Utilities Optimization Group, LLC v. TIN, Inc.

440 F. App'x 249
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 8, 2011
Docket10-40471
StatusUnpublished
Cited by2 cases

This text of 440 F. App'x 249 (Utilities Optimization Group, LLC v. TIN, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utilities Optimization Group, LLC v. TIN, Inc., 440 F. App'x 249 (5th Cir. 2011).

Opinion

PER CURIAM: *

Defendant-Appellant TIN, Inc. d/b/a Temple-Inland (“Temple-Inland”), a paper mill, hired Plaintiff-Appellee Utilities Optimization Group, L.L.C. (“UO Group”) to work as a contractor on two large projects involving paper machines. After the projects were complete, the parties disagreed with regard to the amount of payment Temple-Inland owed UO Group under the governing contracts. UO Group sued Temple-Inland for breach of contract. Following a trial, the jury awarded damages to UO Group. Temple-Inland sought a post-verdict judgment as a matter of law, which the district court denied. Temple-Inland appeals. For the following reasons, we REVERSE the denial of the motion for a judgment as a matter of law and RENDER judgment in favor of Temple-Inland.

I

Temple-Inland manufactures paper products. UO Group is a construction firm specializing in the fabrication, construction, and service of paper machines. Temple-Inland invited bids for two pump and installation projects, the “No. 1 Paper Machine Project” and “No. 2 Paper Machine Project.” For each, Temple-Inland published a Request for Quotation instructing prospective contractors to submit their bids on a time and material not-to-exceed pricing basis. UO Group made a bid for each project, and Temple-Inland accepted both bids. In accordance with Temple-Inland’s request, the pricing in UO Group’s bids was on a not-to-exceed basis. Temple-Inland issued purchase orders for the projects, authorizing UO Group to begin work. Both the Requests for Quotation and the Purchase Orders required contractors to acquire a signed “Field Change Order/Authorization Form” prior to implementing any change in the scope or value of the work originally agreed to by the parties. The Purchase Orders further instructed that such “APPROVALS SHALL BE COORDINATED THROUGH THE TEMPLE-INLAND PROJECT REPRESENTATIVE IDENTIFIED ON THIS PURCHASE ORDER,” and each Purchase Order identified Steve Hospodar (“Hospodar”) as the Project Manager and Temple-Inland’s representative for the project. Both Purchase Orders expressly incorporated the terms of a Purchase of Services Contract, an umbrella agreement between Temple-Inland and UO Group “intended to apply to any services that have been requested by Temple-Inland and accepted by [UO Group].” The Purchase of Services Contract states: “No change order shall be binding upon Temple-Inland unless approved in writing by Temple-Inland prior to commencement of the work indicated by such change order.” The contract further explains that any waiver of terms must be in writing:

No claim or right arising out of a breach by Contractor of any or all of the terms and conditions of this purchase of services contract can be discharged in whole or in part by a waiver, renunciation, or failure to enforce such claim or right unless Temple-Inland expressly consents thereto in a separate writing.

The parties do not dispute that the Purchase of Services Contract, Purchase Orders, UO Group’s bid proposals, and Temple-Inland’s Requests for Bids form the basic contractual framework governing the *251 relationship between Temple-Inland and UO Group. Prior to beginning work on Paper Machines No. 1 and 2, all contractors were required to attend a contractor orientation during which they were shown a PowerPoint presentation stating that “Owner’s Rep [Hospodar] will not be authorized to approve changes in scope of work until he has the approval of Maintenance Manger-Bob Dansby,” and that “[a]ny work performed without authorization is done strictly at liability to the contractor.”

Due to various delays and unexpected complications, UO Group’s work on the projects greatly exceeded both the time and the cost originally expected. According to testimony by UO Group’s foreman Ben Snyder, on multiple occasions Hospo-dar either requested changes in the scope of the work or acquiesced to changes in the scope of the work. According to Snyder, when he brought to Hospodar’s attention that these instances would be changes in the scope of the work, Hospodar repeatedly encouraged Snyder to move forward with the job and promised he would “take care of it.” In accordance with the terms of the contracts, UO Group had each of its time sheets signed by Hospodar. Hospodar continued to sign time sheets, even after the work UO Group was performing had exceeded the scope of what the parties had originally agreed upon. Neither UO Group nor Hospodar, however, ever filed the required written change authorization forms. When UO Group finally submitted its invoices, Temple-Inland refused to pay any amount beyond the not-to-exceed price of each contract, minus alleged deductions for work ultimately completed by other contractors.

Based on diversity of citizenship, UO Group sued Temple-Inland in the district court for breach of contract. The case was tried before a jury. Before the case was submitted to the jury, Temple-Inland filed a motion for judgment as a matter of law. The district court denied the motion. The jury found that Hospodar had the authority to waive the written change order requirement, that he in fact had done so, and that Temple-Inland was liable for payment related to the extra work. Temple-Inland filed a post-judgment motion for judgment as a matter of law, which was also denied. The court ordered Temple-Inland to pay $172,031.31 in damages for breach of contract related to Paper Machine No. 1 and $83,568.19 for breach of contract related to Paper Machine No. 2, as well as pre- and post-judgment interest. This appeal follows.

II

Temple-Inland argues that the district court erred by denying its motion for judgment as a matter of law on the basis of UO Group’s lack of evidence that Hospodar had actual or apparent authority to waive the contractual requirement of a written change order. “A motion for judgment as a matter of law should be granted if ‘there is no legally sufficient evidentiary basis for a reasonable jury to find for a party.’” Pineda v. United Parcel Serv., Inc., 360 F.3d 483, 486 (5th Cir.2004) (quoting Fed. R.Civ.P. 50(a)). A district court should “grant a motion for judgment as a matter of law only when the facts and inferences point so strongly in favor of the movant that a rational jury could not reach a contrary verdict.” Id. (internal quotation marks and citation omitted). “A motion for judgment as a matter of law ... in an action tried by jury is a challenge to the legal sufficiency of the evidence supporting the jury’s verdict.” SMI Owen Steel Co. v. Marsh USA, Inc., 520 F.3d 432, 437 (5th Cir.2008) (per curiam) (internal quotation marks and citation omitted). Although we review the district court’s denial of the motion de novo, “our standard of review *252 with respect to a jury verdict is especially deferential.” Id. (internal quotation marks and citations omitted).

UO Group points to a number of pieces of evidence that, it argues, permitted a reasonable jury to conclude the Hospodar had actual or apparent authority to waive the written change order requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janna Russell v. David Russell
941 F.3d 199 (Fifth Circuit, 2019)
Elbar Invs., Inc. v. Okedokun (In re Okedokun)
593 B.R. 469 (S.D. Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
440 F. App'x 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utilities-optimization-group-llc-v-tin-inc-ca5-2011.