Valerio v. Andrew Youngquist Construction

127 Cal. Rptr. 2d 436, 103 Cal. App. 4th 1264
CourtCalifornia Court of Appeal
DecidedDecember 3, 2002
DocketA094096
StatusPublished
Cited by60 cases

This text of 127 Cal. Rptr. 2d 436 (Valerio v. Andrew Youngquist Construction) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valerio v. Andrew Youngquist Construction, 127 Cal. Rptr. 2d 436, 103 Cal. App. 4th 1264 (Cal. Ct. App. 2002).

Opinion

Opinion

CORRIGAN, J.

Appellant challenges a judgment based on a finding that there was no contract between the parties and allowing quantum meruit recovery. Appellant claims the court erred in ignoring respondent’s judicial admissions that a contract existed. We reverse.

Factual and Procedural Background

Appellant, a general contractor, did business as Birtcher Construction Services (Birtcher). Birtcher solicited bids from subcontractors to build the Brenden Theater complex in Vacaville. Respondent Bart Valerio was awarded the painting subcontract, knowing that he would be required to submit a performance bond. Birtcher sent Valerio two original agreements to be initialed on each page, signed and return to Birtcher. The letter informed Valerio that a “duly executed original will be returned to you for your files.” Valerio was also told to submit his performance bond. Valerio returned the *1267 initialed and signed contract. Birtcher wrote Valerio that it had received the contracts, but still needed the performance bond “in order to process and execute.” As Valerio understood Birtcher’s letter, Birtcher had not executed the contract.

Heavy rains delayed construction progress. Valerio began working at the end of June or beginning of July, even though he had not received an executed contract. He received another letter from Birtcher on July 8, 1998, marked “second request,” advising him that the performance bond was required. The letter stated that “[a]n incorrect insurance certificate will hold up execution of the contract and any payments.” Valerio continued working on the project. On August 24, 1998, he received a fax transmittal from Birtcher advising him of two change orders “pending issuance due to an unexecuted contract (waiting for bonds, etc.)” and asking Valerio to follow up on outstanding contract requirements. On September 3, 1998, Birtcher informed Valerio that if he did not complete the exterior painting by September 4, Birtcher would bring in additional painters to supplement Valerio’s crew. The contract Valerio signed entitled Birtcher to do so at Valerio’s expense. On September 8, these workers were brought in to complete the job. On September 25, 1998, Valerio received a final fax transmittal from Glenn Reindahl, Birtcher’s project engineer, referring to the other painting contractor hired to finish the project. The fax suggested that Valerio would be charged for that contractor’s invoices and stated, “However, all this is irrelevant if you do not provide the required bond so we may execute your contract. Remember, NO BOND + NO CONTRACT=NO PAYMENT.” During the entire time Valerio worked on the project, he did not provide the performance bond, receive an executed contract or get paid.

Valerio sued, alternatively alleging breach of express written contract and quantum meruit. Birtcher filed a compulsory cross-complaint, and Valerio answered. The matter was tried to the court which found there was no written agreement between the parties. The court denied Birtcher’s motion for a new trial and awarded Valerio attorney’s fees.

Birtcher claims the court’s finding that no written contract existed is erroneous in that it ignores Valerio’s express admissions to the contrary and relies on inadmissible evidence.

Discussion

Birtcher contends the court failed to give conclusive effect to Valerio’s judicial admissions regarding the existence of a written contract. We agree.

A. Background

In Valerio’s answer to Birtcher’s cross-complaint for breach of contract, Valerio admitted the following allegation: “Birtcher entered into a written *1268 construction services trade contract with Bart Valerio, . . . which was signed by Bart Valerio on March 4, 1998. The essential terms of the contract were that Valerio was to perform waterproofing, caulking, and painting work and to provide the related supplies for the construction project in a timely and workman like manner, and was to provide a performance bond.”

