Velsicol Chemical Corp. v. Enenco, Inc.

9 F.3d 524, 1993 WL 462512
CourtCourt of Appeals for the Sixth Circuit
DecidedNovember 12, 1993
DocketNos. 92-5579, 92-5580
StatusPublished
Cited by24 cases

This text of 9 F.3d 524 (Velsicol Chemical Corp. v. Enenco, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Velsicol Chemical Corp. v. Enenco, Inc., 9 F.3d 524, 1993 WL 462512 (6th Cir. 1993).

Opinion

ROBERT HOLMES BELL, District Judge.

This consolidated appeal brought by Velsi-col Chemical Corporation and the City of Memphis, Tennessee presents a number of fundamental questions concerning the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“CERC-LA”), as amended by the Superfund Amendments and Reauthorization Act of 1986 (“SARA”), 42 U.S.C. § 9601 et seq. At issue is whether the statute of limitations for a response cost recovery claim under CERC-LA § 107, 42 U.S.C. § 9607, enacted as part of SARA in 1986, should be retroactively applied to an accrued-but-not-yet-filed claim and whether the equitable defense of laches is available for a section 107 claim.

I.

Our examination of the record below reveals no serious dispute in the relevant facts and procedural history. We therefore summarize them briefly.

A.

The North Hollywood Dump is a landfill of about 70 acres near the Wolf River in Memphis, Tennessee. The Curry family and other individuals owned the Dump site, but allowed the City of Memphis (“City”) to operate it from 1930 to 1968.

During the City’s operation, the Dump was primarily used for the disposal of municipal refuse. Industrial and chemical wastes were also disposed of at the Dump. Velsicol Chemical Corporation (“Velsicol”) was one of the entities that disposed of its wastes at the site.

In 1979, the United States Environmental Protection Agency (“EPA”) began investigative studies of the Dump site. The studies revealed the presence of hazardous substances in the sediment and surface water. The EPA concluded that the contamination may have stemmed from the Dump-related activities.

In December 1980, Velsicol and the City, two of the “potentially responsible parties” (“PRPs”), joined forces with the EPA, the State of Tennessee, and the County of Shelby to form the Technical Action Group (“TAG”) to plan the cleanup of the Dump site. The TAG’s goal was to address both the short- and long-term problems caused by the contamination at the site. In February 1981, Velsicol and the City commenced some cleanup as part of the TAG’s activities. A remedial investigation/feasibility study (“RI/FS”)1 was conducted at the Dump site, which was by then a designated site on the National Priorities List (“NPL”).2 Certain other activities — including the excavation and disposal of contaminated soils, the placement of clean imported fill, and the installation of a cover over some parts of the Dump site— occurred. By 1984, a regional office of the EPA, after reviewing the TAG’s RI/FS, issued a “Record of Decision” (“ROD”) to address the long-term cleanup needs for the site.

In February 1985, however, the EPA headquarters rejected the ROD for the Dump site. Issuing a “notice of deficiencies” to the PRPs (Velsicol and the City), the EPA headquarters required the completion of additional investigations and studies. In May 1990, Velsicol and the City submitted the “Supplemental RI/FS” to the EPA.

[527]*527In September 1990, the regional office of the EPA issued the final ROD. The ROD set forth the long-term remedial measures for the Dump site. Velsicol and the City then agreed with the EPA to comply with that ROD.

B.

Meanwhile, as the foregoing cleanup efforts were continuing, Velsicol and the City became embroiled in CERCLA response cost litigation.

In 1983, W.J. Curry & Son, Realtors, then owner of the Dump site, brought a state court tort action against Velsicol for damages allegedly caused by the disposal of hazardous substances at the Dump site. After removal to federal court, Velsicol was granted leave to file third party complaints against several other parties, including Eneneo, Inc. (“Enen-co”) and Browning-Ferris Industries of Tennessee, Inc. (“BFI”), in 1986 and 1988. The third-party complaints alleged that Eneneo and BFI, among others, were also PRPs of the contamination that occurred at the Dump site and sought CERCLA response cost recovery (pursuant to 42 U.S.C. § 9607(a)) and contribution (pursuant to 42 U.S.C. § 9613(f)) from them.

