Velocity Constr. Servs., L.L.C. v. Ohio State Univ.

2019 Ohio 3267
CourtOhio Court of Claims
DecidedJuly 29, 2019
Docket2018-01500JD
StatusPublished

This text of 2019 Ohio 3267 (Velocity Constr. Servs., L.L.C. v. Ohio State Univ.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Velocity Constr. Servs., L.L.C. v. Ohio State Univ., 2019 Ohio 3267 (Ohio Super. Ct. 2019).

Opinion

[Cite as Velocity Constr. Servs., L.L.C. v. Ohio State Univ., 2019-Ohio-3267.]

VELOCITY CONSTRUCTION Case No. 2018-01500JD SERVICES, LLC. Referee Dale A. Crawford Plaintiff/Counter Defendant

DECISION OF THE REFEREE v.

THE OHIO STATE UNIVERSITY

Defendant/Counter Plaintiff

{¶1} This case is before the Court on a complaint brought by Plaintiff/Counter Defendant Velocity Construction Services (Velocity) for breach of contract and unjust enrichment. Defendant/Counter Plaintiff Ohio State University (OSU) filed a counterclaim alleging breach of contract, breach of express warranties, and fraud. On June 12, 2019, OSU moved for summary judgment on the liability portion of its counterclaim for fraud. Velocity did not file a response, and the Referee considers the motion unopposed. For the reasons set forth below, the Referee recommends the court grant OSU’s motion. Standard of Review {¶2} Motions for summary judgment are reviewed under the standard set forth in Civ.R. 56(C), which states, in part: Summary judgment shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, written admissions, affidavits, transcripts of evidence, and written stipulations of fact, if any, timely filed in the action, show that there is no genuine issue as to any material fact and that the moving party is entitled to summary judgment as a matter of law. No evidence or stipulation may be considered except as stated in this rule. A summary judgment shall not be rendered unless it appears from the evidence or stipulation, and only from the evidence or stipulation, that Case No. 2018-01500JD -2- DECISION

reasonable minds can come to but one conclusion and that conclusion is adverse to the party against whom the motion for summary judgment is made, that party being entitled to have the evidence or stipulation construed most strongly in the party’s favor. “[T]he moving party bears the initial responsibility of informing the trial court of the basis for the motion, and identifying those portions of the record before the trial court which demonstrate the absence of a genuine issue of material fact on a material element of the nonmoving party’s claim.” Dresher v. Burt, 75 Ohio St.3d 280, 292, 662 N.E.2d 264 (1996). To meet this initial burden, the moving party must be able to point to evidentiary materials of the type listed in Civ.R. 56(C). Id. at 292-293. {¶3} If the moving party meets its initial burden, the nonmoving party bears a reciprocal burden outlined in Civ.R. 56(E), which states, in part: When a motion for summary judgment is made and supported as provided in this rule, an adverse party may not rest upon the mere allegations or denials of the party’s pleadings, but the party’s response, by affidavit or as otherwise provided in this rule, must set forth specific facts showing that there is a genuine issue for trial. If the party does not so respond, summary judgment, if appropriate, shall be entered against the party. Factual Background {¶4} This case involves three separate contracts between Velocity and OSU for construction projects on buildings owned by OSU. (Velocity Complaint at ¶ 2-4; OSU Counterclaim at ¶ 3, 5.) The parties entered into the contracts through purchase order agreements. (Velocity Complaint at ¶ 1-4; OSU Counterclaim at ¶ 5.) The first contract was for the renovation of the ballroom in Lawrence Tower, which primarily involved the design and installation of a new ceiling grid and ceiling tiles along with new lighting and controls (Lawrence Tower Project). (Velocity Complaint at ¶ 10; OSU Counterclaim at ¶ 8.) The second contract was for the installation of replacement windows in Fechko Case No. 2018-01500JD -3- DECISION

