Vandivier v. Tye

21 S.W.2d 1006, 231 Ky. 630, 1929 Ky. LEXIS 333
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 22, 1929
StatusPublished
Cited by5 cases

This text of 21 S.W.2d 1006 (Vandivier v. Tye) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vandivier v. Tye, 21 S.W.2d 1006, 231 Ky. 630, 1929 Ky. LEXIS 333 (Ky. 1929).

Opinion

Opinion op the Court by

Commissioner Tinsley—

Affirming

The appellant, as plaintiff below, instituted this suit against the appellees, as defendants below, to recover a balance of $1,080 claimed to be due for rent of a steam shovel leased to them by written contract dated November 20, 1924, under which they took possession on that day, and for which they agreed to pay at the rate of $450 per month, alleging that they returned the shovel to him on September 12, 1925, and that the total amount of rent was the sum of $4,380, of which sum they had paid $3,300, and that there was due the balance sued for.

The defendants filed answer and counterclaim, in which they admitted execution of the contract, that they took possession of the shovel on November 20, 1924, and retained it until September 12, 1925; but denied there was due plaintiff for rent of the shovel during the time *632 they had it in possession the sum of $4,380, or any sum in excess of $2,700, and denied there was due plaintiff a balance of $1,080 or any sum or amount.

By way of counterclaim, they asserted that, at the time they made the contract sued on, they were engaged in road construction work in this state; that shortly after making the contract the state highway commission of Kentucky, under which defendants were working, gave notice that there would be no further payments made for road work until the spring of 1925, and until further notice from the commission; that, when this notice was given, they and appellant modified the contract between them, by which it was agreed that appellant would make no charge against them for the steam shovel, nor expect them to pay for its use, until the highway commission resumed payments on road construction work; that, at the time the highway commission gave the notice referred to, they had not received the steam shovel from the railroad company, and would not have received it, but would have returned it to appellant immediately, but for the modification of the contract by which they were relieved from paying for the shovel until the highway commission resumed payments for construction work; that, after the contract was so modified, they received and unloaded the shovel, and took care of it until they were permitted to resume work; that they began work and commenced to use the shovel on March 12, 1925, and returned it to appellant September 12, 1925, using the shovel for a period of six months, for which the rental aggregated the sum of $2,700.

They further pleaded that they had lost or misplaced their copy of the contract, and, when they began to ,use the shovel, they were under the impression they were to pay for it $550 per month, and that, under that impression, they paid appellant $550 per month for the six months they used the shovel, aggregating $3,300, and by mistake paid him $600 more than he was entitled to receive from them, for which sum they sought judgment. They, further pleaded that they loaded the shovel on the railroad car for appellant, and for which he agreed and promised to pay them, $93.38; and that they sold plaintiff a casting for. a boom clasp, for which he promised to pay them $25, and they sought judgment against him for these sums. A demurrer'to the second paragraph of the answer and counterclaim having been overruled, appellant filed reply. Upon the trial, verdict *633 was returned for appellees for the sum of $600 on their counterclaim, and, from the judgment thereon and dismissing the petition, this appeal is prosecuted.

1. The first ground of complaint is that the court should have sustained the demurrer to the counterclaim. The petition declared upon a written contract. The answer and counterclaim pleaded an oral modification of the contract. It is now insisted that modification cannot be had except upon grounds of fraud or mistake, and then only as to consideration. In this contention counsel are in error. It is a well-settled rule that a contract not required to be in writing may be discharged, waived, abandoned, or modified by subsequent oral agreement, and that the parol evidence rule does not exclude oral testimony to establish the fact in a proper case. 6 R. C. L. sec. 299, p. 915; Chiles v. Jones, 3 B. Mon. 51; King Co. v. L. & N. R. R. Co., 131 Ky. 46, 114 S. W. 308; Murray v. Boyd, 165 Ky. 625, 177 S. W. 468; Covington, etc., v. Melvin, 197 Ky. 573, 247 S. W. 714.

The contract sued on was not required to be in writing. Hence it could be modified by subsequent parol agreement. The fact, as is shown by the evidence, that, after the modification of the contract, appellees unloaded the shovel and took care of it during the winter, and relieved appellant of that trouble and expense, is a sufficient consideration for the modification. Paducah Grain & Elevator Co. v. Marshall, 196 Ky. 673, 246 S. W. 30.

2. It is next complained that the court erred in denying to appellant the burden of proof. Section 526 of the Civil Code of Practice provides that the btirden shall be upon the party “who would be defeated if no evidence were given on either side;” and appellant insists that, inasmuch, as he sued to recover a balance of $1,080, and appellees denied that there was a balance of that sum or any sum or amount, due appellant, if no proof had been introduced, he would have been defeated, and therefore the burden was upon him. Ordinarily, this contention would be correct. In this case, however, after admitting the contract sued on, the defendants sought to avoid it by pleading that, after its execution, the parties to it so modified it that not only was the amount claimed by plaintiff- not due or owing, but that they had in fact, by mistake, paid plaintiff more than was due him.

In the case of Whitteker v. Holcomb, 177 Ky. 790, 198 S. W. 533, 534, it is said that the general rule as rec *634 ognized by the common law, and which the section of the Code, supra, but re-enacts, is stated in 16 Cyc. 929, thus:

“Should defendant not traverse, generally or specifically, the allegations of plaintiff’s case, but on the contrary rely upon affirmative defense in abatement, or confession and avoidance which plaintiff denies, the burden of proof is on the defendant to prove every matter alleged relied on by him.”

The defense in this case is an affirmative one—a defense of the nature of confession and avoidance'—and squarely within the rule above set forth. When defendants admitted the execution of the contract sued on and the retention of the shovel in their possession for the time alleged in the petition, had no proof been introduced, plaintiff would have been entitled to a judgment on the pleadings. Consequently, it was not error to adjudge the burden upon appellees. Whitteker v. Holcomb, supra; Home Insurance Co. v. Johnson, 226 Ky. 594, 11 S. W. (2d) 415; Colker v. Connecticut Fire Ins. Co., 224 Ky. 837, 7 S. W. (2d) 502.

3. The court gave to the jury five instructions. By No. 1 the jury were told to find for the plaintiff (appellant) the sum of $1,080, unless they should believe that the written contract was subsequently modified so as that defendants (appellees) were only to pay for the shovel while in use, and were not to pay for it whilst the highway department had suspended operations. By No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blair v. Louisville & Nashville Railroad
390 S.W.2d 178 (Court of Appeals of Kentucky, 1965)
Massachusetts Mutual Life Insurance v. Sexton
74 S.W.2d 206 (Court of Appeals of Kentucky (pre-1976), 1934)
Wallis v. Illinois Central Railroad Co.
56 S.W.2d 715 (Court of Appeals of Kentucky (pre-1976), 1933)
Dwiggins v. Howard
57 S.W.2d 649 (Court of Appeals of Kentucky (pre-1976), 1932)
W. H. Simmons & Co. v. Price's Administrator
38 S.W.2d 6 (Court of Appeals of Kentucky (pre-1976), 1931)

Cite This Page — Counsel Stack

Bluebook (online)
21 S.W.2d 1006, 231 Ky. 630, 1929 Ky. LEXIS 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vandivier-v-tye-kyctapphigh-1929.