Valley Stream Flooring Corp. v. Green Manor Construction Co.

233 F. Supp. 608, 1963 U.S. Dist. LEXIS 9782
CourtDistrict Court, D. Massachusetts
DecidedJune 13, 1963
DocketCiv. A. No. 59-452
StatusPublished
Cited by2 cases

This text of 233 F. Supp. 608 (Valley Stream Flooring Corp. v. Green Manor Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Stream Flooring Corp. v. Green Manor Construction Co., 233 F. Supp. 608, 1963 U.S. Dist. LEXIS 9782 (D. Mass. 1963).

Opinion

FRANCIS J. W. FORD, District Judge.

This is an action by a subcontractor against the general contractor for a housing contract in which plaintiff seeks to recover from defendant and the surety on its payment bond the value of labor and materials furnished for which it alleges it has not been paid. Defendants counterclaim against plaintiff and the surety on its performance bond for damages for alleged breach of the subcontract by the plaintiff.

On May 20, 1958 defendant Green Manor Construction Co., Inc. (Green Manor) entered into a contract with the Air Force for the construction of 395 [609]*609housing units for Air Force personnel at Laurence G. Hanscom Field, Bedford, Massachusetts. Some of the buildings were to be single-family units, others were to contain two or four family units. For convenience the project was divided into areas designated Mortgage Areas A, B and C, corresponding to the division of the project for purposes of financing the work. Sometime thereafter negotiations took place regarding the giving of the subcontract for the installation of flooring in these units to Valley Stream Flooring Corporation (Valley Stream) but it does not appear that the contract drawn up was ever executed.

On July 26, 1958 a subcontract for the flooring installation was executed by Green Manor and Valley Stream. This contract called for the installation of Cromar pre-finished flooring in place of the flooring called for by the original specifications for the project. The use of this flooring was approved by the Air Force with a provision that “Any un-eveness (Sic) of the floor level will not be tolerated, if the top (Sic) of adjacent boards are not even, the contractor will be compelled to sand the floor levels and refinish it to match the rest of the floor.” Cromar flooring was installed in a few units and these floors were rejected by the Air Force because of the unevenness of the floors. On September 13, 1958 a new contract was executed between the parties, providing for the use of the oak and beech flooring called for by the original specifications.

Some 460,000 feet of Cromar lumber had been ordered for use on the project by Valley Stream and had been delivered to the site. Subsequently the Cromar Company recovered judgment against Valley Stream and its surety in an action for the unpaid price of this lumber. In its supplemental complaint Valley Stream seeks to recover from defendants here the damages it was compelled to pay to Cromar, on the ground that the rejection of Cromar floors was caused by the faulty construction of the subflooring and joints by Green Manor.

It is true that physically the cause of the unevenness of the installed Cromar flooring was the unevenness of the sub-flooring and the joists. However, the sub-flooring and joists had been accepted by the Government inspectors, and there is no evidence that they did not fully conform to the specifications of the prime contract. They were satisfactory for the installation of the unfinished oak and maple flooring originally called for by the specifications. Of course, the same unevenness was found in this flooring when installed, but this flooring was intended to be sanded and finished after installation and any irregularities were removed by the sanding so that a satisfactorily even floor resulted. The difficulty with the use of Cromar flooring was that it was not adapted to be used in this particular construction. It is true that the Cromar flooring could have been made acceptable by sanding and refinishing after installation but this would have involved additional expense. The chief reason for using Cromar flooring was, however, to eliminate the work of sanding and finishing after installation, and it was not unreasonable for Green Manor to return to the type of flooring required by the original specifications when the use of Cromar flooring was found to be unsatisfactory. Both parties to the July 26 contract knew that the use of the Cromar flooring was experimental and conditional upon its being found practical to install a floor with Cromar lumber which would meet with Air Force approval. The inability to do so was due to the fact that Cromar was not adapted to use under the conditions found in this project and not to any fault of Green Manor in the installation of the sub-flooring. Any loss suffered by Valley Stream cannot be attributed to any default of Green Manor and hence cannot be charged to defendants.

Plaintiff’s claim in its original complaint is based on the contract of September 13, 1958 under which Valley Stream was to install the flooring in the housing units of the project in strict [610]*610accordance with the plans, specifications and contract documents for a total price of $137,500. Valley Stream was instructed to begin work on October 1, the work to be completed by December 1. Lumber ordered by Valley Stream began to arrive on October 2 and the laying of the flooring began on the next day. Work was not completed by December 1 but defendants appear to make no contention based on this failure and at least as of December 4 Green Manor wrote to Valley Stream expressing satisfaction with adherence to the schedule up to that date.

In December in the course of sanding operations it was found that cracks had developed in some of the flooring laid by Valley Stream. On December 31 and again on January 5, 1959 flooring in which cracks had appeared was ripped up by order of Green Manor’s superintendent, Filloramo, and it was found that the boards had not been nailed according to specifications. The government inspectors refused to accept flooring in which cracks had appeared and Green Manor directed Valley Stream to rip up and relay these floors. Valley Stream took the position that the cracks were caused by conditions for which Green Manor was responsible and that Green Manor should bear the expense of replacing these floors. On January 7, 1959 after several meetings of representatives of the parties to discuss their dispute, Valley Stream pulled its men off the job and later that day sent a letter to Green Manor giving notice of termination of the contract, alleging as grounds for its action failure of Green Manor to pay requisitions when due, ripping up floors without notice to Valley Stream, and ripping up flooring in such manner as to destroy the same and prevent salvage thereof.

Valley Stream contends that it was justified in terminating work under the contract on January 7, 1959 because Green Manor was then in default of its obligations under the contract. Green Manor contends that it was not in default, that Valley Stream defaulted on its obligations under the contract and that Green Manor is entitled to recover damages for the additional expense it suffered in repairing defects chargeable to Green Manor and in completing performance of the contract.

The flooring installed by Valley Stream was in some units oak and in some units beech. The specifications called for the use of No. 1 clear oak or 1st grade beech. Of the beech purchased by Valley Stream and used in this installation 105,000 feet was first grade and 81,000 feet was of the grade described as “second or better” consisting of some boards of first grade and some of second grade. Use of this second grade beech was a violation by Valley Stream of its duty under the contract to install flooring in conformity to the specifications.

The specifications required that flooring be nailed with a nail in every joist. Bidnick, Valley Stream’s supervisor at the job site, admitted that some unskilled floor layers were employed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
233 F. Supp. 608, 1963 U.S. Dist. LEXIS 9782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-stream-flooring-corp-v-green-manor-construction-co-mad-1963.