Utility Consumers' Action Network v. Public Utilities Commission

187 Cal. App. 4th 688, 114 Cal. Rptr. 3d 475, 2010 Cal. App. LEXIS 1443
CourtCalifornia Court of Appeal
DecidedAugust 17, 2010
DocketD055666
StatusPublished
Cited by18 cases

This text of 187 Cal. App. 4th 688 (Utility Consumers' Action Network v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utility Consumers' Action Network v. Public Utilities Commission, 187 Cal. App. 4th 688, 114 Cal. Rptr. 3d 475, 2010 Cal. App. LEXIS 1443 (Cal. Ct. App. 2010).

Opinion

Opinion

McINTYRE, J.

In this proceeding, we consider the petition for writ of review filed by the Utility Consumers’ Action Network (UCAN) challenging Public Utilities Commission of the State of California (Commission) decisions Nos. 08-12-058 and 09-07-024, which granted San Diego Gas and Electric Company’s (SDG&E) application for a certificate of public convenience and necessity (CPCN) to construct the Sunrise Powerlink Transmission Project (Sunrise). (Pub. Util. Code, §§ 1001, 1757; undesignated statutory references are to the Public Utilities Code.) UCAN does not dispute the sufficiency of the evidence to support the Commission’s findings. Instead, it argues that the Commission applied the wrong burden of proof, improperly relied on “extra-evidentiary material facts” to support its findings, and failed to assess cost-effective alternatives as required under section 1002.3. We find no merit in UCAN’s arguments and deny the petition.

FACTUAL AND PROCEDURAL BACKGROUND

We begin by reminding the parties that this original proceeding is governed by the appellate rules. (Cal. Rules of Court, rule 8.4.) California Rules of *693 Court, rule 8.204(a)(1)(C), which applies to writ proceedings (Cal. Rules of Court, rules 8.4, 8.486(a)(6)), requires that the parties’ briefs “[s]upport any reference to a matter in the record by a citation to the volume and page number of the record where the matter appears. . . .” Here, the parties omitted citations to the record or incorrectly cited numerous documents, or, when stating a single fact, cited an entire, sometimes lengthy, document. We are not required to independently search this extensive record to verify the factual or procedural points cited by the parties. (9 Witkin, Cal. Procedure (5th ed. 2008) Appeal, § 695, pp. 764 — 765.) Because all parties failed to comply with California Rules of Court, rule 8.204(a)(1)(C), we take most of the factual and procedural background from the Commission’s two decisions. (See Doppes v. Bentley Motors, Inc. (2009) 174 Cal.App.4th 967, 990 [94 Cal.Rptr.3d 802] [rather than striking appellant’s brief for violation of the rule requiring citations to the record, the reviewing court simply declined to consider the portions of the statement of facts that failed to comply].) We shall refer to the Commission’s December 2008 decision No. 08-12-058 granting SDG&E’s application as the “Decision” and its July 2009 decision No. 09-07-024 modifying the Decision as the “Modified Decision.”

In December 2005, SDG&E applied for a CPCN authorizing construction of Sunrise. Due to deficiencies in the 2005 application, SDG&E filed an amended application in August 2006 which the Commission treated as a new proceeding. SDG&E’s original plans for Sunrise (the Proposed Project) included new 500/230 kilovolt (kV) transmission lines running approximately 150 miles between the Imperial Valley substation and the western portion of SDG&E’s San Diego service area, a new substation in central San Diego County, and other system upgrades and modifications. A 25-mile portion of the proposed 500 kV line crossed Anza-Borrego Desert State Park. SDG&E stated in its 2006 application that Sunrise was needed by 2010 to meet the grid reliability requirements of the California Independent System Operator (CAISO), to enable SDG&E to meet its 2010 renewable energy targets, and to mitigate energy costs.

The Commission’s evaluation of the Proposed Project followed two parallel tracks: (1) the CPCN track, which focused on economics; and (2) the environmental track, which assessed impacts as required by the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21100 et seq.) and the National Environmental Policy Act of 1969 (NEPA) (42 U.S.C. § 4321 et seq.). The final environmental impact report (FEIR) made no recommendation regarding the approval or denial of the Proposed Project, but its contents provided information used by the Commission in deciding whether to issue the CPCN. Public Resources Code section 21168.6 gives the Supreme Court exclusive jurisdiction over challenges to the Commission’s approval of the FEIR. The Supreme Court is holding that challenge in abeyance pending our resolution of the nonenvironmental issues. (Utility Consumers’ Action *694 Network v. California Public Utilities Com. (order filed Dec. 17, 2009, S175532) 2009 Cal. Lexis 13058.)

