIS 3028
CourtCourt of Appeals of Texas
DecidedAugust 29, 1975
Docket976
StatusPublished
Cited by19 cases

This text of 526 S.W.2d 744 (Vermillion Construction Co. v. Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vermillion Construction Co. v. Fidelity & Deposit Co. of Maryland, 526 S.W.2d 744, 1975 Tex. App. LEXIS 3028 (Tex. Ct. App. 1975).

Opinion

*745 OPINION

NYE, Chief Justice.

This case involves a claim by a subcontractor against the general contractor for payment of extra work performed. The subcontractor’s bonding company, Fidelity & Deposit Company of Maryland brought suit originally for a declaratory judgment against various defendants, including the general contractor and its bonding company, Aetna Casualty & Surety Company, for a declaration as to the amount and validity of the claims of various defendants, including the subcontractor CRM Contractors, Inc. for which Fidelity might be liable. Fidelity sought a determination of whether there existed in fact an oral agreement between CRM and the general contractor that would require the general contractor to pay additional compensation for the extra work done by CRM.

Trial was before a jury which answered certain special issues in favor of the subcontractor CRM. The jury found that there was a subsequent oral agreement entered into between CRM and the general contractor Vermillion Construction Company (hereinafter called Vermillion) whereby Vermillion would pay CRM a reasonable price for doing the extra work. The jury found that $18,093.00 was a reasonable sum for the extra work. Vermillion and its bonding company Aetna have duly perfected their appeal to this Court.

The construction site upon which the subject of the controversy arose is known as the “Harbor Oaks Subdivision” and is located near Rockport, Aransas County, Texas. The owner of the land was Canoe Lake Corporation. The engineer on the job was Urban Engineering. The project site was ultimately to consist of a Venetian type water oriented subdivision with three (3) peninsulas or fingers of land extending from the shoreline into a salt water lake. Upon each of the peninsulas, lots were to be located around the edge with a street down the middle. Around the edge of the three peninsulas were to be placed concrete bulkheads. Between the peninsulas the water was dredged and the spoil was placed on the peninsulas. This accomplished two purposes: to deepen the water and to provide for some fill material on the subdivision site. Vermillion, who specialized in concrete bulkheads, was awarded the contract for a total bid of $292,191.08 for the water front and lot improvements.

Thereafter, Vermillion entered into a subcontract with CRM to do a portion of the work relating to the building of streets, curbs, gutters and to grade and level the lots within the subdivision. CRM’s bid was $61,589.62. Prior to the subcontract being entered into between Vermillion and CRM, Mr. Charles Vermillion and Mr. Charles McGuire, (the principal owner of CRM) visited the project site in order to examine the area and to describe CRM’s subcontract work. While at the project site, their discussion centered around problems which might be encountered by CRM in leveling and grading the lots. One problem discussed in particular was the necessity of obtaining sufficient dirt to raise the lots to the proper height in case some of the lots settled to an elevation below that required by the plans and specifications. The three peninsulas which were formed were made up of hydraulic fill material which in essence was dredged material. This material has a tendency to settle after being compacted. Once the fill material has become compacted, it would require additional dirt placed on top of it to bring it to the required elevation. CRM’s main concern in determining its bid amount was whether the dirt removed from the excavation of streets would be sufficient to compensate any settling of the land. After reviewing the job site, McGuire and Vermillion both agreed that the dirt removed from the street would be in sufficient quantity to take care of any settling of the lots. At the pre-bid conference which was attended by Vermillion, the owner, and the engineer, the subject of the fill material was again discussed. It was anticipated that the fill material would settle to such an extent that *746 approximately 14,000 to 16,000 eubie feet of dirt would be required to raise the lots to the required elevation. It was the consensus of those in attendance that the surplus dirt from the excavation of the streets would be sufficient to take care of the settling.

