Varibus Corp. v. South Hampton Co.

623 S.W.2d 157, 1981 Tex. App. LEXIS 4344
CourtCourt of Appeals of Texas
DecidedOctober 15, 1981
DocketNo. 8663
StatusPublished
Cited by3 cases

This text of 623 S.W.2d 157 (Varibus Corp. v. South Hampton Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Varibus Corp. v. South Hampton Co., 623 S.W.2d 157, 1981 Tex. App. LEXIS 4344 (Tex. Ct. App. 1981).

Opinion

KEITH, Justice.

Defendant below appeals from a judgment based upon an instructed verdict in a suit for damages sustained because of an alleged breach of a contract to purchase fuel oil. Although several issues were submitted to the jury, when it was unable to agree upon a verdict, the trial court granted plaintiff’s motion for an instructed verdict and also instructed the jury as to the specific amount of damages it should find for the plaintiff.

The appeal is based upon a number of points of error, only one of which will be reached because of our view of the controlling question. We reverse the judgment of the trial court and render judgment for the defendant for the reasons now to be stated.

On January 14, 1975, the plaintiff “Seller” and the defendant “Buyer” entered into an elaborate written contract for the sale and purchase of fuel oil at “Seller’s Terminal” to be located upon the Neches River in the vicinity of Beaumont. At the time of the execution of the contract, the terminal was not in existence.

Section 1.04 of the contract required Seller to construct a terminal, the provision [158]*158being set out in the margin.1 Other provisions in the contract provided that the quantity and quality of the product would be “determined by SELLER’S shore tank strappings and shore tank sample at the time of each delivery . . .. ” Sec. 1.05(a). Title to the product, and risk of loss passed to Buyer “as the Product passes through the flange connection between BUYER’S vessel and SELLER’S Terminal loading line and into BUYER’S vessel.” Sec. 1.07.

Another paragraph provided that if Seller had not completed the terminal by August 1, 1975, Buyer could cancel the contract, but, in such event, Seller had the option to supply Buyer with product of equal quantity and quality appropriately adjusted in price for any differential in transportation charges. This provision in the contract did not come into play in the dispute.

Instead, Buyer elected to terminate the contract under another provision in the contract reading:

“In the event SELLER’S Terminal is not completed by January 1, 1976, as planned and contemplated, for any reason, including force majeure, BUYER shall have the right to cancel this contract for reason of SELLER’S nonperformance by giving SELLER 30 days pre-notification of cancellation with such pre-notification to be given anytime during the month of January 1976.” (emphasis supplied)

Able counsel representing the parties have filed lengthy and elaborate briefs wherein many contentions are presented in a scholarly manner. After reviewing the entire record, we are of the opinion that counsel for the defendant has succinctly summarized the basic issue in this reply brief:

“The issue before the Court is whether the ‘Terminal’, as planned and contemplated by the parties, was or was not completed by January 1, 1976. Varibus contends that the undisputed evidence established that the Terminal was not in fact completed by January 1, 1976, and accordingly that it established as a matter of law that it was entitled to and did cancel the contract, relieving it of any liability for the alleged breach of contract. South Hampton, on the other hand, contends that under the undisputed evidence, it was established that the Terminal was in fact completed by January 1,1976, and that Varibus was not entitled to cancel the contract, and accordingly, must respond in damages.”

Plaintiff — South Hampton — argues that Sec. 1.04 (footnote 1, supra) treated the terminal and tankage as separate and “[t]he parties clearly did not intend to give Vari-bus the right to cancel this 10-year contract in the event South Hampton . . . failed to complete construction of shore tanks.”

It is obvious that our preliminary inquiry must be to determine what the parties intended would constitute the “Terminal” when it was completed. There is no ambiguity in the instrument.

Plaintiff pleaded, verbatim, the provisions of Sec. 1.04 of the Contract (footnote 1, supra), which required it to construct “SELLER’S Terminal and tankage”, the combined capacity at the terminal and its refinery “shall include heated storage capacity for a minimum of one hundred ten thousand (110,000) barrels of Product.”

Plaintiff pleaded that prior to December 31, 1975, it had completed construction of heated tank storage at its refinery of approximately 53,000 barrels, a pipeline from the refinery to the terminal and 86,000 “barrels of barge storage at the terminal

It also alleged that on December 31,1975, it “was then ready and able to perform the primary intent and purpose of the contract

[159]*159Plaintiff stipulated in open court that on January 1, 1976, “no shore tanks were constructed at this facility”, the terminal. Additionally, numerous pictures taken subsequent to January 1 disclose very clearly that no tanks had been constructed at the terminal.

Executive vice-president Dana of South Hampton, the man primarily in charge of the dealings with Varibus, was interrogated concerning the building of storage tanks at the terminal, and one question and answer is important:

“Q. .. . Isn’t it true that this contract required South Hampton to construct at seller’s terminal at least one shore tank from which deliveries are to be made into vessels or barges of the buyer?
“A. I believe that we intended and ultimately did build one shore tank, yes, sir.”

Mr. Dana was also questioned as to the facilities in place at the terminal on January 1,1976, whereby the quantity and quality of the product could be determined by “shore tank strappings and shore tank sample” as provided in Sec. 1.05(a) of the contract. This brought about a judicial stipulation “that there was no way on January 1 that the quantity and quality could be determined from shore tanks at seller’s terminal.”

The last bit of testimony introduced by either party came from plaintiff’s officer Dana when cross-examined with reference to the construction of shore tanks at the terminal:

“Q. Have you had plans when you signed this contract to have those [shore tanks] completed by January 1, 1976?
“A. I believed we hoped to.”

Answers to requests for admissions also established that “there were no facilities at said terminal to maintain the Product at a minimum of 125° F. and 200° F maximum temperature” and that the “Product in barges was not maintained at the heated temperature.”

From our review of the voluminous record, only some of which is set out herein, we are of the opinion that plaintiff had not complied with the terms of the contractual provision found in Sec. 1.04 (footnote 1), nor had it constructed storage tanks by which tank strappings and shore tank samples could determine the quantity and quality of the product to be delivered to the defendant.

The broad and all-inclusive language used by the parties in the cancellation clause relied upon by the defendant is dispositive of the question.

In Crystal City v. Lo-Vaca Gathering Co., 535 S.W.2d 722, 724 (Tex.Civ.App.—El Paso 1976, writ ref’d n. r. e.), the court reviewed many of the Texas decisions on the subject, holding:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
623 S.W.2d 157, 1981 Tex. App. LEXIS 4344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/varibus-corp-v-south-hampton-co-texapp-1981.