NOTICE 2021 IL App (4th) 200283-U This Order was filed under Supreme FILED Court Rule 23 and is not precedent NO. 4-20-0283 March 8, 2021 except in the limited circumstances Carla Bender allowed under Rule 23(e)(1). IN THE APPELLATE COURT 4th District Appellate Court, IL OF ILLINOIS
FOURTH DISTRICT
VB APARTMENTS LLC, ) Appeal from Plaintiff-Appellant, ) Circuit Court of v. ) McLean County AMEREN ILLINOIS COMPANY, ) No. 14L87 Defendant-Appellee. ) ) Honorable ) Paul G. Lawrence, ) Judge Presiding.
JUSTICE HOLDER WHITE delivered the judgment of the court. Presiding Justice Knecht and Justice Turner concurred in the judgment.
ORDER ¶1 Held: The appellate court affirmed, concluding the trial court properly granted defendant’s motion for summary judgment.
¶2 In January 2015, plaintiff, VB Apartments, LLC, filed an amended complaint
pursuant to the Public Utilities Act (Act) (220 ILCS 5/1-101 et seq. (West 2014)). The
complaint alleged defendant, Ameren Illinois Company, negligently caused plaintiff damages in
excess of $50,000. In October 2018, defendant filed a motion for summary judgment. In
February 2020, the trial court granted the motion for summary judgment. In June 2020, the court
denied plaintiff’s motion to reconsider.
¶3 Plaintiff appeals, arguing the trial court erred by granting defendant’s motion for
summary judgment where (1) defendant’s tariff did not bar plaintiff’s claim; (2) the trial court
had jurisdiction over plaintiff’s claim, not the Illinois Commerce Commission (Commission); and (3) plaintiff’s claim was not barred by the economic-loss doctrine set forth in Moorman
Manufacturing Co. v. National Tank Co., 91 Ill. 2d 69, 435 N.E.2d 443 (1982). For the
following reasons, we affirm the trial court’s judgment.
¶4 I. BACKGROUND
¶5 In January 2015, plaintiff filed an amended complaint pursuant to the Act (220
ILCS 5/1-101 et seq. (West 2014)). The complaint alleged plaintiff installed a main breaker
designed to be the point of entry of electricity into a multiple-family residential property in
Normal, Illinois. An electrical contractor hired by plaintiff extended wire from the main breaker
to a transformer pole owned by defendant. According to the complaint, the connection of the
wire to the transformer was defendant’s sole and exclusive responsibility. The complaint alleged
defendant “negligently and carelessly utilized equipment and a methodology which was violative
of the provisions of the National Electric Safety Code ***, and as a direct and proximate result
of the negligent and illegal connection, naturally accumulating moisture was allowed to intrude
into the breaker, causing it to be damaged and resulting in disruptions of power service to the
improvements owned by [p]laintiff.”
¶6 The record establishes the following undisputed relevant facts. Plaintiff contacted
defendant to set up electrical service prior to the construction of its apartment building.
Defendant installed a utility pole and built a transformer bank. Plaintiff’s electrician installed a
main breaker and extended service conductors to the utility pole. Defendant connected the
service conductors to the transformer bank. Martin Behrens, defendant’s engineering supervisor,
stated the termination (where the service conductor connected to the transformer) was consistent
with the way defendant installed several other conductors. According to Behrens, at the
termination, “the lug actually squeezed the cable down to compress it to the point where there
-2- was virtually no, if any, space around the stranding of the conductors within the cable.” Plaintiff
alleged the exposed ends of the conductors allowed water to wick through the conductors,
ultimately contacting and damaging the electronic breaker. Behrens ultimately “suggested
covering the connections at the transformer[.]” At the same time the covers were installed, “butt
splices *** were installed on the service entrance conductors at the main switch” that could have
stopped the migration of water into the main switch.
¶7 The discharge of water into the breaker damaged the breaker and the conductors.