CRM then moved onto the job site and began job operations. Within a week after CRM had moved onto the job site, it was discovered by Vermillion that the required length and width of each of the peninsulas in question were too short and did not conform to the plans and specifications. Vermillion determined that additional dirt was necessary to extend the peninsulas so that .they could get their machinery out far enough to install the concrete bulkheads in the water. After some of the bulkheads were placed in the water at their correct locations, they were a considerable distance from the peninsula land area. It was then discovered that it was necessary to bring in additional dirt to extend the peninsula shoreline to the bulkheads.

In order to alleviate this problem, Vermillion instructed CRM to haul the dirt which was removed from the street excavation to the end of the peninsula for the purpose of filling in and extending the length of such lots. CRM objected to this for the reason that if they were required to use the dirt that was removed from the street excavation, they would not have sufficient dirt for leveling and grading the lots to the required elevation as required in CRM’s subcontract. CRM stated that supplying this additional dirt to extend the peninsula area to the bulkheads was not a part of their job under their contract.

After some discussions, Vermillion agreed with CRM that the hauling of dirt to be placed at the end and the sides of the peninsulas was not a part of CRM’s contract. Therefore, Vermillion wrote a letter to Urban Engineering concerning the dirt shortage. The letter reads in part as follows:

“As you know at the pre-bid conference, the subject, ‘Settling of Fill Material’, was an item of discussion. Therefore, after the conference we anticipated a settlement of fill area to the extent of approximately 14-16000 cu. yds., to be obtained from excavation of street and other areas above specified grades. We have moved this dirt and placed it, not on the lots, as stated at pre-bid conference, because of settling of material, but on the ends of the fingers where the water ranged from -8' to -9½' deep at the bulkhead line, 18' - 30' out from waters edge. None of the shortage of length or over cutting was mentioned at the conference. None of the other bidders anticipated it would be necessary to measure the length at the fingers or verify any other widths or lengths on the plans. We certainly didn’t.”

CRM contended that an oral agreement was then reached between CRM and Vermillion whereby Vermillion agreed to pay or see to. it that CRM was paid for the additional work on the cost plus profit basis. Vermillion denies that any such oral agreement was ever entered into between it and CRM. In the meantime, CRM began removing the dirt from the street excavation for the purpose of extending the peninsulas to the bulkheads. Finally, CRM sent a detailed invoice to Vermillion which included the charges for the additional extra work in the amount of $18,093.00. Vermillion refused to pay any part of the charges claiming that there never was any agreement between it and CRM to do the additional extra work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Labaj v. VanHouten
322 S.W.3d 416 (Court of Appeals of Texas, 2010)
Barrand, Inc. v. Whataburger, Inc.
214 S.W.3d 122 (Court of Appeals of Texas, 2006)
Coastal Mart, Inc. v. Southwestern Bell Telephone Co.
154 S.W.3d 839 (Court of Appeals of Texas, 2005)
Frost National Bank v. L&F Distributors, Ltd.
Court of Appeals of Texas, 2003
Frost National Bank v. L & F Distributors, Ltd.
122 S.W.3d 922 (Court of Appeals of Texas, 2003)
Guthrie v. Republic National Life Insurance Co.
682 S.W.2d 634 (Court of Appeals of Texas, 1984)
Montgomery Ward & Co. v. Garza
660 S.W.2d 619 (Court of Appeals of Texas, 1983)
O'Shea v. Coronado Transmission Co.
656 S.W.2d 557 (Court of Appeals of Texas, 1983)
Aztec Services, Inc. v. Quintana-Howell Joint Venture
632 S.W.2d 160 (Court of Appeals of Texas, 1982)
McElreath v. McElreath
542 S.W.2d 206 (Court of Appeals of Texas, 1976)
Nixon v. First State Bank of Corpus Christi
540 S.W.2d 817 (Court of Appeals of Texas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
526 S.W.2d 744, 1975 Tex. App. LEXIS 3028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vermillion-construction-co-v-fidelity-deposit-co-of-maryland-texapp-1975.