V. R. Dennis Construction Co. v. City of San Diego

188 Cal. App. 2d 833, 10 Cal. Rptr. 894, 1961 Cal. App. LEXIS 2493
CourtCalifornia Court of Appeal
DecidedFebruary 6, 1961
DocketCiv. 6436
StatusPublished
Cited by4 cases

This text of 188 Cal. App. 2d 833 (V. R. Dennis Construction Co. v. City of San Diego) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
V. R. Dennis Construction Co. v. City of San Diego, 188 Cal. App. 2d 833, 10 Cal. Rptr. 894, 1961 Cal. App. LEXIS 2493 (Cal. Ct. App. 1961).

Opinion

SHEPARD, J.

This is an appeal from a judgment holding invalid certain improvement proceedings leading to a contract for improvement of a portion of Myrtle Avenue and 39th Street in the city of San Diego.

The facts came to the trial court by stipulation, there being no dispute in respect thereto. For the purpose of the present controversy, they are substantially as follows: In a proceeding under the "Improvement Act of 1911” (Sts. & Hy. Code, § 5000 et seq.), plans, specifications, plats, maps and drawings were duly prepared showing the work to be done and the boundaries of the assessment district. The city engineer filed his estimate of $21,948.86 as the cost of doing the work, and all other proceedings preliminary to the passage of the resolu *835 tion of intention by which the council declared its intention to order the improvement above referred to, were had and done as required by law. December 30,1958, the city council passed and adopted said resolution of intention in the form and manner provided by law, and set February 3,1959, as the date for hearing objections and protests. On February 3, 1959, only one property owner appeared to protest. He called attention to the fact that the plans had been so drawn that a curb was to be constructed completely across the westerly side of the intersection of the above named streets, thus cutting off access to the unimproved portion of Myrtle Street west of the intersection, and to property abutting thereon. The hearing of February 3 was continued to February 10, the protest was made in writing to conform with statute, and the hearing was again continued to February 17.

In the meantime the city engineer corrected the plans so as to eliminate the obstructing curb, leaving only the gutter and providing short-return segments on each corner of the westerly edge of the intersection so as to allow access to the unimproved portion of Myrtle Avenue. The engineer estimated the additional cost at $241.65. The plans and specifications as thus corrected were reapproved and the hearing was closed on said resolution of intention. The stipulation then goes on to provide as follows:

“3. That thereafter, in compliance with all of the requirements of the Improvement Act of 1911 and all applicable laws, proceedings were had which resulted in the awarding of the contract for the construction of the said public improvement to the petitioner in this action; thereafter, petitioner, under the provisions of Section 5266 of the Street [s] and Highways Code, being a section of the Improvement Act of 1911, as amended, commenced this action for the determination of the validity of the proceedings prior to the commencement of the work under and pursuant to said contract.”

The trial court made findings of fact in exact accordance with the stipulation above referred to.

It is evident from reading the arguments advanced to the trial court, from the trial court’s discussion, and from the treatment of the whole subject made by both sides and all attorneys in their briefs, that neither the parties hereto, nor the trial court itself, understood the stipulation to mean exactly and literally what it said. Obviously, if it was intended to mean literally what it said, i.e., that all proceedings there *836 after were in compliance with law, the trial court’s decision was unquestionably wrong and there would seem to be no occasion for attempted support of it on appeal.

In order that this appeal may not be a complete frustration to all parties, we will assume the additional facts represented to us on appeal to be what was really meant, that is, that after so correcting the plans, no further notice or hearing regarding such correction was given or had, as is provided for in sections 5232 and 5233 of the Streets and Highways Code, but that all other proceedings except the giving of such notice and the holding of such hearings were in accordance with the law.

Thus, there is presented for our decision only the single question of whether or not such contended defect was waived by failure of any property owner to file a protest, as is provided by section 5258.

Under the stipulation that all proceedings following the closing of the hearing on resolution of intention were in compliance with all provisions of law, we must assume that the amount of $241.65 is less than 10 per cent of the total estimated cost of the work, as determined by the successful bid. (See § 5234.) Mathematically, said estimated additional cost amounts to only slightly more than 1 per cent of the engineer’s total estimate. The stipulation does not give the amount of the successful bid but, of course, it does say that all proceedings were according to law, so that if section 5234 applies at all we still do not need to know the amount of the successful bid. Actually, however, both sides have informed us on oral argument that the successful bid was approximately $19,000. Thus, it is clear both by argument and by accepting the stipulation at its face value that the limitations provided by section 5234, even if applicable, do not interfere.

Prom the foregoing statement of facts, it is obvious that the ultimately accepted bid was approximately $3,000 under the engineer’s estimate. We can hardly avoid noticing that if the engineer’s estimate was anywhere near correct, competition must have produced a very favorable bid. Nor can we avoid the knowledge that if these proceedings are held void, the improvement district owners under the steady price pressures of present-day construction may easily lose this advantage and with it several thousand dollars. Even if a similar bid was received, the expense, time and effort lost in complete reinstitution of the proceedings would probably far more than offset the cost of the correction ordered.

*837 In attempting to solve the problem of the question presented, it is the duty of our courts to arrive at the true intent of the Legislature by what it said. A reasonable interpretation in accordance with the apparent purpose of the Legislature is a primary rule of interpretation. (County of Alameda v. Kuchel, 32 Cal.2d 193, 199 [3] [195 P.2d 17].) It should be reasonable, fair and harmonious with its manifest purpose and avoiding mischief or absurd consequences. (Kennard. v. Rosenberg, 127 Cal.App.2d 340, 345 [4-5] [273 P.2d 839].) A liberal construction should be given and all doubts resolved in favor of the validity of the proceedings. (Mathes v. City of Long Beach, 121 Cal.App.2d 473, 477 [2] [263 P.2d 472].) In determining what is intended, the entire act must be viewed as a whole to achieve harmony, if possible. (Wemyss v. Superior Court, 38 Cal.2d 616, 621 [2] [241 P.2d 525].)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Izhar v. The Permanente Federation CA4/2
California Court of Appeal, 2014
Hoffman v. City of Red Bluff
407 P.2d 857 (California Supreme Court, 1965)
People v. Rodriguez
222 Cal. App. 2d 221 (California Court of Appeal, 1963)
Capital Freight Lines v. City of Sacramento
206 Cal. App. 2d 279 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
188 Cal. App. 2d 833, 10 Cal. Rptr. 894, 1961 Cal. App. LEXIS 2493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/v-r-dennis-construction-co-v-city-of-san-diego-calctapp-1961.