Uvalde Rock Asphalt Co. v. Fantham

210 S.W.2d 646, 1948 Tex. App. LEXIS 1167
CourtCourt of Appeals of Texas
DecidedApril 15, 1948
DocketNo. 11970.
StatusPublished
Cited by12 cases

This text of 210 S.W.2d 646 (Uvalde Rock Asphalt Co. v. Fantham) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uvalde Rock Asphalt Co. v. Fantham, 210 S.W.2d 646, 1948 Tex. App. LEXIS 1167 (Tex. Ct. App. 1948).

Opinion

CODY, Justice.

This was an action by appellant, the paving company, on a contract for paving the streets in the subdivision owned by defendants, which was located outside of, but adjoining the city limits of Houston. At the conclusion of all the evidence, both plaintiff and defendants moved for directed verdicts. The court granted defendants’ motion by withdrawing the case from the jury and rendering judgment that plaintiff take nothing.

Plaintiff alleged, among other things, that the paving improvements were completed in accordance with the terms of the contract and were accepted by defendants, as therein provided for. Defendants answered that the work was not in accord with the plans and specifications, and‘that the acceptances relied upon by defendants were executed by the supervising engineer through mistake and because of concealment by plaintiff of faulty workmanship. Also, that said engineer had acted so arbitrarily, capriciously and with such gross negligence in supervising the work and giving the acceptances as to' amount to a fraud on defendants, and that, because of material deviations from the specifications, there was in fact, a new contract, and that it was beyond the authority of said engineer to permit such deviation or to accept such work as completed.

The contract was executed on September 14, 1929 and bound the plaintiff to construct the paving improvements in a good, sound and workmanlike' manner in accordance with the specifications set forth in Exhibit A attached thereto. The contract bound defendants to pay in accordance with its terms upon the completion of the work and the acceptance thereof by T. C. Edminster, engineer.

' Said Exhibit A, among other things, pro7 vided that the streets should be paved with a concrete base six inches thick and it specified the mixture that should be used and that “this pavement shall be constructed in *648 accordance with the City of Houston's specifications”. It was further provided that the work should be done under the supervision of C. T. Edminster, enigneer “with full and absolute authority to accept the completed improvements as such for the property owners and to release * * * the contractor from further obligation after such acceptance with the exception of guaranteed maintenance * * The guaranty so referred to was that the pavement should, for five years, remain in good serviceable condition “smooth and free from defects due to faulty materials or workmanship or any deviation from the City of Houston’s specifications covering such work that may impair its usefulness as a roadway” ; and that if the pavement in the judgment of the city engineer, whose judgment was made conclusive on the contractor (with an exception not here material), became defective, the contractor shall, within five days notice by the engineer, repair the defects.

The “City of Houston’s specifications” in accordance with which plaintiff was bound by the contract to construct the pavements, was not attached to said contract but there was a document issued by H. L. Shaw, City Engineer, on June 12, 1929, identified upon its face as being “Form E-13” and which was designated as being “City of Houston, Texas, —Engineering Department, — Specifications, — Street Paving”. This document, Form E-13, the court held, as a matter of law, was intended by the parties as being the specifications and all the specifications referred to in the contract as being “City of Houston’s specifications”. The specifications relative to concrete paving contained in Form E-13 required that expansion joints be installed in the concrete. Said specifications also' provided against “raking” and required that'-the concrete be puddled, and tamped solid and further provided that the thickness of the concrete base should be not less than ninety per cent of the specified six inches.

Work under the contract was begun the latter part of 1929 and on January 28, 1930, Mr: Edminster, as supervising engineer, executed an acceptance as to the completion of the paving on certain of the streets in the subdivision; and on March 14, 1930, executed an acceptance as to the remaining streets in the subdivision. Within less than a year after the work was so accepted, large cracks and fissures appeared in the pavement entirely through the concrete on all of the streets. Defendants notified plaintiff of such condition verbally and by letter and requested repairs. The acting Director of Public Works for the City of Houston did also. No repairs were made by plaintiff after 1932. By letter dated September 6, 1934, plaintiff notified defendants “In view of the fact that your firm has not taken care of its obligation to us, we do not feel that we are in any way obligated to make said repairs”.- — It was undisputed that the specified expansion joints were not installed and that the pavement was not the specified thickness of six inches nor was it of the specified minimum thickness of ninety per cent of said specified thickness (which would be 5.40 inches) but averaged the thickness of 5.24 inches. — It may be added that at the time the contract was entered into, defendants owed a part of the purchase price on the aforesaid subdivision, and that long prior to the trial, their interest was foreclosed.

The plaintiff predicates its appeal on nine points, being in substance:

Points 1-4 are to the effect: That proof of the supervising engineer’s acceptance required that the court direct a verdict for plaintiff. That the evidence was insufficient to support a finding of fraud in the execution of said acceptance and was insufficient to compel a finding of fraud in the execution of said acceptances. That plaintiff’s evidence of compliance with the contract at least raised a jury question.

Point 5: That the court erred in holding as a matter of law that Form E-13 'constituted the specifications and all of the specifications included in the provision that the pavement was to be constructed “in accordance with the City of Houston’s specifications”.

Points 6, 7: That the court erred in refusing to admit in evidence paragraph 14 of the City of Houston’s' engineering department Form E-10 and further erred in excluding the testimony of plaintiff’s witnesses, Lee and Nolan, concerning the cus *649 tom and practice of the City of Houston’s engineering department with regard to the use of expansion joints.

Points 8, 9: That the court erred in overruling plaintiff’s motion to strike from the evidence the aforesaid Form E-13 and defendant’s evidence on the question of maintenance.

In passing on the court’s refusal of plaintiff’s motion for directed verdict we must, of course, take the evidence in the light most favorable to defendants, inclusive of all inferences favorable to defendants that can he legitimately drawn therefrom. The paving contract specified the character or quality and quantity of maternal and the manner or quality of the workmanship and it provided that the acceptance by Edminster, the supervising engineer, of the work as completed shall be binding on defendants-. It is clear, therefore, that plaintiff made out a prima facie case against the defendants by proving up the acceptance by the supervising engineer.

It is well settled, however, that if such acceptances were rendered fraudulently (Herring v. City of Mexia, Tex.Civ.App., 290 S.W. 792; Uvalde Rock Asphalt Company v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kleberg Cnty. v. URI, Inc.
540 S.W.3d 597 (Court of Appeals of Texas, 2016)
Smith v. Smith
112 S.W.3d 275 (Court of Appeals of Texas, 2003)
Carol Sylvia Smith v. Farrell M. Smith
Court of Appeals of Texas, 2003
NL Industries, Inc. v. GHR Energy Corp.
932 F.2d 422 (Fifth Circuit, 1991)
Uhlir v. Golden Triangle Development Corp.
763 S.W.2d 512 (Court of Appeals of Texas, 1988)
John T. Measday v. Kwik-Kopy Corporation
713 F.2d 118 (Fifth Circuit, 1983)
Monarch Life Insurance Co. v. Trinity Industries, Inc.
495 S.W.2d 41 (Court of Appeals of Texas, 1973)
Lewter v. Parker
354 S.W.2d 945 (Court of Appeals of Texas, 1962)
Weissberger v. Brown-Bellows-Smith, Inc.
289 S.W.2d 813 (Court of Appeals of Texas, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
210 S.W.2d 646, 1948 Tex. App. LEXIS 1167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uvalde-rock-asphalt-co-v-fantham-texapp-1948.