Vecellio & Grogan, Inc. v. Department of Highways

17 Ct. Cl. 153
CourtWest Virginia Court of Claims
DecidedDecember 13, 1988
DocketCC-83-207 & CC-83-208
StatusPublished

This text of 17 Ct. Cl. 153 (Vecellio & Grogan, Inc. v. Department of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vecellio & Grogan, Inc. v. Department of Highways, 17 Ct. Cl. 153 (W. Va. Super. Ct. 1988).

Opinion

HANLON, JUDGE:

These claims arise out of two separate projects on Interstate 79 designated as Project No. 1-79-1(16)29 and Project No. 1-79-1(15)25. The projects will hereinafter be referred to as Projects (16)29 and (15)25, respectively. These projects entailed the construction of three bridges, excavation and grading, and providing drainage for Interstate 79. The two projects are adjacent to each other with Project 15(25) as the southerly project. Claimant contends that there were differing site conditions and that errors in the plans caused claimant to incur extra costs in construction of the projects in the amount of $5,994,353.74.

Claimant also alleges that it is entitled to recover $9,000.00 in liquidated damages assessed by respondent on project (15)25 for 90 days at $300 per day as claimant did not complete the project in accordance with the contract completion date. Claimant asserts that the Court previously determined this issue in J. F. Allen Co. vs. Dept. of Highways, 12 Ct.Cl. 364 (1981). In that claim, the Court made an award for liquidated damages based upon the application of the liquidated damage clause in the contract as being unjustifiable. The Court indicated that "Irrespective of Governor Moore's oral proclamation...granting a ninety-day extension to the various contractors, the Court... is of the opinion that enforcement of the liquidated damage clause in the contract was unjustifiable." Claimant herein asserts that the proclamation applies to it also and should substantiate an award for the liquidated damages assessed. The Court will treat the issue of liquidated damages in this claim de novo.

Claimant bid on the northern project designated (16)29 in March 1970 and was awarded the project. In May 1970, claimant bid on the southern project designated (15)25. Claimant desired to construct both projects as the projects were adjacent to each other. Prior to bidding the projects, representatives of the claimant walked the job sites to examine the terrain and conditions then and there existing. Claimant reviewed the mass diagram and grading summary prepared by respondent which accompanied the plans in order to determine the excavation and fills which constituted the major portion of the work. The plans indicated that these projects were waste projects meaning that there would be sufficient material in the cuts to provide the embankment [154]*154material for the fills. In particular, claimant noted that the mass diagrams for the projects indicated that the projects were balanced i.e. waste equalled fill. The plans also indicated the shrink/swell factors for the material to be excavated. Claimant used these factors in calculating the amount of material necessary for the fills to be constructed.

The northern project provided for the construction of two bridges with a major cut of one million cubic yards between the bridges. There was also a major fill north of the bridges and the remainder of the construction involved channel changes to the northern end of the project.

The southern project provided for the construction of a major interchange known as the Amma Interchange. There was a large cut which contained one million cubic yards of material which appeared to be an amount which would be wasted. North of this interchange, claimant was to relocate local service route 29 and relocate a creek which involved several channel changes. The plans contained a note that the topsoil was unsuitable material which meant it would be wasted. Claimant's representatives determined that the topsoil was suitable and could be used as embankment material. When claimant bid the projects, the bids were base upon the premise that claimant would not have a borrow item as there would not be a necessity for borrow.

On the northern project, claimant proceeded with the construction of the two bridges which were in close proximity to one another but separated by a large cut. The material in the cut between Bridge 2681 and Bridge 2682 had to be transported north to an area known as the "million yard fill." Temporary access areas were constructed to facilitate the moving from the excavation between the bridges. North of the million yard fill was an area known as the cemetery fill. It was impossible to haul material up into that fill due to the high elevation of the rock. Therefore, the approximately 15,000 cubic years at that location was wasted.

The projects progressed without major problems until spring of 1972. At that time, claimant began to suspect that there would not be sufficient material to complete the embankments on either project with the material that remained to be removed in the cuts. Claimant instructed its employees to calculate the amount of fill needed as compared with material in the cuts by taking cross sections of the project. In June 1982, claimant informed respondent that it would need to borrow material to complete the projects. Respondent allowed the borrowing of material, but informed claimant that respondent would not pay for this item.

The southern project was started at the Amma Interchange as claimant determined that the area was accessible and claimant could work through the winter on excavation which could be wasted. At the pre-construction conference for this job. respondent's representative noted that claimant needed to submit waste areas for approval in order to claimant to waste material. This was done and claimant proceeded to waste both suitable and unsuitable material in a large waste site north of the bridge being constructed at the Amma Interchange. Claimant was able to use approximately 250,000 cubic yards of the cut for the construction of the interchange.

[155]*155Claimant continued with the projects and did, in fact, borrow material to complete the embankments. Claimant excavated approximately 300,000 cubic yards of material at the common cut which claimant used on project (15)25 although the material came from project (16)29. This action was permitted by respondent, but claimant was not paid for the borrow on project (15)25. There was also material borrowed at the site of the office. However, claimant had wasted material at this site, and then found it necessary to remove the wasted material to another location in order to excavate borrow material. The work entailed additional blasting and excavation. The claimant also borrowed material at the northern end of project (16)29 where there was a shortage of material.

Claimant contends that the shortage of materials was the direct result of an error in the plans which indicated the shrink-swell factors. It is claimant's position there were errors in the shrink/swell factor of more than 10% on project (15)25 and 5% or more on project (16)29. Although permission was granted by respondent to use material excavated from the cut common with the adjoining project at stations 1510 -1517 as borrow material to complete this project, the fills were still short, and claimant required additional borrow. Borrow material was drilled and blasted, then excavated and hauled to the construction area to satisfy the embankment shortage.

Claimant relied upon these factors in calculating the amount of material needed for the embankments. Claimant also contends that the channel change material which was indicated as suitable material on the plans could not be used as it was too wet. This material was wasted. Claimant asserts that borrow would not have been needed if the plans had been correct. As a result, claimant alleges that respondent breached an implied warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ideker, Inc. v. Missouri State Highway Commission
654 S.W.2d 617 (Missouri Court of Appeals, 1983)
Finch v. United States
12 Ct. Cl. 364 (Court of Claims, 1876)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ct. Cl. 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vecellio-grogan-inc-v-department-of-highways-wvctcl-1988.