The damage to plaintiff’s equipment prevented the breaker from distributing electricity to the
apartment building 57 times between July 2012 and May 2013. Plaintiff alleged it replaced the
breaker at least three times, replaced the water-logged conductors, and spent more than 600
hours tending to the damage.
¶8 In October 2018, defendant filed a motion for summary judgment. The motion
for summary judgment argued plaintiff’s claim was (1) within the exclusive jurisdiction of the
Commission, (2) barred by the utility tariff, and (3) barred by the economic-loss doctrine. The
tariff included a limitation of liability provision, requiring defendant to “use reasonable diligence
in furnishing uninterrupted and regular [e]lectric [s]ervice, but will in no case be liable for
interruptions, deficiencies[,] or imperfections of said service, except to the extent of a pro rata
reduction of the monthly charges.” In February 2020, the trial court granted defendant’s motion
for summary judgment in its entirety.
¶9 In March 2020, plaintiff filed a motion to reconsider, arguing there was new
evidence and the trial court misapplied the law in its ruling. The trial court denied the motion to
reconsider. In making its ruling, the court relied on Sheffler v. Commonwealth Edison Co., 2011
IL 110166, 955 N.E.2d 1110, to determine the Commission had jurisdiction over plaintiff’s
-3- claims of inadequate service. The court concluded the utility tariff barred plaintiff’s claims
because plaintiff sought to recover for interruptions in service, which defendant was only liable
for to the extent of a pro rata reduction in charges. Finally, the court determined the
economic-loss doctrine applied to the provision of electrical services and barred plaintiff’s claim
because it related to a defeated commercial expectation.
¶ 10 This appeal followed.
¶ 11 II. ANALYSIS
¶ 12 On appeal, plaintiff argues the trial court erred by granting defendant’s motion for
summary judgment where (1) defendant’s tariff did not bar plaintiff’s claim; (2) the trial court
had jurisdiction over plaintiff’s claim, not the Commission; and (3) plaintiff’s claim was not
barred by the economic-loss doctrine set forth in Moorman, 91 Ill. 2d 69.
¶ 13 Summary judgment is appropriate where the pleadings, depositions, admissions,
and affidavits establish no genuine issue of material fact exists and the moving party is entitled to
judgment as a matter of law. Purtill v. Hess, 111 Ill. 2d 229, 240, 489 N.E.2d 867, 871 (1986).
“While use of the summary judgment procedure is to be encouraged as an aid in the expeditious
disposition of a lawsuit [citation], it is a drastic means of disposing of litigation and therefore
should be allowed only when the right of the moving party is clear and free from doubt.” Id. In
ruling on a motion for summary judgment, the court must view the evidence in the light most
favorable to the non-moving party. Boldini v. Owens Corning, 318 Ill. App. 3d 1167, 1170, 744
N.E.2d 370, 372 (2001). We review de novo an order granting summary judgment. Id.
¶ 14 A. Utility Tariff
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE 2021 IL App (4th) 200283-U This Order was filed under Supreme FILED Court Rule 23 and is not precedent NO. 4-20-0283 March 8, 2021 except in the limited circumstances Carla Bender allowed under Rule 23(e)(1). IN THE APPELLATE COURT 4th District Appellate Court, IL OF ILLINOIS
FOURTH DISTRICT
VB APARTMENTS LLC, ) Appeal from Plaintiff-Appellant, ) Circuit Court of v. ) McLean County AMEREN ILLINOIS COMPANY, ) No. 14L87 Defendant-Appellee. ) ) Honorable ) Paul G. Lawrence, ) Judge Presiding.
JUSTICE HOLDER WHITE delivered the judgment of the court. Presiding Justice Knecht and Justice Turner concurred in the judgment.
ORDER ¶1 Held: The appellate court affirmed, concluding the trial court properly granted defendant’s motion for summary judgment.
