Ventana Condominium Association, Inc. v. Chancey Design Partnership, Inc.

203 So. 3d 175, 2016 Fla. App. LEXIS 12173
CourtDistrict Court of Appeal of Florida
DecidedAugust 12, 2016
Docket2D15-1803
StatusPublished
Cited by9 cases

This text of 203 So. 3d 175 (Ventana Condominium Association, Inc. v. Chancey Design Partnership, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ventana Condominium Association, Inc. v. Chancey Design Partnership, Inc., 203 So. 3d 175, 2016 Fla. App. LEXIS 12173 (Fla. Ct. App. 2016).

Opinion

BLACK, Judge.

Ventana Condominium Association, Inc., challenges the final summary judgment in favor of Chaneey Design Partnership, Inc., Gregory Jones, and Elliott Wheeler. 1 Because the trial court erred in determining that no issues of material fact were in dispute and erred in applying the law, we reverse and remand for further proceedings.

I. History

Ventana Tampa, LLC, the developer, contracted with Hardin Construction Company, LLC, and Chaneey Design to build the condominium. Issues with delays and additional costs arose, and Ventana Tampa (the Developer) entered into a Mediated Settlement Agreement (MSA) with Hardin whereby Hardin was given authority to take action on behalf of the Developer against Chaneey Design. The MSA provided that it was binding upon the parties’ successors, assigns, and all those holding title under them. The Developer did not assign its interests in the claims or the claims themselves to Hardin via the MSA.

Hardin sued Chaneey Design in July 2008 in its own right and on behalf of the Developer. 2 During the pendency of the suit the development was foreclosed upon, and as stated in the foreclosure settlement agreement, the Developer was required to execute an assignment of its interests in any litigation between it and Hardin and Chaneey Design. The assignee was Mercantile Bank. The final judgment of foreclosure did not reference an assignment of interests in litigation, nor did the judgment incorporate the settlement agreement.

Mercantile Bank subsequently assigned the foreclosure judgment to BMR Funding, LLC. The assignment to BMR did not reference the assignment of any interests in the litigation from the Developer to Mercantile Bank. BMR executed an “agency authority” stating that BMR was “the successor assignee and real party in interest to, among other things, the direct (‘brick and mortar’) claims” in the lawsuit between Hardin and Chaneey Design. In February 2010 Hardin and Chaneey Design entered into a confidential settlement agreement, and in May 2010 Hardin — for itself and BMR — and Chaneey Design executed a general release (the Release). The Release provided, in part: •'

Hardin, for itself, its agents, representatives, beneficiaries, heirs, successors, creditors, assigns, and executors, hereby fully, completely and forever releases and discharges Chaneey [Design] ... from and against any and all past and present losses, liabilities, responsibilities, demands, obligations, actions, causes of action, rights, judgments, damages, compensation of any kind, expenses (including attorneys’ fees and costs), and claims whatsoever, in law or in equity, arising out of .the facts and circumstances raised in the [lawsuit].
BMR, for itself, its agents, representatives, beneficiaries, heirs, successors, creditors, assigns, executors, entities, companies and any entities or persons in privity with them, hereby fully, completely and forever releases and dis *178 charges Chancey [Design] ... from and against any and all past and present losses, liabilities, responsibilities, demands, obligations, actions, causes ■ of action, rights, judgments, damages, compensation of any kind, expenses (including attorneys’ fees and costs), and claims whatsoever, in law or in equity, arising out of the facts and circumstances raised in the [lawsuit].

The lawsuit was dismissed in June 2010. In July 2010 Ventana Condominium Association obtained operation, control, and duty of maintenance through turnover from the Developer. The Association filed the current lawsuit in 2014,.alleging design defects with regard to the “amenities deck,” The Association sued Chancey Design, Gregory Jones, and Elliott-Wheeler (the Chancey Defendants) 3 and Hardin.

II. Summary Judgment

The Chancey Defendants filed their motion for summary judgment on December 17, 2014, arguing that the Association is a successor to BMR, who — through Hardin — entered into the Release with Chan-cey Design, and that the Association’s claims are the same amenities deck claims which were resolved and released in the prior lawsuit.

At the hearing, the Association argued that in the motion for summary judgment the Chancey Defendants admitted “the Amenities Deck was redesigned and constructed prior to substantial completion of the [condominiums]. Ventana, as owner/developer, accepted the redesigned and constructed Amenities Deck.” The Association argued that the defects now at issue are construction defects and/or defects of the redesign and construction, not the original defects which resulted in the redesign and construction; that the Release is ambiguous; and that the Release did not expressly state it covered unknown claims arising out of the construction. The Chan-cey Defendants responded that the new lawsuit is premised on the same design defects resolved in the prior suit regardless of “whether it fixed the issue, whether Hardin didn’t do the right work, [or] whether the [Developer] didn’t put the money in to do it.”

At the end of the hearing, the court found “based upon the record evidence that’s been submitted, that Ventana Condominium Association is bound by the [R]elease entered into on behalf of the [Developer] at the time of the prior lawsuit” and granted the motion for summary judgment:

Plaintiff, the Ventana Condominium Association, is the successor in interest to Ventana Tampa, LLC, the prior owner of Ventana. Ventana Tampa, LLC[,] previously assigned its interests in claims concerning the Ventana building design defects to Hardin Construction Company. These claims were settled and [the Release] signed in Case No. 08-CA-014505. Because of an identity in interest and identity in claims, the court finds plaintiff is bound by the [confidential] settlement agreement and [the Release].

III. Analysis

A. The Association and the Developer

In the order granting the motion for summary judgment the court found that the Association is the successor in interest to. the Developer and that the Developer had assigned its interest in the claims against Chancey Design to Hardin. The *179 court further found that the claims against Chancey Design were settled and that the Release has been executed.

1. Applicable statutes

“A condominium is created by recording a declaration in the public records of the county where the land is located, executed and acknowledged with the requirements for a deed.” § 718.104(2), Fla. Stat. (2014). “The declaration must contain or provide for ... [t]he name of the association, which must be a corporation for profit or a corporation not for profit,” and “[t]he document or documents creating the association.” § 718.104(4)(i), (k). The association, therefore, is created at the same time that the condominium is created by virtue of the declaration of condominium and documents creating the association being recorded together. See also

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lassen v. Dolphin Tower Condominium Association, Inc.
District Court of Appeal of Florida, 2025
MBlock Investors, LLC v. Bovis Lend Lease, Inc.
274 So. 3d 504 (District Court of Appeal of Florida, 2019)
Blakeley v. Livorsi
269 So. 3d 673 (District Court of Appeal of Florida, 2019)
PETER M. BLAKELEY v. MICHAEL T. LIVORSI
District Court of Appeal of Florida, 2019
CHARLES W. GRIMES & BRENDA GRIMES v. KEVIN R. LOTTES
241 So. 3d 892 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
203 So. 3d 175, 2016 Fla. App. LEXIS 12173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ventana-condominium-association-inc-v-chancey-design-partnership-inc-fladistctapp-2016.