Birtcher propounded requests for admissions pursuant to Code of Civil Procedure section 2033, and Valerio responded as follows: “The written contract between Bart Valerio . . . and Birtcher Construction for painting services at Brenden Theaters project in Vacaville required Bart Valerio to provide a performance bond [Response: Admitted.],” and “The written contract between Bart Valerio . . . and Birtcher Construction for painting services at Brenden Theaters project in Vacaville provide[d] that Birtcher retained] the right to supplement with other workers the work being done by plaintiff and to charge Bart Valerio the costs of the additional workers. [Response: Admitted, subject to further proviso that Valerio was not himself performing the work required under the contract.]”

Seven months before trial, Valerio stated in his February 10, 2000, trial management conference statement: “Only after having gathered together all of the documents and having digested the deposition testimony of Birtcher’s Operations Manager did the actual status of the contract become clear. Birtcher intentionally never signed the contract. Since there was no contract Valerio’s only claim is upon the second cause of action for work, labor, services and materials rendered on a quantum meruit basis.” Valerio did not move to dismiss the breach of contract claim, nor did he amend his answer to the cross-complaint or his responses to Birtcher’s request for admissions.

In its May 10, 2000, trial management conference statement, Birtcher stated: “The existence of the written contract is not in dispute. Valerio admitted to the existence of the written agreement in his complaint and in his answer to the cross-complaint, as well as in response to discovery demands.” Birtcher argued that Valerio was bound by his judicial admissions and discovery answers. Additionally, Birtcher advised: “No motions in limine are expected. However, while not offered as a formal motion in limine, the court should be aware of the evidentiary dispute that will arise if Valerio attempts to offer any evidence at trial that the written subcontract between Valerio and Birtcher is unenforceable . . . .” Birtcher pointed out that Valerio made judicial admissions in his cross-complaint and discovery responses. Accordingly, Birtcher argued that Valerio was bound by those admissions and prohibited from offering contrary evidence at trial. In his trial brief, filed on August 17, 2000, Birtcher again argued that Valerio was bound by his judicial admissions and “[a]s a matter of law, Valerio may not *1269 argue that there is no written contract between the parties concerning their respective duties and obligations on the Brenden Theater Project.” Again, after receipt of Birtcher’s conference statement and trial brief, Valerio did not amend his pleadings or discovery responses.

In closing argument, Valerio’s counsel described the issue before the court as follows: “[W]as there an express written contract between these parties or should the plaintiff be held to the fiction that there was an express written contract due to alleged admissions by the plaintiff?” Counsel argued that “if there is an explanation as why testimony is later given to the contrary [to the admissions], ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dini v. Dickinson CA6
California Court of Appeal, 2025
Estate of Fox CA6
California Court of Appeal, 2024
Beucke v. Pitonyak CA4/1
California Court of Appeal, 2024
Herzog v. Super. Ct.
California Court of Appeal, 2024
Arax v. Thomas CA5
California Court of Appeal, 2024
Chases v. Chases CA4/1
California Court of Appeal, 2023
Marriage of V.S. & V.K.
California Court of Appeal, 2023
Zwanziger v. Zwanziger Land and Cattle CA3
California Court of Appeal, 2022
Marriage of Davis (Price) and Davis CA5
California Court of Appeal, 2022
Marriage of Elali & Marchoud
California Court of Appeal, 2022
Cook v. Trebino CA6
California Court of Appeal, 2022
DLI Properties v. O'rrell CA2/8
California Court of Appeal, 2021
Ochoa v. T.M Duche Nut Co. CA5
California Court of Appeal, 2020
Aljabban v. Fontana Indoor Swap Meet, Inc.
California Court of Appeal, 2020
Aljabban v. Fontana Indoor Swap Meet CA4/1
California Court of Appeal, 2020

Cite This Page — Counsel Stack

Bluebook (online)
127 Cal. Rptr. 2d 436, 103 Cal. App. 4th 1264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valerio-v-andrew-youngquist-construction-calctapp-2002.