Vaughn Coltrane & Associates, Inc. v. LaM Distribution, LLC
This text of Vaughn Coltrane & Associates, Inc. v. LaM Distribution, LLC (Vaughn Coltrane & Associates, Inc. v. LaM Distribution, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
Vaughn Coltrane & Associates, Inc., Plaintiff,
v.
LaM Distribution, LLC and Fidelity & Deposit Company of Maryland, Defendants.
LaM Distribution, LLC, Appellant,
Vaughn Coltrane & Associates, Inc., KCV Construction Services, Inc.; Albert V. Coltrane, P.E., Respondents.
Appeal From Calhoun County
James C. Williams, Jr., Circuit Court
Judge
Unpublished Opinion No. 2004-UP-309
Submitted April 12, 2004 Filed May
7, 2004
REVERSED
Henry W. Brown and John W. Davidson, both of Columbia, for Appellant.
R. Davis Howser, George V. Hanna, IV and Andrew E. Haselden, all of Columbia, for Respondents.
PER CURIAM: In this dispute relating to the construction of a freezer facility, Appellant LaM Distribution (LaM) contends the trial court erred in concluding Respondent Vaughn Coltrane & Associates (VCA) had not breached its contract with LaM and in discounting the award of damages to LaM for fees not paid to VCA. We reverse. [1]
FACTS
On March 30, 1998, LaM secured a building permit for a $6,500,000.00 refrigerated warehouse facility to be constructed in Calhoun County, South Carolina. Employing temperatures as low as -25 degrees Fahrenheit, the facility freezes and stores food products and other perishables. To design and manage construction of the facility, LaM contracted for the services of VCA, a consulting engineering firm specializing in food industry services. The agreement between the parties contained the following clause:
3. VCA will be responsible for exercising the degree of skill and care required by customarily accepted, good professional engineering practices and procedures.
Construction of the facility took longer than planned. When the project was approximately sixty-five percent complete, LaM discovered various design and construction problems. A dispute then arose regarding lack of payment of some of the construction management fees owed to VCA. As a result of the dispute, VCA left the job prior to the completion of construction, thereby leaving unfulfilled its contractual obligations. All told, LaM paid VCA $284,498.21 for the work, but did not pay approximately $89,000.00 in fees charged during the last portion of the construction management phase of the project.
After construction was complete and the facility went into operation, LaM discovered additional problems with the design and construction of the facility. To assess the condition of the facility, LaM engaged the services of Facilities Design, Inc., an engineering company with experience in the design of cold storage facilities and construction management. Over the course of its investigation, Facilities Design found nineteen defects in the facilitys design and construction. These deficiencies included various instances of inadequate insulation, improper wiring, insufficient emergency lighting, lack of proper drainage, and various code violations.
VCA eventually filed suit against LaM to collect the unpaid fees, alleging causes of action for breach of contract, quantum meruit, and foreclosure of mechanics lien. LaM answered and counterclaimed, alleging causes of action for breach of contract, negligence, fraudulent misrepresentation, constructive fraud, negligent misrepresentation, breach of implied warranty, and breach of express warranty.
By order dated May 30, 2001, the trial court granted LaMs motion for summary judgment on all causes of action alleged against it by VCA. In so ruling, the court noted VCA was not properly licensed to practice engineering in South Carolina because it lacked a Certificate of Authorization as required by statute. Because VCA had not complied with the statutory mandate, the court held VCA is prohibited from enforcing this contract and collecting its fees. VCA did not appeal the order.
With only LaMs counterclaims remaining, the parties tried the matter without a jury in February 2002. The trial court ruled in favor of LaM on only its negligence cause of action, finding VCA liable for eight of the alleged nineteen design and construction defects. Of the eight defects found, however, the court awarded LaM compensation for only six and also reduced damages to account for VCAs unpaid fees, thereby arriving at a total award of $34,140.00. LaM now appeals.
STANDARD OF REVIEW
An action for breach of contract is an action at law. Roberts v. Gaskins, 327 S.C. 478, 483, 486 S.E.2d 771, 773 (Ct. App. 1997). In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge will not be disturbed upon appeal unless found to be without evidence which reasonably supports the judges findings. Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976).
LAW/ANALYSIS
Contract
LaM asserts the trial court erred in failing to find VCA had breached its contract with LaM. We agree.
In concluding VCA had not breached its contract by discontinuing work on the project, the trial court stated, the evidence further discloses that LaM failed to pay VCA and/or KCV for the work it performed under the contract, thereby giving VCA and KCV the legal right to pull off of the job based on this non-payment of agreed to fees. The court also indicated other actions by LaM that contributed to affording VCA the legal right to discontinue its performance under the contract. In essence, the court ruled LaMs non-payment and other actions amounted to a material breach of the contract, thereby relieving VCA of its obligation to perform.
While the trial court is correct that the legal consequences of one partys material breach is to relieve the other contracting party of its performance obligation, that rule has no application in the present case. As previously noted, VCA failed to appeal the court order of May 30, 2001, dismissing its breach of contract claim against LaM. As an unappealed order, all the findings of fact and legal conclusions contained thereinincluding the ruling that LaM did not breach the contractare now the indisputable law of the case. See Charleston Lumber Co. v. Miller Housing Corp., 338 S.C.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Vaughn Coltrane & Associates, Inc. v. LaM Distribution, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vaughn-coltrane-associates-inc-v-lam-distribution-llc-scctapp-2004.