Vandevort v. Thompson-Starrett Co.

182 F. 875, 1910 U.S. App. LEXIS 5676
CourtU.S. Circuit Court for the District of Western Pennsylvania
DecidedNovember 2, 1910
DocketNo. 76
StatusPublished
Cited by1 cases

This text of 182 F. 875 (Vandevort v. Thompson-Starrett Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Western Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vandevort v. Thompson-Starrett Co., 182 F. 875, 1910 U.S. App. LEXIS 5676 (circtwdpa 1910).

Opinion

YOUNG, District Judge.

This is a motion for judgment for defendant non obstante veredicto. At the trial the court directed judgment to be entered for plaintiff for the full amount of his claim and interest. The defendant requested the court, by a point submitted, to instruct the jury to find for the defendant, which was refused. Under the facts admitted by the pleadings, or uncontradicted in the case, there was nothing to be left to the jury, because the whole case turned upon the interpretation of the contract sued upon. It is conceded that, if the court was right in its interpretation of the contract, the verdict must be for the plaintiff. Equally, if the court was wrong in its interpretation of the contract, there was nothing for the jury, and the verdict must be for the defendant. This whole case may therefore' be disposed of upon this rule for judgment non obstante veredicto.

In order that the case may be clearly understood, it is necessary to state certain facts which appear by the pleadings and evidence. The suit was brought by N. A. Vandevort, the plaintiff, against the Thompson-Starrett Company, the defendant, upon the following contract :

“Memorandum of agreement, made this fourth day of March, 1908, by and between N. A. Vandevort, of Pittsburg, Pennsylvania, and Thompson-Star-rett Company, óf New York, New York:
“I. N. A. Vandevort hereby agrees to expedite the deliveries of-structural steel for Thompson-Starrett Company, including cast-iron columns and bases, with the exemption expressed in paragraph III of this agreement, for a period of two years, commencing April 1, 1908, with the privilege to either party to terminate this agreement within one year by giving written notice to the other party on or before December 31, 1908; it being further agreed by N. A. Vandevort that if, for just cause, his services under this agreement are unsatisfactory and unacceptable to Thompson-Starrett Company, this agreement is terminable upon the part of Thompson-Starrett Company upon the giving of thirty days’ written notice to N. A. Vandevort of Thompson-Star-rett Company’s intention to terminate this agreement upon the date stated in said written notice.
“II. It is mutually understood and agreed by and between -N. A. Vande-vort and Thompson-Starrett Company that the services of N. A.. Vandevort covered by this agreement are as follows: Generally, the securing of the delivery of the structural steel and cast iron necessary in Thompson-Starrett Company’s business, at the times and in the manner required by Thompson-Starrett Company; supervising the entering of the rolling lists and follow-[877]*877Jng them through the fabricating company’s offices and the rolling mills, until the plain material has been delivered at the shops of the fabricating company ; to supervise the making of shop drawings,' the fabrication and shipment of iinislied material, and, where necessary, to trace cars and expedite movement of such cars to destination; to keep in communication with Thompson-Starrett Company through its chief engineer, reporting once weekly, or whenever requested, the condition of the work at the mills and. in the shops as to plain and finished material.
“III. Ifor and in consideration of the services above described, Thompson-Starrett Company agrees to pay N. A. Vandevort, at the rate of forty cents (40⅜ per ton of 2,000 pounds, and to give to N. A. Vandevort all its tonnage, including cast-iron columns and bases, with the exception of such cast-iron columns and bases, obtained outside a territory inclosed by a radius of fifty (50) miles from Pittsburg, Pennsylvania.
“IV. Thompson-Starrett Company hereby agrees that not over one-tliird of its total tonnage, covered by this agreement, will be placed outside of the Pittsburg territory above described.
“V. If more than one-third of Thompson-Starrett Company’s entire tonnage, exclusive of the cast-iron columns and bases exempted under paragraph III of tills agreement, is placed outside of the said Pittsburg territory, Thompson-Starrett Company agrees to pay N. A. Vandevort at the rate of fifty-five cents (55⅜ per ton of 2,000 pounds on such excess tonnage over the one-third of the total tonnage placed outside the said Pittsburg territory; the adjustment as to such excess tonnage to be made the 1st day of xlpril of each year.
“VI. Thompson-Starrett Company agrees to make payments for the material expedited not later than the fifteenth (]5th) day of each calendar month for the tonnage of finished material shipped during the preceding month.
“In witness whereof, the parties hereto subscribe their respective names.”

In performance of this contract the plaintiff expedited, as he was required to do under the contract, the deliveries of structural steel for all such contracts of Thompson-Starrett Company, except the Wanamaker contract hereinafter referred to, and he was paid for those services. It appears that during the time of this contract, -namely, between April 1, 1908, and April 1, 1909, the Thompson-Star-rett Company had a partially unperformed contract, made April 25, 1904, for the Wanamaker Building in the city of Philadelphia, under which contract the defendant company was to unload, store, haul, erect, and paint the structural steel in a building to be erected, etc., and that the plaintiff knew at the time he entered into the agreement that the defendant had this contract, and that it was unperformed as to the third section; that the contract did not include the furnishing of the steel for the building, and that the steel was being furnished by the American Bridge Company at Philadelphia. It also appears from the evidence that between April 1, 1908, and April 1, 1909, the defendant performed the work and erected the material provided for by the contract to the amount set out in the plaintiff’s claim. It appears, also, from the contract sued upon and from the evidence in the case, that the services to be performed by the plaintiff in expediting deliveries of structural steel meant the supervising of the entering of the rolling lists and following them through the fabricating company’s ^offices and the rolling mills, until the plain material has been delivered at the shops of the fabricating company, and supervision of the making of shop drawings, the fabrication and shipment of finished material, and, where necessary, the tracing of cars, expediting the movement of such cars to destination, and keeping in communication with

[878]*878Thompson-Starrett Company through its chief engineer, reporting once weekly, or whenever requested, the condition of the work at the mills and in the shops as to plain and finished material. The necessity of expediting deliveries is seen from the following evidence:

“Q. Mr. Cadmus, wliy should the erector require the delivery of the steel or iron at certain times and in proper sequence? A. Well, the erector in charge of the construction of a building of that nature, a large construction, necessarily plans his work in advance, very much in advance. He has got to meet the conditions which enable him to not only erect his work cheaply, economically, keep his full force going, all his erection outfit in use, but at the same time he has got to- work in such a way that the allied trades will not be delayed if they are following closely on the work he is erecting. The stone masons, brick men, concrete floor men, and so on, must necessarily be taken care of in an erection of that kind.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sarnia Steamships, Ltd. v. Continental Grain Co.
125 F.2d 362 (Seventh Circuit, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
182 F. 875, 1910 U.S. App. LEXIS 5676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vandevort-v-thompson-starrett-co-circtwdpa-1910.