¶2 In January 2015, plaintiff, VB Apartments, LLC, filed an amended complaint
pursuant to the Public Utilities Act (Act) (220 ILCS 5/1-101 et seq. (West 2014)). The
complaint alleged defendant, Ameren Illinois Company, negligently caused plaintiff damages in
excess of $50,000. In October 2018, defendant filed a motion for summary judgment. In
February 2020, the trial court granted the motion for summary judgment. In June 2020, the court
denied plaintiff’s motion to reconsider.
¶3 Plaintiff appeals, arguing the trial court erred by granting defendant’s motion for
summary judgment where (1) defendant’s tariff did not bar plaintiff’s claim; (2) the trial court
had jurisdiction over plaintiff’s claim, not the Illinois Commerce Commission (Commission); and (3) plaintiff’s claim was not barred by the economic-loss doctrine set forth in Moorman
Manufacturing Co. v. National Tank Co., 91 Ill. 2d 69, 435 N.E.2d 443 (1982). For the
following reasons, we affirm the trial court’s judgment.
¶4 I. BACKGROUND
¶5 In January 2015, plaintiff filed an amended complaint pursuant to the Act (220
ILCS 5/1-101 et seq. (West 2014)). The complaint alleged plaintiff installed a main breaker
designed to be the point of entry of electricity into a multiple-family residential property in
Normal, Illinois. An electrical contractor hired by plaintiff extended wire from the main breaker
to a transformer pole owned by defendant. According to the complaint, the connection of the
wire to the transformer was defendant’s sole and exclusive responsibility. The complaint alleged
defendant “negligently and carelessly utilized equipment and a methodology which was violative
of the provisions of the National Electric Safety Code ***, and as a direct and proximate result
of the negligent and illegal connection, naturally accumulating moisture was allowed to intrude
into the breaker, causing it to be damaged and resulting in disruptions of power service to the
improvements owned by [p]laintiff.”
¶6 The record establishes the following undisputed relevant facts. Plaintiff contacted
defendant to set up electrical service prior to the construction of its apartment building.
Defendant installed a utility pole and built a transformer bank. Plaintiff’s electrician installed a
main breaker and extended service conductors to the utility pole. Defendant connected the
service conductors to the transformer bank. Martin Behrens, defendant’s engineering supervisor,
stated the termination (where the service conductor connected to the transformer) was consistent
with the way defendant installed several other conductors. According to Behrens, at the
termination, “the lug actually squeezed the cable down to compress it to the point where there
-2- was virtually no, if any, space around the stranding of the conductors within the cable.” Plaintiff
alleged the exposed ends of the conductors allowed water to wick through the conductors,
ultimately contacting and damaging the electronic breaker. Behrens ultimately “suggested
covering the connections at the transformer[.]” At the same time the covers were installed, “butt
splices *** were installed on the service entrance conductors at the main switch” that could have
stopped the migration of water into the main switch.
¶7 The discharge of water into the breaker damaged the breaker and the conductors.
The damage to plaintiff’s equipment prevented the breaker from distributing electricity to the
apartment building 57 times between July 2012 and May 2013. Plaintiff alleged it replaced the
breaker at least three times, replaced the water-logged conductors, and spent more than 600
hours tending to the damage.
¶8 In October 2018, defendant filed a motion for summary judgment. The motion
for summary judgment argued plaintiff’s claim was (1) within the exclusive jurisdiction of the
Commission, (2) barred by the utility tariff, and (3) barred by the economic-loss doctrine. The
tariff included a limitation of liability provision, requiring defendant to “use reasonable diligence
in furnishing uninterrupted and regular [e]lectric [s]ervice, but will in no case be liable for
interruptions, deficiencies[,] or imperfections of said service, except to the extent of a pro rata
reduction of the monthly charges.” In February 2020, the trial court granted defendant’s motion
for summary judgment in its entirety.
