V.E. Amick & Associates, LLC v. Palmetto Environmental Group, Inc.

716 S.E.2d 295, 394 S.C. 538, 2011 S.C. App. LEXIS 210
CourtCourt of Appeals of South Carolina
DecidedAugust 10, 2011
Docket4860
StatusPublished
Cited by3 cases

This text of 716 S.E.2d 295 (V.E. Amick & Associates, LLC v. Palmetto Environmental Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
V.E. Amick & Associates, LLC v. Palmetto Environmental Group, Inc., 716 S.E.2d 295, 394 S.C. 538, 2011 S.C. App. LEXIS 210 (S.C. Ct. App. 2011).

Opinion

GEATHERS, J.

In this breach of contract action, Palmetto Environmental Group, Inc. (Palmetto) argues (1) the trial court erred in denying Palmetto’s motion for a directed verdict because Palmetto’s performance was excused due to V.E. Amick & *542 Associates, LLC’s (Amick’s) failure to hire a Department of Health and Environmental Control (DHEC) qualified engineer to certify Palmetto’s work and (2) the trial court erred in denying Palmetto’s motion for a judgment notwithstanding the verdict or, in the alternative, for a new trial nisi remittitur because Amick will receive $137,650 in future contract payments from DHEC, and this amount should have been offset from the jury’s verdict. We affirm on both points.

FACTS/PROCEDURAL HISTORY

Amick is a DHEC certified company that performs remediation construction projects to rectify environmental contamination caused by petroleum products. Palmetto is also an environmental contracting company that remediates soil and groundwater contamination caused by petroleum products. Jimmy Cooper, Palmetto’s owner and principal shareholder, was formerly employed by David Jordan and David Snodgrass, the owners of a large construction enterprise including Amick, L-J Incorporated, and Environmental Engineering. After Cooper was fired, he formed Palmetto and began bidding for DHEC remediation projects through Amick.

Cooper assembled bids for three remediation projects (the Huse site, the Cromer’s Grocery site, and the Lakeside Market site) so that Amick could submit the bids to DHEC for approval. Amick would mark up Palmetto’s estimates by 10% and submit the bid to DHEC in exchange for furnishing Palmetto with performance bonds 1 required by DHEC. DHEC awarded Amick all three contracts, and Amick subcontracted 100% of the DHEC contracts to Palmetto. All of the contracts between Amick and Palmetto were oral.

During trial, Cooper testified Palmetto submitted invoices and was paid by Amick on a percentage basis once the company reached each reduction milestone set by DHEC. Cooper explained DHEC set four separate target level milestones of 25%, 50%, 75%, and 100% relating to the percentage of reduction of petroleum in the groundwater. Cooper agreed to reach 100% of the ultimate clean-up target levels set by *543 DHEC in exchange for 90% of the DHEC contract with Amick. Once Palmetto met a certain milestone, DHEC would pay Amick, and Amick would in turn remit 90% of the DHEC payment to Palmetto.

Palmetto reached the 75% target level milestone on all three contracts at issue before the company ceased working. Cooper claimed Palmetto actually completed each project to between 95% and 98% of the ultimate target levels, but he admitted that he submitted no more invoices to Amick after reaching the 75% milestone. Cooper conceded the biggest reason he failed to meet the ultimate target levels for the reduction of petroleum was that his company ran out of money and could no longer operate. Cooper also admitted Palmetto was paid for all the invoices it submitted to Amick.

After Palmetto ceased working on the three sites, Amick hired Carolina Technical Services, Inc. (CTSI) to complete the groundwater remediation contracts. Bill Wood, a CTSI employee, testified at trial on Amick’s behalf and was qualified as an expert in groundwater assessment and remediation. Wood testified the estimated cost to complete the Lakeside Market contract would be $88,297. Wood further testified it would cost an estimated $121,059 to complete remediation on the Huse site. Finally, Wood noted it would cost an estimated $78,037 to complete remediation on the Cromer’s Grocery site.

Wood testified Amick was paying CTSI on a “time and materials” basis, unlike the Amick contract with Palmetto. Specifically, Wood explained CTSI was receiving progress payments on a rolling basis, and the company did not have a contract with Amick to complete the projects to 100% of DHEC’s ultimate target levels.

Hugh Wilson, an employee of L-J Incorporated, testified DHEC was aware Amick had hired CTSI to complete the three projects after Palmetto failed to do so. Wilson also testified regarding Amick’s damages and explained “the way we look at it is what we spent today on the project plus the estimated cost of completion furnished by CTSI and crediting back the amount of the Palmetto subcontract....” Wilson testified the total amount needed to complete all three jobs and make Amick whole, after subtracting payments from *544 DHEC intended for Palmetto, would be “a little over $391,000.”

Wilson noted this amount represented the total payments to Palmetto and CTSI to date, plus the estimated cost for CTSI to complete remediation, less 90% of the amount of the original contract between Amick and DHEC (for specific damages amounts, see charts in Section II of this opinion). In other words, Wilson took the total amount Amick would end up paying both subcontractors on the three contracts with DHEC and subtracted the total amount Amick would have paid to Palmetto had Palmetto fully performed its contract with Amick. Palmetto’s counsel did not question the accuracy of any of the stated figures during Wilson’s cross-examination.

At the close of Amick’s case, Palmetto moved for a directed verdict on multiple grounds, including the contention that it “would have been illegal until Amick ... hired another [professional licensed engineer] as an employee to continue to certify completion to DHEC.” The trial court denied Palmetto’s directed verdict motion, noting:

[A]ll that stuff about the regulation about having a qualified person doesn’t matter. DHEC accepted those things, correspondence, all that stuff in there. They can hire somebody to certify it. [Cooper] tried to get his brother one time. But anyway, no evidence that anything was ever kicked out because it was not certified. [Cooper] admittedly got paid 75 percent. And in the light most favorable to him, he had done 95 percent of the work and they’ve got 25 percent of the money. The fact that DHEC now wants a pristine situation, which it probably can’t do, indicates that the job was underbid to start with.

Palmetto did not present any evidence in its own defense.

The trial court charged the jury as follows regarding the law of damages:

In the event of a failure to complete performance of a contract according to its terms, including a construction contract or subcontract, the injured party is entitled to such compensation which would leave it as well off as it would have been had the contract been fully performed. Measure of damages ordinarily is the reasonable cost of completion of *545 the same work if completion is possible and does not involve unreasonable economic wait.

The jury returned with a verdict for Amick in the amount of $391,209.21. Palmetto’s counsel moved for a judgment notwithstanding the verdict, or in the alternative, a new trial nisi remittitur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morin v. Innegrity, LLC
819 S.E.2d 131 (Court of Appeals of South Carolina, 2018)
Tuten v. Joel
763 S.E.2d 54 (Court of Appeals of South Carolina, 2014)
Figueroa v. CBI
Court of Appeals of South Carolina, 2012

Cite This Page — Counsel Stack

Bluebook (online)
716 S.E.2d 295, 394 S.C. 538, 2011 S.C. App. LEXIS 210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ve-amick-associates-llc-v-palmetto-environmental-group-inc-scctapp-2011.