Valley Forge Insurance Company v. Washington Square Hotel Holdings, LLC

CourtDistrict Court, W.D. Washington
DecidedFebruary 4, 2022
Docket2:21-cv-00847
StatusUnknown

This text of Valley Forge Insurance Company v. Washington Square Hotel Holdings, LLC (Valley Forge Insurance Company v. Washington Square Hotel Holdings, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Forge Insurance Company v. Washington Square Hotel Holdings, LLC, (W.D. Wash. 2022).

Opinion

1 2 3

4 5 6 7 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON 8 AT SEATTLE

9 10 VALLEY FORGE INSURANCE CASE NO. C21-0847JLR COMPANY, et al., 11 ORDER Plaintiffs, 12 v.

13 WASHINGTON SQUARE HOTEL HOLDINGS, LLC, 14 15 Defendant.

16 I. INTRODUCTION 17 Before the court is Plaintiffs Valley Forge Insurance Company (“Valley Forge”) 18 and Continental Casualty Company’s (“Continental”) (collectively, “Plaintiffs”) motion 19 for summary judgment. (Mot. (Dkt. # 15); Reply (Dkt. # 21).) Defendant Washington 20 Square Hotel Holdings, LLC (“WSHH”) opposes the motion and asks the court to 21 continue this matter under Federal Rule of Civil Procedure 56(d). (Resp. (Dkt. # 19) at 22 9-10.) The court has considered the parties’ submissions, the relevant portions of the 1 record, and the applicable law. Being fully advised,1 the court DENIES WSHH’s motion 2 for a continuance under Federal Rule of Civil Procedure 56(d) and GRANTS Plaintiffs’ 3 motion for summary judgment.

4 II. BACKGROUND 5 This declaratory judgment action arises out of the construction of a Hilton Garden 6 Inn hotel in Bellevue, Washington that began in 2015 (the “Project”). (See Compl. (Dkt. 7 # 2) ¶¶ 4.2-4.4; Answer (Dkt. # 10) ¶¶ 4.2-4.4.) WSHH, the owner of the Project, seeks 8 to recover losses allegedly caused by its former general contractor, Vandervert

9 Construction, Inc. (“Vandervert”), under two policies issued by Plaintiffs to Vandervert: 10 (1) a primary commercial general liability policy issued by Valley Forge (the “CGL 11 Policy”); and (2) an umbrella policy issued by Continental (the “Umbrella Policy”) 12 (collectively, the “Policies”). (See Compl. ¶¶ 4.2-4.4, 6.3-6.5; Answer ¶¶ 4.2-4.4; Bradix 13 Decl. (Dkt. # 17) ¶ 2, Ex. 3 (“CGL Policy”); Bradix Decl. ¶ 3, Ex. 4 (“Umbrella

14 Policy”).) 15 On July 15, 2015, WSHH contracted with Vandervert to act as the general 16 contractor of the Project with an expected substantial completion date of January 25, 17 2017 (the “Contract”). (Todaro Decl. (Dkt. # 16) ¶ 2, Ex. 1 at 1, 3; Todaro Decl. ¶ 3, Ex. 18 2.) Vandervert, in turn, subcontracted with Peter Winberg Construction Inc. (“PWCI”)

19 for rough carpentry and framing work on the Project. (Todaro Decl., Ex. 1 at 34; Todaro 20 //

21 1 None of the parties request oral argument (see Mot. at 1; Resp. at 1), and the court concludes that oral argument would not be helpful to its disposition of the parties’ submissions. 22 See Local Rules W.D. Wash. LCR 7(b)(4). 1 Decl. ¶ 11, Ex. 14 (“Reasonableness Mot.”) at 4).) PWCI began framing work on the 2 Project on February 18, 2016. (Reasonableness Mot. at 4.) On June 2, 2016, a City of 3 Bellevue inspector determined that PWCI’s installation of exterior sheathing was

4 deficient and required substantial correction. (See Todaro Decl. ¶ 6, Ex. 9 at 3.) The 5 following day, Vandervert notified PWCI that, as a consequence of its substandard work, 6 “water proofing and window installation” work had been halted and the Project was in 7 danger of missing its substantial completion deadline. (Id. at 2.) 8 Between June 14, 2016 and July 14, 2016, the Project received numerous

9 additional failed inspection notices related to PWCI’s work. (Id. at 5-11.) Without 10 correcting the flaws in its work, PWCI left the Project on or about July 21, 2016. (See 11 Todaro Decl. ¶ 7, Ex. 10 ¶ 7; Reasonableness Mot. at 5.) Vandervert replaced PWCI 12 with JC’s General Construction Co. on July 22, 2016. (Todaro Decl. ¶ 8, Ex. 11.) On 13 August 26, 2016, the City of Bellevue inspector found that framing on the Project had

14 been “covered without inspection and city approved plans,” and ordered Vandervert to 15 cease work on the Project, submit revised plans to the City for review and approval, and 16 to schedule additional inspections of those plans. (Todaro Decl. ¶ 9, Ex. 12 17 (capitalization omitted).) 18 Although a “watertight vapor barrier roofing membrane” had been installed on the

