Utah Power & Light Co. v. Public Service Commission

713 P.2d 240, 1986 Wyo. LEXIS 463, 1986 WL 1167000
CourtWyoming Supreme Court
DecidedJanuary 28, 1986
Docket85-115
StatusPublished
Cited by4 cases

This text of 713 P.2d 240 (Utah Power & Light Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Power & Light Co. v. Public Service Commission, 713 P.2d 240, 1986 Wyo. LEXIS 463, 1986 WL 1167000 (Wyo. 1986).

Opinion

ROONEY, Justice.

Petitioner petitioned the district court for review of an agency action by respondent Public Service Commission of Wyoming (commission). The district court concluded that the matter was appropriate for determination by this Court and certified it to this Court for such determination pursuant to Rule 12.09, W.R.A.P., 1985 Cum.Supp. Petitioner contends that the commission improperly authorized Pacific Power & Light Company (PP&L) to furnish electrical power to the entire Shute Creek gas processing plant of Exxon Company, U.S.A. (Exxon). The plant is located on the boundary of Sweetwater and Lincoln Counties and requires electrical service in both counties. Petitioner holds a certificate of public convenience and necessity to provide service in Lincoln County, and PP&L holds such to provide service in Sweetwater County.

We affirm the agency action.

The Shute Creek gas processing plant was being constructed to process gas from Exxon’s LaBarge gas field in Sublette, Lincoln and Sweetwater Counties. It is composed of three gas processing trains and a carbon dioxide compression station. Two of the gas processing trains were to be located on the Lincoln County side of the plant. The other gas processing train and the compressor station were to be located on the Sweetwater County side of the plant. The gas processing trains require a *242 power load of 35 megawatts each, and the compressor station requires a power load of 45 megawatts. Thus, the power load for that in Lincoln County is 70 megawatts, and for that in Sweetwater County it is 80 megawatts. The service requirement for the entire load is at a transmission voltage of 230 kV. PP&L’s closest 230-kV source is its Granger line 12.8 miles from the site. Petitioner’s closest kV source is at its Naughton generating plant 30.5 miles from the site.

PP&L’s request for a certificate of public convenience and necessity is to construct a single radial 12.8-mile 230-kV transmission line to provide the entire 150-megawatt load requirement of the plant. Petitioner opposed the request of PP&L and requested a certificate of public convenience and necessity for itself to construct a 30.5-mile 230-kV transmission line to provide 70 megawatts for the two gas processing trains in Lincoln County. The commission granted PP&L’s request and denied that of petitioner.

Subsequently, petitioner unsuccessfully attempted to obtain a rehearing of the matter on the basis of alleged newly discovered evidence that Exxon was planning to expand the processing facility.

Petitioner words the issues on appeal as:

“ISSUE I
“Did the Public Service Commission of Wyoming err in ordering that the public convenience and necessity requires that electric service be provided by Pacific Power & Light Company in the certificated territory of Utah Power & Light Company.
“ISSUE II
“Did the Public Service Commission of Wyoming abuse its discretion and err in refusing to allow the administrative record to be reopened in order to supplement it with newly-discovered evidence.”

ISSUE I

Petitioner emphasizes that it is willing and able to serve Exxon’s demand for electrical power to the facilities in Lincoln County, petitioner’s certificated area. It points to language by the commission in connection with previous matters which recognizes the impropriety of invasion of a certificated area of one utility by another utility, but it refuses to accept the commission’s determination that the conditions in this case are unique. At page 40 of its findings, opinion and order, the commission recites:

“This Commission does not by this decision condone the raiding or invasion of another utility’s certificated territory. * * * Pacific Power * * * would not have been allowed to serve the Shute Creek Plant if the public interest had not demanded that result. The Commission considers this case as unique and it would be a mistake for any public utility to attempt to use this decision as a stepping stone for the invasion of another’s certificated area.” (Emphasis in original.)

Pertinent to this case are the following statutory powers given to the commission:

“No public utility shall begin construction of a line, plant or system, or of any extension of a line, plant or system without having first obtained from the commission a certificate that the present or future public convenience and necessity require or will require such construction. This act shall not be construed to require any public utility to secure a certificate for an extension within any city or town within which it has lawfully commenced operation, or for an extension into territory contiguous to its line, plant or system for which no certificate is in force and is not served by a public utility of like character or for any extension within or to territory already served by it, necessary in the ordinary course of its business. If any public utility, in constructing or extending its line, plant or system interferes or is about to interfere with the operation of the line, plant or system *243 of any other public utility already authorized or constructed, the commission on complaint of the public utility claiming to be injuriously affected, may after hearing make such order and prescribe the terms and conditions for the location of the lines, plants or systems affected, as to it are just and reasonable. * * *” (Emphasis added.) Section 37-2-205(a), W.S.1977.

The commission has, thus, been given the power to accomplish the reason for the existence of certificates of public convenience and necessity. The purpose for such must be kept in mind in making a determination relative to incidents pertinent to, and the activities allowed by, certificates of public convenience and necessity. Such purposes are concisely set forth at 73B C.J.S. Public Utilities § 69(c) (1983):

“The purposes of requiring a certificate of convenience and necessity are to protect the public from speculation and duplication of facilities, and from inadequate service and higher rates which frequently result from such duplication, and to protect utilities from competition. * * *
“Whether there should be competition * * *, and to what extent, is largely a matter of policy [for] the commission. * * * i)

The facts upon which the commission based the decision in this case reflect that, by allowing PP&L to serve that part of the plant in the area which had been certificated to petitioner, the purpose, i.e., to “protect the public from * * * duplication of facilities,” to “protect the public from * * * inadequate service,” and to “protect the public from * * * higher rates,” was accomplished. To have ruled in favor of petitioner, just the opposite would have occurred — and the purpose for certificates of public convenience and necessity in the specific territory would have been nullified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knight v. Environmental Quality Council
805 P.2d 268 (Wyoming Supreme Court, 1991)
Vandehei Developers v. Public Service Commission
790 P.2d 1282 (Wyoming Supreme Court, 1990)
Beddow v. Employment Security Commission
718 P.2d 12 (Wyoming Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
713 P.2d 240, 1986 Wyo. LEXIS 463, 1986 WL 1167000, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-power-light-co-v-public-service-commission-wyo-1986.