The CPCN proceedings under section 1001 considered whether SDG&E established a need for the Proposed Project or for an alternative evaluated in those proceedings. The CPCN proceedings were devoted to quantifying the benefits claimed by SDG&E to determine whether the Proposed Project could meet the goals of reliability, use of renewable energy, and reduced cost more economically than other alternatives. For this purpose, the Commission adopted a slightly modified version of CAISO’s modeling approach, based on numerous assumptions described in the Decision as forming the analytical baseline.

In 2006, the Legislature adopted Assembly Bill No. 32 (2005-2006 Reg. Sess.), which requires California to reduce its greenhouse gas (GHG) emissions to 1990 levels by 2020. (Health & Saf. Code, § 38550, including Historical and Statutory Notes, 41B West’s Ann. Health & Saf. Code (2010 supp.) foil. § 38550, p. 13.) The Commission adopted policies and rules designed to achieve these goals in the energy sector, including the recommendation that the electricity sector achieve renewable procurement at 33 percent renewable portfolio standard (RPS) by 2020. The California Air Resources Board (CARB) was tasked with implementing those rules. Models used in the CPCN proceedings reflected California’s GHG policy goals.

On the CEQA/NEPA track, the Commission as lead agency performed a detailed analysis of 27 alternatives to the Proposed Project, including the “No-Project Alternative.” The alternatives offered both generation-based and transmission-based plans, and both minor adjustments and major route changes. The No-Project Alternative included as possibilities the “All-Source Generation Alternative,” the “In-Area Renewable Generation Alternative,” and the “Lake Elsinore Advanced Pump Storage (LEAPS) Transmission-Only Alternative.” Together with the United States Bureau of Land Management (BLM), the Commission prepared an 11,000-page FEIR. The FEIR ranked the Proposed Project and various alternatives in terms of environmental superiority in the following order: (1) All-Source Generation Alternative; (2) In-Area Renewable Generation Alternative; (3) LEAPS Transmission-Only Alternative; and (4) “Final Environmentally Superior Southern Route Alternative.” The last alternative was the only choice among the top four that included transmission lines providing direct access to new renewable resources in Imperial County. It ranked the Proposed Project and other alternative routes through portions of Anza-Borrego Desert State Park below the first four because of their unmitigable impacts on that environmentally sensitive region.

*695

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sevilla v. Sandoval CA2/5
California Court of Appeal, 2025
City and County of S.F. v. Public Utilities Com.
California Court of Appeal, 2025
Croft v. Napoleon CA1/4
California Court of Appeal, 2024
Starcevic v. Pentech Financial Services, Inc.
California Court of Appeal, 2021
Walt Disney Parks & Resorts U.S., Inc. v. Superior Court of L. A. Cnty.
230 Cal. Rptr. 3d 811 (California Court of Appeals, 5th District, 2018)
Rothman v. City of Los Angeles CA2/7
California Court of Appeal, 2016
New Cingular Wireless PCS, LLC v. Public Utilities Commission
246 Cal. App. 4th 784 (California Court of Appeal, 2016)
Alvarez v. W & L Harris Ranches CA3
California Court of Appeal, 2015
Dinaali v. Rohani CA2/3
California Court of Appeal, 2015
Pacific Gas & Electric Co. v. Public Utilities Commission
237 Cal. App. 4th 812 (California Court of Appeal, 2015)
Southern California Edison Co. v. Public Utilities Commission
227 Cal. App. 4th 172 (California Court of Appeal, 2014)
So. Cal. Edison v. PUC CA2/3
California Court of Appeal, 2014
Utility Reform Network v. Public Utilities Commission
223 Cal. App. 4th 945 (California Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
187 Cal. App. 4th 688, 114 Cal. Rptr. 3d 475, 2010 Cal. App. LEXIS 1443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utility-consumers-action-network-v-public-utilities-commission-calctapp-2010.