Utah Dep't of Transp. v. Target Corp.

2018 UT App 24, 414 P.3d 1080
CourtCourt of Appeals of Utah
DecidedFebruary 8, 2018
Docket20160122-CA
StatusPublished
Cited by7 cases

This text of 2018 UT App 24 (Utah Dep't of Transp. v. Target Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Dep't of Transp. v. Target Corp., 2018 UT App 24, 414 P.3d 1080 (Utah Ct. App. 2018).

Opinion

HARRIS, Judge:

¶1 One extremely small portion of a massive freeway interchange was built on land that the Utah Department of Transportation (UDOT) took from claimants Target Corporation (Target) and Weingarten/Miller/American Fork LLC (Miller) (collectively, Claimants). The vast majority of the interchange was constructed upon UDOT's own land or upon land taken from others. Claimants complain that the interchange prevents or impairs motorists from viewing their shopping center, and they claim the right to recover severance damages from UDOT related to this loss of visibility and related to the loss of a right-out exit 1 from the shopping center's parking lot. The trial court allowed that claim to proceed to a jury trial, and a jury awarded Claimants more than $2.3 million in severance damages.

¶2 UDOT now appeals, and asserts that the trial court erred in even allowing Claimants' suit for severance damages to reach the jury. UDOT asserts that Claimants' evidence was insufficient, regarding both causation and damages, to support their claims. For the reasons discussed below, we find UDOT's arguments unpersuasive, and therefore affirm.

BACKGROUND 2

¶3 In 2009, UDOT determined that two major highway construction projects (the Projects) needed to be built in fast-growing Utah County. One project involved widening and reconstructing Interstate 15 through essentially the entire length of Utah County, from Santaquin to the Salt Lake County line. This project, in total, was more than twenty-two miles long. The other project involved the construction of a new east-west arterial road from American Fork through Lehi to Saratoga Springs. This project, in total, was seven miles long. The two Projects intersect at a point in American Fork where Main Street crosses I-15. Before the Projects, there was already a freeway interchange at the site, allowing motorists to cross I-15 on Main Street via an overpass, or get on or off I-15 at that same location. The Projects called for the widening of both I-15 and American Fork Main Street, and therefore UDOT found it necessary to completely rebuild the existing freeway interchange (the Interchange).

¶4 In order to facilitate construction of the new Interchange at that location, UDOT condemned various properties, including three relatively small portions 3 of the Alpine Valley Shopping Center (the Shopping Center), a mall owned largely by Claimants that is located on the northeast corner of the Interchange. The Shopping Center is a large retail facility with many stores and shops. It has one major "anchor" tenant-Target-as well as other smaller retail stores, and includes a large outdoor parking lot. Claimants' witnesses testified at trial that the Shopping Center is designed to draw customers from a large regional area, and that customers are drawn there due to "ease of access and convenience, and knowing how to get there by visibility or good signage." Target owns the land on which its store is located, and Miller owns most of the Shopping Center's remaining land. Both Target and Miller share a parking lot, and also share a cross-easement across the entirety of the Shopping Center. The shared parking lot abuts Main Street, and prior to completion of the Projects a driver could easily access northbound I-15 by making a right-hand turn out of the south side of the parking lot, driving briefly westbound along Main Street, and then merging onto northbound I-15. The original northbound I-15 on-ramp was "at grade"-on the same level-with Main Street.

¶5 UDOT chose to rebuild the Interchange using an innovative "diverging diamond" design, which is "a very unique cross-over type interchange" that involves cars temporarily driving on the left side of the road. Significantly for present purposes, a diverging diamond design requires a lot of space, and in this case that design required that the bridge over the freeway be built higher than other design options, and also required much larger and higher on-and off-ramps. To take one specific example, the northbound I-15 on-ramp was raised from "at grade" (in the before condition) to a height of some twenty-three feet (in the after condition). The new Interchange's increase in height affected Claimants' property and the surrounding area in several ways.

¶6 First, the heightened overpass and raised northbound I-15 on-ramp required UDOT to gradually raise the elevation of Main Street as it approached the Interchange. Because Main Street itself was being raised, UDOT determined that, "for safety reasons," it could no longer permit right-out access from the south end of the Shopping Center onto the now-heightened Main Street, although UDOT was able to preserve right-in access from westbound Main Street into the parking lot. In connection with closing this right-out exit, UDOT took from Claimants one small rectangular parcel located on the south side of the shared parking lot, along Main Street. UDOT did not build any portion of the Interchange on this parcel. Prior to the taking, the right-out exit was the most heavily used exit in the parking lot, due to its proximity to the northbound I-15 on-ramp. After the taking, the closure of the right-out exit required all traffic exiting the parking lot to use an intersection located along the east side of the Shopping Center, along Kawakami Drive.

¶7 Next, to facilitate construction of the heightened northbound I-15 on-ramp, UDOT built a retaining wall along the northbound on-ramp. In order to support the retaining wall, UDOT found it necessary to construct an earthen slope alongside the retaining wall. UDOT did not, however, have enough space on its own property for the entire dirt support slope, so UDOT took a perpetual "slope easement" across a long, narrow parcel of Claimants' land that runs alongside the northbound I-15 on-ramp. UDOT then placed a large amount of dirt on the slope easement, creating a slope that supported the retaining wall that, in turn, supported the raised on-ramp onto northbound I-15. While the retaining wall itself is not located on the slope easement, the dirt slope supporting the retaining wall is at least partially located on the slope easement. 4

¶8 At trial, Target's representative testified that UDOT informed him that "it was not feasible to maintain the right-out [exit] due to the new construction, the design, specifically, of this diverging diamond." However, no other witness at trial testified that the condemnation of Claimants' specific parcels was "essential to the completion of the project as a whole." See Ivers v. Utah Dep't of Transp. , 2007 UT 19 , ¶ 21, 154 P.3d 802 , overruled in part on other grounds by Utah Dep't of Transp. v. Admiral Beverage Corp. , 2011 UT 62 , 275 P.3d 208

Free access — add to your briefcase to read the full text and ask questions with AI

Related

UDOT v. Target Corp.
2020 UT 10 (Utah Supreme Court, 2020)
Sprague v. Avalon Care Center
2019 UT App 107 (Court of Appeals of Utah, 2019)
Pinney v. Carrera
2019 UT App 12 (Court of Appeals of Utah, 2019)
Arreguin-Leon v. Hadco Construction
2018 UT App 225 (Court of Appeals of Utah, 2018)
Rocky Mountain Power Inc. v. Randy E. Marriott, Edge Holdings LLC
2018 UT App 221 (Court of Appeals of Utah, 2018)
Utah Dep't of Transp. v. Lej Invs. LLC
437 P.3d 569 (Court of Appeals of Utah, 2018)
UDOT v. LEJ Investments
2018 UT App 213 (Court of Appeals of Utah, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2018 UT App 24, 414 P.3d 1080, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-dept-of-transp-v-target-corp-utahctapp-2018.