On June 2, 1989, the district judge in that case dismissed Velsicol’s claims against En-enco and BFI for untimeliness. The district court found that Velsicol’s delay in raising these claims was unjustifiable and unduly prejudicial to the original plaintiff and the third party defendants. The district court’s order mentioned neither the statute of limitations nor the doctrine of laches.

On June 22,1989, Velsicol commenced this action. Not unlike the third-party complaints in the dismissed action, Velsicol alleged that Eneneo, BFI and others disposed of their wastes containing hazardous substances at the Dump site and thus should be liable for response costs. Velsicol brought cost recovery and contribution claims under CERCLA against them.

In October 1989, in Velsicol’s action, Enen-co and BFI then moved to dismiss Velsicol’s complaint or, in the alternative, for summary judgment, arguing that the statute of limitations, CERCLA § 113(g), 42 U.S.C. § 9613(g), and the doctrine of laches barred Velsicol’s claims. On April 4, 1991, the City also filed its motion to intervene as a party plaintiff to the Velsicol action.

After reassignment of the ease, another judge heard oral arguments on the motions on January 21, 1992. The district court, treating Enenco’s and BFI’s motions as summary judgment motions, granted them from the bench. Velsicol’s cost recovery and contribution claims were dismissed on the grounds of statute of limitations and laches. The district court also orally denied the City’s intervention motion as untimely. These rulings were subsequently formalized in an order.

Velsicol and the City requested reconsideration of the order. The district court issued another order denying their request. In that order, however, the court clarified the ground for dismissal of Velsicol’s contribution claim; the order stated that the contribution claim could not be maintained in light of the dismissal of the cost recovery claim.

Velsicol and the City now appeal from these orders.

II.

Velsicol argues that the district court erroneously concluded that the cost recovery claim against Eneneo and BFI was time-barred. Velsicol also requests reinstatement of its contribution claim. Finally, the City argues that it should have been allowed to intervene into Velsieol’s action. We address each argument in turn.

Velsicol contends that the district court erred as a matter of law by granting summary judgment in favor of Eneneo and BFI on Velsicol’s cost recovery claim under section 107(a) of CERCLA. According to Velsi-col, the claim was barred neither by the statute of limitations nor the doctrine of lach-es.

We begin our consideration of this argument by reciting the standards governing our review of the district court’s grant of sum[528]*528mary judgment. This Court applies de novo

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ESTATE OF MARTHA HARRISON BANE v. JOHN BANE
Court of Appeals of Tennessee, 2025
Lynette Hathon v. State of Michigan
Michigan Supreme Court, 2024
Matthew Schafer v. Kent County
Michigan Supreme Court, 2024
James L. Coxwell ex rel v. Watco Communities LLC
Court of Appeals of Tennessee, 2023
Mellinger v. Braithwaite
W.D. Washington, 2020
In Re Estate of Karen Klyce Smith
Court of Appeals of Tennessee, 2018
Donna Shedd v. Community Health Systems, Inc.
Court of Appeals of Tennessee, 2010
Martin v. Correction Corp. of America
231 F.R.D. 532 (W.D. Tennessee, 2005)
United States v. Chrysler Corp.
157 F. Supp. 2d 849 (N.D. Ohio, 2001)
Sherwin-Williams Co. v. Artra Group, Inc.
125 F. Supp. 2d 739 (D. Maryland, 2001)
American Materials Technologies, LLC v. City of Chattanooga
42 S.W.3d 914 (Court of Appeals of Tennessee, 2000)
In Re Eagle-Picher Industries, Inc.
197 B.R. 260 (S.D. Ohio, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
9 F.3d 524, 1993 WL 462512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/velsicol-chemical-corp-v-enenco-inc-ca6-1993.