¶9 In March 2020, plaintiff filed a motion to reconsider, arguing there was new
evidence and the trial court misapplied the law in its ruling. The trial court denied the motion to
reconsider. In making its ruling, the court relied on Sheffler v. Commonwealth Edison Co., 2011
IL 110166, 955 N.E.2d 1110, to determine the Commission had jurisdiction over plaintiff’s
-3- claims of inadequate service. The court concluded the utility tariff barred plaintiff’s claims
because plaintiff sought to recover for interruptions in service, which defendant was only liable
for to the extent of a pro rata reduction in charges. Finally, the court determined the
economic-loss doctrine applied to the provision of electrical services and barred plaintiff’s claim
because it related to a defeated commercial expectation.
¶ 10 This appeal followed.
¶ 11 II. ANALYSIS
¶ 12 On appeal, plaintiff argues the trial court erred by granting defendant’s motion for
summary judgment where (1) defendant’s tariff did not bar plaintiff’s claim; (2) the trial court
had jurisdiction over plaintiff’s claim, not the Commission; and (3) plaintiff’s claim was not
barred by the economic-loss doctrine set forth in Moorman, 91 Ill. 2d 69.
¶ 13 Summary judgment is appropriate where the pleadings, depositions, admissions,
and affidavits establish no genuine issue of material fact exists and the moving party is entitled to
judgment as a matter of law. Purtill v. Hess, 111 Ill. 2d 229, 240, 489 N.E.2d 867, 871 (1986).
“While use of the summary judgment procedure is to be encouraged as an aid in the expeditious
disposition of a lawsuit [citation], it is a drastic means of disposing of litigation and therefore
should be allowed only when the right of the moving party is clear and free from doubt.” Id. In
ruling on a motion for summary judgment, the court must view the evidence in the light most
favorable to the non-moving party. Boldini v. Owens Corning, 318 Ill. App. 3d 1167, 1170, 744
N.E.2d 370, 372 (2001). We review de novo an order granting summary judgment. Id.
¶ 14 A. Utility Tariff
-4- ¶ 15 Plaintiff first asserts the trial court erred by granting summary judgment based on
defendant’s utility tariff. Defendant contends the court properly determined the utility tariff
barred plaintiff’s claim.
¶ 16 “A tariff is a public document setting forth services being offered, the rates and
charges with respect to services, and the governing rules, regulations, and practices relating to
those services.” Sheffler, 2011 IL 110166, ¶ 28. When a tariff is filed with the Commission, it
binds the utility and the customer and governs their relationship. Id. A tariff approved by the
Commission becomes the law and has the force and effect of a statute. Id. “Tariff provisions are
usually referred to as liability limitations, which reflect the status of public utilities as regulated
monopolies whose operations are subject to extensive restrictions, the requirements of uniform,
nondiscriminatory rates, and the goal of universal service, achieved through the preservation of
utility prices that virtually all customers can afford.” Id. ¶ 29. A strictly regulated public
utility’s liability should be defined and limited so it may provide service at reasonable rates,
which is in part dependent on a rule limiting liability. Adams v. Northern Illinois Gas Co., 211
Ill. 2d 32, 57, 809 N.E.2d 1248, 1264 (2004).
¶ 17 Here, the utility tariff contained a limitation of liability that provides, in part, as
follows:
“The Company will use reasonable diligence in furnishing
uninterrupted and regular [e]lectric [s]ervice, but will in no case be
liable for interruptions, deficiencies[,] or imperfections of said
service, except to the extent of a pro rata reduction of the monthly
charges.
