Vázquez v. Municipality of Arecibo

40 P.R. 486
Supreme Court of Puerto Rico·Decided January 31, 1930·No. No. 4463·Published

Opinion

Mr. Justice Texidor

delivered the opinion of the court.

In this case the plaintiff substantially alleged that the Municipality of Arecibo had called for bids for the construction of four kilometers of road in the wards of Dominguito and Esperanza in that municipality; that the council awarded the contract to the plaintiff and authorized the Commissioner of Public Works to sign a formal agreement with the plaintiff, which was executed accordingly, and the agreement was thereafter ratified by the Commissioner of. the Interior of Porto Rico; that the contract was let out at $9,551.40; that after the work had been commenced, the plaintiff was compelled to make some alterations in building the road which increased the original cost by 20 per cent and which the plaintiff executed at the prices specified in the original contract, wherein it was stipulated that alterations exceeding 20 per cent should be paid according to prices first agreed upon by the Commissioner of Public Works; that after the 20 per cent margin of increase became exhausted, the plaintiff had to incur certain extraordinary and unforeseen expenditures by reason of a change in the course of the road and, in pursuance of the contract, the municipality and the plaintiff, on February 8, 1924, executed a supplemental agreement, which was approved by the Commissioner of the Interior and involved the sum of $3,901.70; that the plaintiff has demanded payment of the above sum from the Municipality of Arecibo but the defendant has failed to pay the same.

In its answer the defendant municipality denied that any [488]*488contract under competitive bidding bad been awarded to tbe plaintiff for tbe construction of tbe four kilometers of road, and averred that a contract without advertising bad been executed. It further alleged that tbe alterations made by tbe plaintiff in tbe road were executed for bis own benefit a:ud in order to effect savings in tbe work, and it denied that be had to incur any extraordinary expenditures or that any valid contract bad been entered into with tbe municipality covering tbe payment of such expenditures; that tbe plaintiff delivered the road in tbe middle of 1924 and liquidated tbe works during tbe first part of November of tbe same year, and that after several months bad elapsed since such delivery be put in a claim on a supplemental contract, which bad never been filed in tbe office of tbe municipal secretary nor approved by tbe municipal council; that tbe said supplemental contract is void and that the purpose of tbe claim filed by tbe plaintiff was to secure payment for work which be bad never performed, and with reference to which be submitted no claim at the time tbe road was delivered; and that tbe defendant owed no money to tbe plaintiff. The defendant also interposed a demurrer to tbe complaint for lack of facts sufficient to constitute a cause of action, in that tbe additional work was not specified or alleged to have been performed.

A trial was bad before tbe court, which beard tbe evidence introduced and rendered judgment for tbe defendant. From that judgment this appeal has been taken by tbe plaintiff, who assigns error as follows:

“The court erred in rendering judgment for the defendant.”

That form of assignment is too general, but it shall not prevent us from considering and deciding tbe main questions involved in this appeal.

We are of opinion, and so bold, that the complaint in tbe present case fails to allege essential facts.

Tbe complaint does not state what particular work, alterations, or changes had to be performed by tbe plaintiff; why [489]*489he had to execute them; whether they were imperative or unavoidable; and whether they were first submitted to the Commissioner of Public Works and approved by him in the manner required by the law, the regulations and the contract.

It is not stated or alleged that the said work, which cost more than $500, had been let through competitive bidding; or, if not so let, that it had been exempted from such requirement and the reasons therefor.

What work was it? What alterations were made to the original course of the road? Only vague hints as to these particulars appear from the evidence. A landowner through whose property the road was laid objected to it. But there is no allegation or proof as to the steps taken to overcome such opposition, or as to how the latter forced a change, the cost of which exceeded 35 per cent of the original estimate. This is .an important amount. Indeed any sum, however small, would be important where the property or the funds of a municipality are concerned. The money of such communities is the money of the people, of the taxpayers, and its use or investment calls for the exercise of the greatest prudence, which is the aim sought by applicable statutory requirements.

The particulars of the work done and the plans for its execution are not satisfactorily shown. Moreover, from the evidence heard it clearly appears that the officials of the municipality had no previous knowledge of the alterations alleged to have been made by the plaintiff. Under date of February 5, 1924, the plaintiff wrote to the Commissioner of Public. Works of Arecibo the following letter: (pages 8 and 9 of the transcript of the evidence):

“Arecibo, P. R. — February 5, 1924. — The Municipal Commissioner of Public Works. — City.-—Sir: Referring to our conversation in regard to the extra work already executed in the third section of the domiNguito-esp'ERANZa road and for. which I made timely claim as exceeding 20% of 1he unit amounts stated in .the contract, I beg [490]*490leave to submit to you the following prices per unit: 28 cubic meters of dry masonry at $6.00 . . . $168; 521 cubic meters of broken stone rolled and graveled at $2.20 . . . $1,146.20; 3,450 cubic meters of rock exeayations at $0.75 . . . $2,387.50; (total) $3,901.70.— Bearing in mind tbe facts above stated that such work exceeds the 20% and must be dealt with in the manner provided by section 30 of the general stipulations for public works per unit, which form a part of the present contract, and by section 26 of the instructions to bidders, I now beg to request that speedy action be taken in this matter in order that I be paid the value of said work. Respectfully yours, (Signed) Manuel Vázquez, Contractor.”

The plaintiff himself makes reference in that letter to work already executed, not to Avork pending of execution; and after mentioning the AYork as already performed, he submits the prices per unit. Even assuming that the Avork is to be considered as approved, there was no preAdous agreement as to prices, either with the commissioner or with the assembly, or with any representative of the municipality. And it appears from the evidence that the letter above quoted was sent to the municipal assembly long after February 5, 1924.

Subdivision 27 of the instructions to bidders for that contract (page 87 of the transcript) reads as follows:

”27. — Wore Not provided in the Contract. — No claim shall be considered for work not provided in the contract unless such'work has been previously ordered by the Municipal Commissioner of Public Works with the approval of the Council of Administration, and unless the Municipal Commissioner of Public Works and the contractor haA^e agreed as to the prices to be charged for the said extra Avork and such prices have been duly approved.”

Free access — add to your briefcase to read the full text and ask questions with AI

Vázquez v. Municipality of Arecibo, 40 P.R. 486 (prsupreme 1930).

40 P.R. 486 (Vázquez v. Municipality of Arecibo) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reams v. Cooley
152 P. 293 (California Supreme Court, 1915)