House, including the installation of new window frames and trim. (Fechko Window Project). (Velocity Complaint at ¶ 11; OSU Counterclaim at ¶ 23, Ex. B.) The third contract was for renovation of the heating, ventilating, and air conditioning (HVAC) system in Fechko House (Fechko HVAC Project). (Velocity Complaint at ¶ 12; OSU Counterclaim at ¶ 43, Ex. C.) All three contracts were terminated before any of the projects were completed. (Velocity Complaint at ¶ 26, 32, 41; OSU Counterclaim at ¶ 18, 39, 66.) The parties’ respective pleadings offer competing accounts of the events leading up to the terminations. {¶5} On February 15, 2019, OSU served Velocity with a set of discovery requests, including a request for admissions. Velocity failed to respond to the request for admissions, despite the fact that OSU agreed to multiple extensions of Velocity’s response deadline. Consequently, the Referee deemed the matters set forth in the requests for admissions to be admitted pursuant to Civ.R. 36(A)(1). (Order of the Referee, July 12, 2019.) As a result, the following facts are in evidence: (1) Velocity was required to use new material on the Lawrence Tower Project. (2) Velocity, and/or its subcontractors, installed work on the Lawrence Tower Project which did not use new material, specifically the ceiling grid. (3) Velocity knew that it was installing used materials, specifically the ceiling grid, on the Lawrence Tower Project and billed for new material. (4) Velocity installed incorrectly sized ceiling tiles on the Lawrence Tower Project. (5) Velocity never returned to the Lawrence Tower Project to re-install the correctly sized ceiling tiles on the Lawrence Tower Project. Case No. 2018-01500JD -4- DECISION

(6) Velocity failed to install new wiring as required for the plans and specifications, for the new lighting system in the Lawrence Tower Project. (7) The specifications on the Fechko Window Project required that the wood trim be pre-stained prior to installation. (8) Velocity did not pre-stain the wood trim on the Fechko Window Replacement Project prior to installation. (9) Velocity did not install new electrical service from the panel to the air conditioning units on the Fechko HVAC Project. (10) Velocity specifically represented to OSU personnel that it had installed new electrical service from the panel to the air conditioning units on the Fechko HVAC Project. (11) Velocity abandoned its work on the Fechko HVAC Project. (12) Velocity abandoned its work on the Fechko Window Project. (Motion for Summary Judgment, Ex. A-1 at 4-6.) On the basis of these admissions, OSU now moves for summary judgment on its claim for fraud. (Motion for Summary Judgment at 4-5.) Law and Analysis {¶6} At the outset, the Referee notes that OSU’s motion for summary judgment is unopposed. “The failure to respond to a motion for summary judgment does not in and of itself mandate the granting of summary judgment in favor of the moving party.” Thompson v. Pingue Properties, 10th Dist. No. 9APE07-881, 1996 Ohio App.LEXIS 1346, 6 (March 29, 1996). However, by failing to respond, the nonmoving loses the ability to contest the truth of the matters asserted in the moving party’s Civ.R. 56 evidence. Id. Furthermore, “[a] litigant who fails to respond to a motion for summary judgment ordinarily may not later litigate the issues that could have been raised in the motion. If allowed, such practice would undermine the purposes of Civ.R. 56 and 60(B) Case No. 2018-01500JD -5- DECISION

and create a ready avenue for delay.” Tankersely v. Scales, 2d Dist. Montgomery No. 26299, 2004-Ohio-4964, ¶ 19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berger v. Wade
2014 Ohio 1262 (Ohio Court of Appeals, 2014)
Turtutici Family Trust v. Carey
2012 Ohio 6191 (Ohio Court of Appeals, 2012)
Crown Property Development, Inc. v. Omega Oil Co.
681 N.E.2d 1343 (Ohio Court of Appeals, 1996)
Holt Co. of Ohio v. Ohio MacHinery Co., 06ap-911 (10-18-2007)
2007 Ohio 5557 (Ohio Court of Appeals, 2007)
Morrow v. Reminger & Reminger Co.
915 N.E.2d 696 (Ohio Court of Appeals, 2009)
Burr v. Board of County Commissioners
491 N.E.2d 1101 (Ohio Supreme Court, 1986)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 3267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/velocity-constr-servs-llc-v-ohio-state-univ-ohioctcl-2019.