-5- The Company does not guarantee uninterrupted service and
shall not be liable for any damages, direct or otherwise, which the
Customer may sustain by reason of any failure or interruption of
service, increase or decrease in energy voltage or change in
character of energy, whether caused by accidents, repairs or other
causes except when caused by gross negligence on its part;
however, in no event shall the Company be liable for any loss by
Customer of production, revenues[,] or profits or for any
consequential damages whatsoever on account of any failure or
interruption of service or increase or decrease in energy voltage or
change in character of energy; nor shall the Company be liable for
damages that may be incurred by the use of electrical appliances or
the presence of the Company’s property on the Customer’s
Premises. Company is not responsible or liable for damage to
Customer’s motor or any other equipment or property caused by
conditions not due to negligence of Company. ***
***
The Company shall not be responsible nor liable for
electric energy from and after the point at which it first passes to
the wires or other equipment owned or controlled by the Customer,
and the Customer shall protect and save harmless Company for all
claims for injury or damage to Persons or property occurring
beyond said point, except where injury or damage shall be shown
-6- to have been occasioned solely by the negligence of the
Company.”
¶ 18 Plaintiff argues its claim is not barred by the tariff because the claims sound in
negligence and seek recovery for damages to its property. Defendant contends plaintiff ignores
the pro rata reduction clause, which limits defendant’s liability because plaintiff seeks damages
for interruptions in electrical service.
¶ 19 Plaintiff seeks damages for the time its officers spent responding to interruptions
in service, meetings concerning the outages and resetting of power, charges from the electrician
responding to outages, charges for displacement of tenants during outages, and credits to tenants
for food spoilage due to outages. The utility tariff limits defendant’s liability for service
interruptions to a reduced pro rata monthly service charge. Moreover, the clause plaintiff
selectively cites (“Company is not responsible or liable for damages to Customer’s motor or any
other equipment or property not due to the negligence of Company”) ignores a preceding clause
which provides:
“The Company does not guarantee uninterrupted service
and shall not be liable for any damages, direct or otherwise, which
the Customer may sustain by reason of any failure or interruption
of service, increase or decrease in energy voltage or change in
character of energy, whether caused by accidents, repairs or other
however, in no event shall the Company be liable for any loss by
consequential damages whatsoever on account of any failure or
-7- interruption of service or increase or decrease in energy voltage or
change in character of energy ***.” (Emphasis added.)
The utility tariff bars plaintiff’s claims for damages for its expenditures responding to service
interruptions, even if the claims are framed in terms of negligence. Accordingly, we conclude
the trial court did not err in granting defendant’s motion for summary judgment on this basis.
¶ 20 B. Jurisdiction
¶ 21 Plaintiff next asserts the trial court erred by granting summary judgment based on
its conclusion the Commission had exclusive jurisdiction over plaintiff’s claim. Defendant
contends the court properly determined the Commission had exclusive jurisdiction over
plaintiff’s claims for reparations.
¶ 22 The Act allows claims for civil damages to be filed in the circuit court:
“In case any public utility shall do, cause to be done or
permit to be done any act, matter or thing prohibited, forbidden or
declared to be unlawful, or shall omit to do any act, matter or thing
required to be done either by any provisions of this Act or any rule,
regulation, order or decision of the Commission, issued under
authority of this Act, the public utility shall be liable to the persons
or corporations affected thereby for all loss, damages or injury
caused thereby or resulting therefrom, and if the court shall find
that the act or omission was wilful, the court may in addition to the
actual damages, award damages for the sake of example and by the
way of punishment. An action to recover for such loss, damage or
-8- injury may be brought in the circuit court by any person or
corporation.” 220 ILCS 5/5-201 (West 2014).
However, the Commission has jurisdiction over claims for reparations. Sheffler, 2011 IL
110166, ¶ 42. “[A] claim is for reparations when the essence of the claim is that a utility has
charged too much for a service, while a claim is for civil damages when the essence of the
complaint is that the utility has done something else to wrong the plaintiff.” Id. Complaints
concerning the adequacy of a utility’s service fall within the Commission’s jurisdiction and
within the rubric of “reparations.” Id. ¶ 55.