19 Project’s roof by the August 26, 2016 stop work date, “the remainder of the [Project’s] 20 [r]oofing [s]ystem remained to be installed.” (See Todaro Decl. ¶ 10, Ex. 13 at 2 21 (emphasis omitted).) Accordingly, the roof was not fully “dried in” and remained 22 incomplete when more than eleven inches of rain fell on Bellevue in October 2016, 1 including more than five inches between October 13 and 17, 2016. (See Todaro Decl. 2 ¶ 20, Ex. 23 at 1 (daily log reports from October 13 and 14, 2016); see also Todaro Decl., 3 Ex. 13 at 2; Todaro Decl. ¶ 12, Ex. 15 at WEST001013, WEST001021 (consultant report

4 describing water damage and noting that, “the roof was not fully sealed during 5 construction and rain water entered the building” in Fall 2016); Reasonableness Mot. at 6 6 (describing flooding and resulting damage).) 7 This rainfall “caused a substantial accumulation of standing water on the roof,” 8 which overwhelmed the “temporary water pumps” Vandervert had installed (Todaro

9 Decl., Ex. 13 at 2 (emphasis omitted)), and “flooded the Project, causing damage to” 10 heating, ventilation, and air conditioning (“HVAC”) work, as well as to electrical work 11 performed by other subcontractors (see Reasonableness Mot. at 5-6; see also Todaro 12 Decl., Ex. 15 at WEST001013, WEST001021, WEST001031 (describing damage from 13 flooding)). Bellevue also experienced significant winter storms around December 8 and

14 12, 2016, which resulted in further flooding and water damage to the Project. 15 (Reasonableness Mot. at 6.) 16 Vandervert “attempted to repair the damage to the work of its other subcontractors 17 and recover the Project schedule,” but nevertheless “continued to fall behind schedule 18 and accrue liability under [the Contract].” (Id.) Vandervert and WSHH thus executed an

19 addendum to the Contract, which extended the Project’s completion date to October 31, 20 2017, and set the amount of liquidated damages for delay beyond that date to $14,800 per 21 day. (Id. at 6-7; Todaro Decl. ¶ 4, Ex. 5 §§ 3-4 (addendum).) Vandervert failed to 22 // 1 complete the Project by that deadline and was ultimately terminated by WSHH on 2 February 1, 2018. (Todaro Decl. ¶ 13, Ex. 16.) 3 In connection with the Project, WSHH had purchased two builders risk policies

4 from Darwin National Assurance Company and Westchester Fire Insurance Company. 5 (See Todaro Decl. ¶ 14, Ex. 17 at 1; id. at n.1.) On January 23, 2017, WSHH notified its 6 insurers that it was seeking coverage under these policies for losses related to repairing 7 the water damage and associated delays in the Project’s completion. (See id. at 2.) On 8 April 27, 2018, WSHH’s insurers advised WSHH that they had determined, after

9 conducting a “preliminary coverage analysis,” that the builders risk policies did not 10 provide coverage for losses stemming from the water damage repairs or associated 11 Project delays. (See id. at 5-7.) 12 On February 2, 2018, Vandervert, which had been terminated by WSHH from the 13 Project the day before (Todaro Decl., Ex. 16), entered receivership in Spokane County

14 Superior Court (see Todaro Decl. ¶ 15, Ex. 18 (appointing Barry W. Davidson as 15 Receiver)). WSHH submitted a claim against Vandervert in the receivership proceeding 16 for $7,772,904.32 in damages related to an alleged “Breach of Contract.” (See Todaro 17 Decl. ¶ 16, Ex. 19 (the “Claim”) at 1.) The Claim included liquidated damages, damages 18 relating to the amount required to complete the Project, and legal fees. (Id. at 2.) The

19 Receiver tendered the Claim to Plaintiffs on Vandervert’s behalf on April 20 and 24, 20 2018, respectively, and sought coverage under the Policies. (Clapham Decl. (Dkt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brillhart v. Excess Insurance Co. of America
316 U.S. 491 (Supreme Court, 1942)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Texas v. United States
523 U.S. 296 (Supreme Court, 1998)
Coventry Associates v. Am. States Ins. Co.
961 P.2d 933 (Washington Supreme Court, 1998)
McDonald v. State Farm Fire & Casualty Co.
837 P.2d 1000 (Washington Supreme Court, 1992)
Queen City Farms, Inc. v. Central Nat'l Ins. Co. of Omaha
882 P.2d 703 (Washington Supreme Court, 1995)
Hayden v. Mutual of Enumclaw Ins. Co.
1 P.3d 1167 (Washington Supreme Court, 2000)
Meadow Valley Owners Ass'n v. St. Paul Fire & Marine Ins. Co.
156 P.3d 240 (Court of Appeals of Washington, 2007)
Schmidt v. Cornerstone Investments, Inc.
795 P.2d 1143 (Washington Supreme Court, 1990)
Tony Martinez v. Columbia Sportswear USA Corp.
553 F. App'x 760 (Ninth Circuit, 2014)
Leesa Jacobson v. Usdhs
882 F.3d 878 (Ninth Circuit, 2018)
Western National Assurance Co. v. Shelcon Construction Group, LLC
332 P.3d 986 (Court of Appeals of Washington, 2014)
Bancroft v. Minn. Life Ins. Co.
329 F. Supp. 3d 1236 (W.D. Washington, 2018)
Pryor v. Bishop
234 F. 9 (Seventh Circuit, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
Valley Forge Insurance Company v. Washington Square Hotel Holdings, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-forge-insurance-company-v-washington-square-hotel-holdings-llc-wawd-2022.