Venice v. Frazier Davis Const. Co.

87 F. Supp. 475, 1949 U.S. Dist. LEXIS 2057
CourtDistrict Court, Canal Zone
DecidedDecember 23, 1949
DocketCiv. A. No. 3048
StatusPublished
Cited by2 cases

This text of 87 F. Supp. 475 (Venice v. Frazier Davis Const. Co.) is published on Counsel Stack Legal Research, covering District Court, Canal Zone primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Venice v. Frazier Davis Const. Co., 87 F. Supp. 475, 1949 U.S. Dist. LEXIS 2057 (canalzoned 1949).

Opinion

HANCOCK, District Judge.

This action was instituted by plaintiff Venice against Frazier Davis Construction Company and MacDonald Construction Company to enforce payment under a written contract wherein the use of steel beams was rented, and as claimed, that contrary to such contract some of the steel was not returned and other steel was returned in a damaged and unusable condition.

The defendant Frazier Davis Construction Company is not before the Court by process or appearance, and the proceedings have been prosecuted alone against the MacDonald Construction Company. Prior to November 10, 1947, the MacDonald Construction Company, hereafter referred to as defendant, was engaged in erecting a culvert in the bed of Rio Curundu River. This culvert was 20 feet wide and 11 feet deep. The territory through which this excavation was being dug for the culvert was composed of a type of soil known as “sea mud”, necessitating the erection and use of a cofferdam constructed of metallic piling along the sides to prevent the banks of sludge from sliding or caving in.

During the process of the work and prior to November 10th, 1947, defendant discovered that the pressure of the sludge was too great for the metallic piling. Bracing of this metallic piling was then resorted to by placing steel beams as supports to each side of cut and against metallic piling. This was not sufficient to withstand the pressure of the sludge, for the pressure was too great for the strength of the steel beams then being used. To correctly describe the impending conditions, we refer to the language of defendant’s superintendant who was in charge of the undertaking. On Page 77, Transcript of Testimony, the superintendant stated: “I had shipped down $8000.00 of beams from the United States, brand new beams, in the hope that they would be sufficient. There is no actual way of calculating the pressure in the sea mud. We weighed it, we found it to weight 90 pounds to the cubic foot, but that meant nothing because it was unstable * * *. We installed some of the beams that we brought down, and subsequent to that date (October 25, 1947) they failed. They were absolutely crushed by the pressure.”

Defendant being confronted with these difficulties sought other means of obtaining bracing sufficient to resist this pressure. Plaintiff at that time owned and had stored at Paraíso, four structures referred to as trusses, and one bridge.

There is some controversy relative to negotiations between the Superintendant of defendant and plaintiff prior to execution of contract, of which issue there will be no reference. To refer to such would serve no purpose or assistance in determining the issues in this controversy.

Plaintiff and defendant’s Superintendent went to “Paraíso” where these four trusses and bridge were located. These four structures were composed of steel beams fastened together with bolts and rivets, and one bridge, 105 feet long and 20 feet wide, likewise was composed of steel beams and bolted and riveted together. Defendant’s Superintendant made measurements to get the dimensions of the steel constituting these structures. He ascertained that some of the steel beams were 8 inch at 33 pounds, and others 8x13 “H” beams. The Superintendant then advised plaintiff that defendant would not be interested in the use of the steel beams, as defendant desired beams that would be economical in weight and easily handled; that the beams contained in the structures or struts of plaintiff were big and awkward, and that defendant did not want them.

Soon thereafter a Mr. Wyatt, defendant’s Manager, came to the Canal Zone, and while he was here a second failure of the cofferdam bracing took place. Up to that time all bracing theretofore used had been the steel which defendant had purchased in the United States, to be used for bracing.

•The Manager, Wyatt, upon the second failure, directed defendant’s Superintend-ant to contact plaintiff and rent the use of the steel contained in the four trusses and bridge belonging to plaintiff, the Manager and Superintendant realizing that the [478]*478Steel contained in the trusses and bridge of plaintiff could be obtained faster than they could be obtained in the States. The Superintendant contacted plaintiff, Venice, and the Superintendant and Mr. Wyatt prepared contract which was signed “MacDonald Construction Company, hy E. H. Kersting, individually and as General Superintendant”, and by the plaintiff Venice, on November 10th, 1947. The contract contained seven separate paragraphs, as follows:

“1. You certify that the five (5) steel spans are your property, without lien or claim against them.
“2. Steel is to be rented to us for use principally as cofferdam bracing during, the entire construction period of the Rio Curundu River Culvert.
“3. We are to move the five (5) steel spans from their present position to a location' accessible by road, at our expense.
“4. We are to disassemble the trusses and haul to our yard at our expense. We are to stand all expenses of disassembling trusses.
“5. We are to pay you as rental on such steel as we take from the trusses the sum of two thousand five hundred dollars ($2500.00), same to be complete and full payment for rental for the period necessary to complete our contract for the Rio Curundu Culvert.
“6. At the completion of the rental period, we are to turn over to you at your yard in Panama City all steel in good condition, less ordinary wear and tear inherent to such type of work.
“7. All steel we are unable to return we are to pay you at the price of $59.00 per ton.”

After the above contract was executed, deféndant moved the trusses and bridge across the Canal from Paraíso, to the West Bank of Cocoli, and the disassembling was begun.

The weight of the steel contained in these trusses and bridge was not known, and no weight was mentioned or estimated or obtained. The contract between plaintiff and defendant was prepared by the representatives of the defendant, in which a rental price for the use of such steel was provided, and in addition to the rental price was a proviso that for any steel not returned, a price of $59.00 per ton was to be paid to plaintiff by defendant. It was the understanding between the contracting parties that the trusses and bridge were to be disassembled, and the steel obtained through such disassembling was to be used as bracing for the cofferdam.

Defendant’s Superintendant was in a better position to know, and at the time this contract was prepared, did know, the strain to which the steel contracted for would be subjected. He had experienced the failure of the steel obtained from the States to withstanding the existant pressure to which the bracing would be subjected. He knew the dimensions of the steel contained in the trusses and bridge of plaintiff, and it is reasonable to believe that defendant’s representative did know that some of the steel obtained from plaintiff would be lost, or its usable condition destroyed. In view of that expected loss, the provision for payment of unreturned steel was made. Defendant’s Superintendant admits that some of this steel was lost and the usable condition of other steel was destroyed. On page 88 of Transcript of Record the Superintendant stated: “I delivered every bit that I had received, minus a few pieces that I was ashamed to send back.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LIGHT v. Lend Lease Transportation Co.
156 N.E.2d 94 (Indiana Court of Appeals, 1959)
Terminal Warehouse v. United States
101 F. Supp. 937 (D. New Jersey, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
87 F. Supp. 475, 1949 U.S. Dist. LEXIS 2057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/venice-v-frazier-davis-const-co-canalzoned-1949.