¶ 23 In Sheffler, the plaintiffs brought a claim under the Act for damages resulting
from the utility’s alleged negligence. Id. ¶ 5. The Sheffler plaintiffs sought compensatory
damages for “personal injury, property damage and financial damages, including the loss of use
of property, and costs of repair and replacement of property.” Id. ¶ 44. The plaintiffs claimed
the electric company had a duty to provide continuous power and the utility was negligent due to
an inadequate process to warn customers of a power outage, a failure to timely restore power,
and a deficient infrastructure. Id. ¶¶ 51-52. The Illinois Supreme Court concluded “the nature of
the relief sought by plaintiffs is compensation for ComEd’s allegedly inadequate service, which
directly relates to the Commission’s rate-setting functions for electrical power services.” Id.
¶ 53.
¶ 24 Plaintiff attempts to distinguish Sheffler by arguing defendant in this case always
provided power but its negligent design and choice of equipment violated Commission rules and
damaged plaintiff’s equipment. As defendant correctly notes, the Sheffler plaintiffs argued the
damages were not merely caused by service interruptions but by the utility’s inadequate planning
and infrastructure. Id. ¶¶ 4-5. Similarly, plaintiff here seeks compensation for defendant’s
-9- allegedly inadequate service due to its choice of design and equipment. The Sheffler court
determined a complaint based on allegations concerning a utility’s infrastructure and provision of
electrical services and seeking relief based on defects in the provision of electrical services or the
repair of those services following a power outage was a complaint for reparations within the
exclusive jurisdiction of the Commission. Id. ¶ 56. In support of its argument, plaintiff cites
Durica v. Commonwealth Edison Co., 2015 Il App (1st) 140076, 30 N.E.3d 499. We find
Durica distinguishable because the plaintiffs’ claims in that case did not relate to the utility’s
failure to provide adequate services. Id. ¶ 41. Indeed, the Durica court distinguished Sheffler on
this basis, stating “[plaintiffs] do not allege that they were overcharged by ComEd or that
ComEd failed to provide adequate electricity services. Rather, they allege that ComEd
trespassed upon their property and seek to recover civil damages in tort, not reparations for rate
overcharges or inadequate service. Thus, the holding of Sheffler that the [Commission] has
jurisdiction over complaints seeking reparations for inadequate service does not compel
exclusive [Commission] jurisdiction in this case.” Id.
¶ 25 Plaintiff further attempts to distinguish Sheffler by pointing out the plaintiffs in
that case did not allege any violations of the National Electrical Safety Code. Plaintiff argues the
Commission adopted various provisions of the National Electrical Safety Code as its rules and
defendant violated those rules. 83 Ill. Adm. Code 305.20 (2003). Plaintiff asserts that, “pursuant
to the Public Utilities Act, [defendant] is liable for all loss, damages, or injury to [p]laintiff
caused by [defendant’s] violations.” (Emphasis in original). However, Sheffler made it very
clear that “courts focus on the nature of the relief sought rather than the basis for seeking relief in
determining whether an action falls within the jurisdiction of the Commission.” Sheffler, 2011
IL 110166, ¶ 50. Here, plaintiff seeks damages for inadequate service and power outages,
- 10 - including expenses associated with outages and the hours it spent dealing with repeated outages.
While defendant may have violated the Commission’s rules, the nature of the relief plaintiff
seeks falls within the jurisdiction of the Commission.
¶ 26 We conclude Sheffler applies in this case, where plaintiff’s claims concern the
adequacy of defendant’s service and fall within the Commission’s jurisdiction. Accordingly, the
trial court properly determined it lacked jurisdiction over plaintiff’s claims and granted
defendant’s motion for summary judgment. As we have determined the court properly granted
defendant’s motion for summary judgment because plaintiff’s claim was barred by the utility
tariff and the Commission had exclusive jurisdiction, we need not address the court’s decision
based on the economic-loss doctrine. Therefore, we affirm the judgment of the trial court.
¶ 27 III. CONCLUSION
¶ 28 For the reasons stated, we affirm the trial court’s judgment.
¶ 29 Affirmed.
- 11 -