Uvalde Asphalt Paving Co. v. Central Union Stock Yards Co.

86 A. 425, 84 N.J.L. 297, 55 Vroom 297, 1913 N.J. LEXIS 166
CourtSupreme Court of New Jersey
DecidedMarch 3, 1913
StatusPublished
Cited by4 cases

This text of 86 A. 425 (Uvalde Asphalt Paving Co. v. Central Union Stock Yards Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uvalde Asphalt Paving Co. v. Central Union Stock Yards Co., 86 A. 425, 84 N.J.L. 297, 55 Vroom 297, 1913 N.J. LEXIS 166 (N.J. 1913).

Opinion

The opinion of the court was delivered by

Garrison, J.

In this case the action is brought by a paving company to recover from the defendant the balance of the price of certain work executed under a contract between them. The work consisted in the paving of the defendant’s stock yard. The defences were that the certificate of the defendant’s engineer was not obtained as required by the contract, that it was not waived, and that the work was not substantially performed by the plaintiff or accepted by the defendant. With respect to the engineer’s certificate the contract contained these provisions. The eighth section provided: “In case of anjr disagreement or dispute between the contractor and the stock yards company respecting the true construction or meaning of any specification, map, profile or plan, the same shall be referred to and decided by the engineer, and his decision shall be final and conclusive; but should any disagreement or dispute arise relating to the true performance of any covenant or agreement, or the true value of extra work, because of a written requisition under the third mutual covenant, then and in either of such cases such disagreement or dispute shall be referred to three arbitrators, one to be selected by each of the parties, and the third to be selected by the two selected by the parties, and the decision in writing by a majority shall be final. Each party hereto shall pay one-half the expense of such reference.”

The specification as to “payments” provided: “The balance, including the twenty per cent, reserved each month, to be paid upon the completion of the work to the satisfaction of the engineer, to be evidenced by his certificate to that effect.”

There was testimony from which a jury might find that the work when completed met with the apparent approval of the engineer and of his authorized representatives who had supervised it, and that a bill based upon estimates furnished by the latter with the statement that the work was [299]*299“complete and satisfactory” was sent to the defendant in July, 1909, and was followed by some correspondence that related only to the time and method of payment. On August 17th the plaintiff was for the first time reminded that no certificate had been given by the defendant’s engineer, and was then likewise apprised that there were indications that the work had not been satisfactorily done. This communication of the defendant was immediately followed by a letter from its engineer in which he stated that the specification tliat the interstices between the blocks be completely filled with cement grout had not been complied with. The plaintiff thereupon brought suit on the contract, not the present action, but an earlier one, in which the defendant set up by plea the failure of the plaintiff to procure the arbitration provided for in the eighth section of the contract. Upon demurrer it was held by the Circuit Court that a compliance with this provision by the plaintiff was a condition precedent to its right to maintain an action. Plaintiff thereupon discontinued its suit and proceeded to arbitrate the dispute as provided in the contract. As this dispute involves the substantial controversy, it will be well at this point to state precisely of what it consisted. The contract specified as follows: “The proposed pavement shall consist of selected blocks, laid so as to form a fairly uniform level top; they shall be laid on a sand bod one inch thick; after the paving is completed, it shall be rammed to a uniform even surface, satisfactory to the engineer or his inspector, and after having been so rammed it shall be immediately covered with a Portland cement grout, consisting of one part Portland cement and two parts clean, sharp sand. This shall be spread dry over the pávement, leaving a surplus of at least one-eighth inch to one-quarter inch in thickness. Water shall then be added, and with the aid of brooms this grout shall be swept over and all about on the paved surface until the joints and interstices between said blocks shall be completely filled. jSTo blocks with badly broken faces will be accepted.”

After the plaintiff' had completed the pavement, and after [300]*300the defendant had begun using it for the j^arding of cattle, it was claimed that the cement grout (a semi-fluid mixture of sand and cement) had not penetrated to the entire depth of the interstices between the blocks owing to the rising in such spaces of the sandy subsoil on which the pavement was laid, caused by the nature of the soil, the ramming of the blocks and the-putting on of the grout before the soil had subsided or dried out of the interstices. The plaintiff contended that it had performed the work in compliance with the specifications, that this and not the result obtained was the measure of its duty, that it was not responsible for the nature of the subsoil and that the ramming of the blocks and the putting on of the grout “immediately” were expressly required by the contract.

The defendant, on the other hand, contended that in addition to what was detailed in the contract the plaintiff in order to perform properly what was specified should have raked out the sand from the interstices before putting on the grout. This was the dispute at the time the first action was brought, and was the ground of the engineer’s refusal to certify. After the first action was discontinued this precise dispute was submitted to arbitrators appointed under the contract whose award sustained the plaintiff’s contention as to all points, i. both as to its duty under the contact and its true performance thereof.

Upo'n the trial of the present action, which like the earlier one was upon the contract, the plaintiff offered this award in evidence, and upon the objection of the defendant that it was immaterial, irrelevant and incompetent the court refused to admit it as testimony to go to the jury, holding that it presented a question for the court. No exception to this ruling was taken, but the legal question that has been argued is adequately presented by the exception upon which error is assigned, viz., the direction of a verdict for the defendant, for •the substantial question is not the ruling upon the admission of evidence, but the propriety of directing a verdict in view of the court question involved. The first has become aca[301]*301tieinic by the course pursued at the trial, the latter is the substantial question in view of such, judicial course.

Our present concern, therefore, is with the directed verdict which was ordered upon two grounds — first, that the defendant had not waived the certificate of the engineer, and second, that the plaintiff had not substantially performed the contract; upon both of which points the trial judge felt constrained to take the case from the jury because of what he considered to he the overwhelming weight of the evidence. While these questions were thus taken from the jury the award, which admittedly presented a question of law for the court was apparently not considered, certainly was given no controlling effect.

In each of these respects error was, we think, committed.

In view of the conclusion we have reached upon the legal question touching the award the error of taking the case from the jury upon the questions of fact may he dismissed with the remark that the rule of Baldwin v. Shannon, 14 Vroom

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palestroni v. Jacobs
73 A.2d 89 (New Jersey Superior Court App Division, 1950)
Dickinson v. Erie Railroad
90 A. 305 (Supreme Court of New Jersey, 1914)
Central Union Stock Yards Co. v. Uvalde Asphalt Paving Co.
87 A. 235 (New Jersey Court of Chancery, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
86 A. 425, 84 N.J.L. 297, 55 Vroom 297, 1913 N.J. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uvalde-asphalt-paving-co-v-central-union-stock-yards-co-nj-1913.