Vandervoort v. Levy

396 So. 2d 480, 1981 La. App. LEXIS 3681
CourtLouisiana Court of Appeal
DecidedMarch 10, 1981
Docket11728
StatusPublished
Cited by5 cases

This text of 396 So. 2d 480 (Vandervoort v. Levy) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vandervoort v. Levy, 396 So. 2d 480, 1981 La. App. LEXIS 3681 (La. Ct. App. 1981).

Opinion

396 So.2d 480 (1981)

H. A. H. VANDERVOORT, Sr.
v.
Charles A. LEVY, Jr.

No. 11728.

Court of Appeal of Louisiana, Fourth Circuit.

March 10, 1981.

*481 LaBorde & Brooks, Gerald Thos. La-Borde, New Orleans, for plaintiff-appellee.

Eric Oliver Person, New Orleans, for defendant-appellant.

Jefferson, Bryan & Gray, Trevor G. Bryan, New Orleans, for defendant-appellee.

Before GULOTTA, CHEHARDY and KLIEBERT, JJ.

*482 GULOTTA, Judge.

These three consolidated suits arose out of the renovation of a residence. In the first-filed matter,[1] H. A. H. Vandervoort, the architect, seeks professional fees from the homeowner, Charles A. Levy, Jr. The owner reconvened for costs of decorations and renovation caused by the architect's defective performance, and for pain and suffering, mental anguish and humiliation resulting from the filing of a lien against the residence by the contractor, Andrew P. Allain, d/b/a Allain Construction Co., for unpaid services. In the second suit,[2] claim is made by the owner against the architect for damages based on allegations similar to those made in reconvention in the first-filed suit. Thereafter, the general contractor filed a third suit against the owner and the architect to enforce a privilege against the residence for unpaid labor and materials.[3] The owner reconvened against the contractor; and both the owner and the architect third-partied each other.

After consolidation, the matter was referred to a commissioner and judgment was rendered, in accordance with the Commissioner's report, in favor of the contractor and against the owner for $7,167.51. This amount represents the extra work performed by the contractor on the renovations. All other main and incidental demands were dismissed.

On appeal, the homeowner contends the trial judge erred in holding him liable to the contractor since there was no privity of contract between them. He further argues if any amount is owed to the contractor it is the architect's liability since the architect employed the contractor, supervised him during the course of the work, and received a profit based on the contractor's work. Finally, the homeowner contends extra work was performed without his knowledge or consent and this unauthorized work is the responsibility of the architect or contractor. In answer to the appeal, the contractor claimed that the judgment, though correct as to liability, should be increased to $12,744.51. The architect has neither appealed nor answered the appeal.

BACKGROUND

In 1972, Mr. and Mrs. Charles A. Levy, Jr. contacted the architect, Vandervoort, for the purpose of making improvements on their home. Initially contemplated by the homeowners were soundproofing and carpet installation. Vandervoort submitted a bid of $7,000.00, but after discussions with the Levys the scope of the renovation broadened considerably to include new furniture and extensive interior and exterior renovation at a proposed cost of approximately $31,000.00. Vandervoort and the Levys held extensive discussions, but no written contract was entered into between them.

Vandervoort prepared a list of specifications dated September 18, 1972, which set forth the scope of the work to be performed.[4] Thereafter the architect contacted Andrew P. Allain and obtained a bid from him of $8,480.00 as the cost of the contracting work. According to the testimony of Allain's supervisor on the Levy job, the $8,480.00 figure was not a fixed price for the contracting work but was a "budget" figure assigned to him. In an October 27, 1972 letter from Vandervoort to the Levys in which the proposed work is itemized at a total figure of $31,192.55,[5] however, *483 the $8,480.00 figure is listed as an "upset" price of the contractor.

Although it is not clear from the record, it appears that Allain began the renovation on the Levy residence sometime in November, 1972. With the exception of the first month of construction, Vandervoort apparently was at the job site at least twice a week at a minimum during the course of the project.

Levy testified that he advanced $8,000.00 to Vandervoort but had no written document or plans. Sometime between October 20 and December 15, 1972 Levy received the plans and specifications, but did not read them at that time because of his concern for his wife's health. Work continued on the project, however, and Levy made periodic payments to Vandervoort as requested.

In the course of the renovation, Allain's crew and sub-contractors hired by Allain performed, without written change orders, certain "extra" work not included in the Vandervoort specifications. According to Allain's supervisor, all the extra work was authorized orally by Vandervoort. Vandervoort stated that certain extras had been approved by the Levys or had been done by Allain on his own initiative. Levy, on the other hand, testified that with the exception of some minor items, he did not authorize any extra work.

While the work continued in the latter part of February, 1973, the Levys took a vacation out of the country. Upon their return, the relationship among the parties deteriorated. At that time the Levys had paid out $29,000.00 but were unsatisfied with the work performed and concerned about the added expenses. Vandervoort thereupon audited the invoices submitted by Allain for payment and prepared an itemization of various changes, additions and substitutions to the specification document of September 18, 1972.

According to the Vandervoort audit, Allain invoiced a total of $23,955.20 for labor and material through March 1, 1973. Vandervoort determined that the correct figure for work performed by Allain was $19,572.87. Since Allain had already been paid $12,000.00, a balance of $7,572.87 was still owed according to Vandervoort.[6]

The Levys refused to make any further payments and work was terminated. Levy testified, however, that he later obtained a new contractor and interior decorator who started on the job in September, 1973 and finished it to his satisfaction on December 21, 1973 at a total cost of $30,900.00 for the new work. This litigation followed.

The Commissioner's report adopted by the trial judge, states, in pertinent part:

"The Court finds that no contract of any type existed between the owner and the architect which would guarantee an upset price to the owner....
Allain kept time records for his employees and material records for materials used. Some of the work ... was encompassed within the original bid submitted by Allain to Vandervoort of $8,480.00. *484 Other work was performed as extras either at the request of the owner, his wife, the architect, or was performed by Allain himself.
The architect went over the invoices from Allain and established that there was a variance between the amounts charged by Allain, the amount contractually agreed to by Allain, and the extra work performed by Allain and that work which Mrs. Levy directly ordered from Allain's employees.
The amount ... due and owing is $7,572.87 and the Court should recognize that a lien and privilege exists for such amount, subject to further credits outlined below.
While there exists controversy as to who exactly authorized such work, there is no doubt in the Court's mind that the work was indeed performed and that its performance was adequate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gray v. McCormick
663 So. 2d 480 (Louisiana Court of Appeal, 1995)
SOUTH CENT. BELL TELEPHONE v. Rouse Co.
590 So. 2d 801 (Louisiana Court of Appeal, 1991)
Vega v. Off The Wall Racquet & Health Club, Inc.
481 So. 2d 153 (Louisiana Court of Appeal, 1985)
Mattix v. Ranna
427 So. 2d 584 (Louisiana Court of Appeal, 1983)
Orleans Onyx, Inc. v. Buchanan
428 So. 2d 841 (Louisiana Court of Appeal, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
396 So. 2d 480, 1981 La. App. LEXIS 3681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vandervoort-v-levy-lactapp-1981.