Vecellio & Grogan, Inc. v. Piedmont Drilling & Blasting, Inc.

644 S.E.2d 16, 183 N.C. App. 66, 2007 N.C. App. LEXIS 837
CourtCourt of Appeals of North Carolina
DecidedMay 1, 2007
DocketCOA06-887
StatusPublished
Cited by8 cases

This text of 644 S.E.2d 16 (Vecellio & Grogan, Inc. v. Piedmont Drilling & Blasting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vecellio & Grogan, Inc. v. Piedmont Drilling & Blasting, Inc., 644 S.E.2d 16, 183 N.C. App. 66, 2007 N.C. App. LEXIS 837 (N.C. Ct. App. 2007).

Opinion

LEVINSON, Judge.

Plaintiff appeals from summary judgment entered in favor of defendants, and from an order granting defendant’s motion to quash its subpoena served on Forensic Analysis & Engineering Corporation. We reverse in part and dismiss in part.

The relevant facts are summarized as follows: Plaintiff, Vecellio & Grogan, Inc. (V&G), is a West Virginia corporation doing business as a general contractor on road construction contracts. In 2002 V&G was under contract with the North Carolina Department of Transportation (NCDOT) to construct part of a road improvement project for North Carolina Highway 64. The contract required V&G to install two below-ground sewer lines. These lines, designated Sewer Lines A and B, were parallel to each other and about thirty feet apart. Defendant, Piedmont Drilling & Blasting, Inc. (Piedmont), is a North Carolina corporation that provides drilling and blasting services. In October 2002 V&G executed a subcontract with Piedmont, wherein Piedmont agreed to drill and blast the trenches for Sewer Lines A and B. V&G subcontracted with another company to construct the actual sewer lines.

On 1 April 2003 Piedmont was blasting the trench for Sewer Line B. Sewer Line A was partially completed, and piping was installed between two points known as manholes 3 and 4. Piedmont set off an explosion in Sewer Line B which caused damage to both Sewer Lines A and B. The present appeal arises from V&G’s claim that Piedmont is liable for the damages resulting from its blasting in Sewer Line B.

*68 Following the explosion on 1 April 2003, the parties contacted Ranger Insurance Company (Ranger), the insurance company that had insured Piedmont. Ranger hired Forensic Analysis & Engineering Corporation (FAEC) to investigate the matter. On 13 May 2003 Ranger paid V&G $600,000 with a check marked “Advance Payment for Property Damages.” Neither Ranger nor Piedmont would pay V&G any more money, and on 24 November 2003 V&G filed suit against Piedmont and Ranger for damages not covered by Ranger’s advance payment check. V&G sought damages based on strict liability, negligence, breach of contract, and contractual indemnity; additionally, plaintiff sought a declaratory judgment regarding Ranger’s obligations. In an amended answer and counterclaim, Piedmont denied the material allegations of the complaint and brought a counterclaim for unpaid labor.

On 23 February 2004 V&G issued a subpoena to FAEC for documents pertaining to the blast. Ranger and Piedmont moved to quash the subpoena; their motions were granted by the trial court in August 2004. .

Ranger moved for summary judgment in July 2005. The parties agreed to entry of summary judgment, under the terms of which Ranger was ordered to provide coverage for all non-liquidated damages for which Piedmont was ultimately found liable. Ranger is not a party to this appeal.

In January 2006 V&G moved for partial summary judgment on the issue of liability, and Piedmont moved for summary judgment on all of plaintiff’s claims. By order entered 13 February 2006, the trial court granted Piedmont’s summary judgment motion, denied V&G’s summary judgment motion, and dismissed all of V&G’s claims. Thereafter, Piedmont dismissed its counterclaim, allowing V&G to appeal the trial court’s summary judgment order. Plaintiff also appeals the trial court’s order quashing its subpoena for FAEC.

Standard of Review

“Summary judgment is appropriate ‘if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that [a] party is entitled to a judgment as a matter of law.’ ” N.C. Gen. Stat. § 1A-1, Rule 56(c) (2005). “On appeal of a trial court’s allowance of a motion for summary judgment, we consider whether, on the basis of materials supplied to the trial court, there was a genuine issue of material fact and whether the moving party is *69 entitled to judgment as a matter of law. Evidence presented by the parties is viewed in the light most favorable to the non-movant.” Summey v. Barker, 357 N.C. 492, 496, 586 S.E.2d 247, 249 (2003) (citation omitted).

Strict Liability for Ultra Hazardous Activities

Plaintiff argues first that the trial court erred by dismissing its claim for damages based on defendant’s being strictly liable for damages caused by its blasting.

Plaintiff correctly asserts that blasting with explosives is deemed an “ultra hazardous” activity, for which strict liability is imposed. Insurance Co. v. Blythe Brothers Co., 260 N.C. 69, 131 S.E.2d 900 (1963). In Blythe, plaintiffs sought compensation for damages caused by defendant’s use of explosives to blast a tunnel for a sewer line. The Court held:

Blasting is considered intrinsically dangerous; it is an ultra-hazardous activity . . . since it requires the use of high explosives and since it is impossible to predict with certainty the extent or severity of its consequences.. . . “Blasting operations are dangerous and must pay their own way. . . . The principle of strict or absolute liability for extrahazardous activity thus is the only sound rationalization.”

Id. at 74, 117 S.E.2d at 904 (quoting Wallace v. A. H. Guion & Company (S.C.), 237 S.C. 349, 354, 117 S.E.2d 359, 361 (I960)) (citations omitted). North Carolina cases decided after Blythe have uniformly held that blasting is an ultra hazardous activity for which the actor is strictly liable. See, e.g., Kinsey v. Spann, 139 N.C. App. 370, 374, 533 S.E.2d 487, 491 (2000), in which this Court reiterated that:

Ultrahazardous activities are those that are so dangerous that even the exercise of reasonable care cannot eliminate the risk of serious harm. In such cases, the employer is strictly liable for any harm that proximately results. In other words, he is liable even if due care was exercised in the performance of the activity. In North Carolina, only blasting operations are considered ultrahazardous.

(citing Woodson v. Rowland, 329 N.C. 330, 350-51, 407 S.E.2d 222, 234 (1991)) (internal quotation marks omitted).

Defendant concedes that blasting is subject to strict liability, but contends that in the instant case summary judgment was properly *70 granted on plaintiff’s strict liability claim. Defendant argues that recovery is barred by plaintiffs assumption of risk. Plaintiff argues that assumption of risk is not even a permissible defense to a claim based on strict liability, and that even if it were available as a defense that plaintiff did not assume the risk of the 1 April 2003 blast.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cheryl Lloyd Humphrey Land Inv. Co. v. Resco Prods., Inc.
831 S.E.2d 395 (Court of Appeals of North Carolina, 2019)
Fagundes v. Ammons Dev. Grp., Inc.
820 S.E.2d 350 (Court of Appeals of North Carolina, 2018)
Thrash Commercial Contractors, Inc. v. Terracon Consultants, Inc.
889 F. Supp. 2d 868 (S.D. Mississippi, 2012)
Tillman v. Commercial Credit Loans, Inc.
655 S.E.2d 362 (Supreme Court of North Carolina, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
644 S.E.2d 16, 183 N.C. App. 66, 2007 N.C. App. LEXIS 837, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vecellio-grogan-inc-v-piedmont-drilling-blasting-inc-ncctapp-2007.