Uscoc of Greater Missouri v. Vill. of Marlborough

618 F. Supp. 2d 1055, 2009 U.S. Dist. LEXIS 36410, 2009 WL 1176282
CourtDistrict Court, E.D. Missouri
DecidedApril 30, 2009
DocketCase No. 4:08CV896 CDP
StatusPublished

This text of 618 F. Supp. 2d 1055 (Uscoc of Greater Missouri v. Vill. of Marlborough) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uscoc of Greater Missouri v. Vill. of Marlborough, 618 F. Supp. 2d 1055, 2009 U.S. Dist. LEXIS 36410, 2009 WL 1176282 (E.D. Mo. 2009).

Opinion

618 F.Supp.2d 1055 (2009)

USCOC OF GREATER MISSOURI, L.L.C., Plaintiff,
v.
VILLAGE OF MARLBOROUGH, MISSOURI, Defendant.

Case No. 4:08CV896 CDP.

United States District Court, E.D. Missouri, Eastern Division.

April 30, 2009.

*1058 Eric D. Martin, Jill A. Lens, Husch Blackwell Sanders, LLP, St. Louis, MO, for Plaintiff.

Daniel G. Vogel, Cunningham, Vogel & Rost, PC, St. Louis, MO, for Defendant.

MEMORANDUM AND ORDER

CATHERINE D. PERRY, District Judge.

Plaintiff U.S. Cellular is seeking a court order that would allow it to build a cell phone tower on an abandoned McDonald's lot located in the Village of Marlborough, Missouri. Defendant Village of Marlborough denied U.S. Cellular's application to build a tower on the site, and refused to grant U.S. Cellular a variance from the Village's setback requirements. U.S. Cellular's eight-count complaint alleges that the Village's zoning regulations, and their application to U.S. Cellular, violated the Federal Telecommunications Act, the Constitution, and Missouri law.

The Village has moved to dismiss all counts of U.S. Cellular's complaint. Because I conclude that U.S. Cellular has pleaded facts that negate any claim that the Village effectively prohibited the provision of wireless services or discriminated against wireless providers under the Federal Telecommunications Act, I will grant the Village's motion to dismiss Counts I, II, and V, which make those claims. I will, however, deny the Village's motion with respect to U.S. Cellular's claims that the Village failed to support its decisions with substantial evidence in Counts III and IV, and with respect to U.S. Cellular's constitutional and state law claims in Counts VI through VIII.

I. Allegations of the Complaint

The following facts are based on the allegations in U.S. Cellular's amended complaint and on its attached exhibits. U.S. Cellular is a wireless telecommunications provider. In 2005, U.S. Cellular decided to build a cell phone tower in the Village of Marlborough so that it could fill a gap in its cell phone coverage of the area. U.S. Cellular investigated multiple sites within the Village that would provide the necessary coverage, and eventually settled on a site owned by McDonald's Corporation. U.S. Cellular determined that the McDonald's site was the best location for the new tower.

U.S. Cellular approached the Village about obtaining the necessary approvals and permits to build the tower on the McDonald's site. In response, the Village suggested that U.S. Cellular look, instead, into building the tower on property owned by the Village. The Village, through its attorney, told U.S. Cellular that the Village zoning regulations required that U.S. Cellular build its tower on property owned by the Village. Further, the Village told U.S. Cellular that all necessary permits and approvals would be given on an expedited basis for the Village site, and that U.S. Cellular's application, if any, to build on the McDonald's site would not be approved. *1059 If it built the tower on Village property, U.S. Cellular would have to lease the property from the Village and pay rent. Because U.S. Cellular thought the economic terms demanded by the Village were unreasonable, and because the Village site was not a suitable location for the new tower, U.S. Cellular decided to pursue an application to build the tower on the McDonald's site.

The Village's zoning regulations require different application and approval procedures depending on the proposed location of a cell phone tower. If U.S. Cellular chose to build a tower on Village-owned property, it would need to obtain a lease agreement approved by the Village. To build on private property like the McDonald's site, however, U.S. Cellular would need to obtain an administrative permit or a conditional use permit. To obtain an administrative permit, an applicant must submit an application to the Village Building Commissioner along with a $2000 deposit. An applicant must also submit a detailed site plan, showing proposed improvements, the zoning categories of surrounding properties, and required setbacks, among other things.

On July 20, 2007, U.S. Cellular applied for an administrative permit to construct a "disguised support structure" on the Mc-Donald's site. The proposed cell phone tower was to be disguised as a 150-foot tall flagpole. As per the Village's rules, U.S. Cellular submitted a $2000 fee with the application. On September 6, 2007, the Village told U.S. Cellular that the application was incomplete, and would be denied. The Village told U.S. Cellular to submit a revised application, with a site plan "consistent with the applicable ordinances at this location or another location that would meet applicable approval requirements." On September 10, 2007, the Village denied U.S. Cellular's application.

On November 30, 2007, U.S. Cellular submitted a revised site plan. On December 3, 2007, the Village told U.S. Cellular that it needed to file a new application and another $2000 fee. U.S. Cellular complied, and re-submitted its revised site plan, along with other pieces from its first application and a new fee on February 1, 2008. Through a letter dated February 21, 2008, the Village informed U.S. Cellular that the revised application had been denied.

The Village cited numerous reasons for the denial. First, the Village determined that the tower did not meet the requirements of a "disguised support structure" under the Village Code. Second, the Village found that U.S. Cellular's plan violated the Code's setback requirements. Third, the Village found that the application failed to contain plans for sufficient landscape materials or other screening required under the Code to "conceal" equipment. Finally, the Village determined that the application failed to show a parking area as required by the Code and that required site plan and security issues were not addressed.

On March 21, 2008, U.S. Cellular appealed the Village's decision. That same day, and in the same document, U.S. Cellular applied for a variance from the Village's setback requirements. In support of its request for variances and appeal, U.S. Cellular argued that (1) the Village incorrectly interpreted various sections of the Village Code; (2) the Village violated U.S. Cellular's due process rights under the federal and Missouri constitutions, (3) the denial was "arbitrary, capricious, and an abuse of discretion"; (4) the denial violated the Federal Telecommunications Act; and (5) the Village unlawfully required U.S. Cellular to pay duplicate fees.

At the time U.S. Cellular submitted the petition for variances and appeal, the Board of Adjustment was not fully formed. *1060 The Village Board of Trustees appointed members to act on the Board of Adjustment some time after U.S. Cellular filed its appeal. On May 22, 2008, the newly-constituted Board held a hearing on U.S. Cellular's petition. At that hearing, the Village attorney presented the case against U.S. Cellular and called witnesses. The Village attorney also advised the Board about whether it should grant or deny U.S. Cellular's petition. Immediately following the hearing, the Village attorney gave the Board a typed, seventeen-page document entitled "Findings of Fact." The document was prepared before the hearing, yet it cites to the testimony of witnesses who testified live at the hearing. The Board adopted these pre-prepared findings and denied U.S. Cellular's petition for variances and appeal. U.S. Cellular alleges that the Board adopted the "Findings of Fact" without ever reading or reviewing the document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
City of Cleburne v. Cleburne Living Center, Inc.
473 U.S. 432 (Supreme Court, 1985)
Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
City of Rancho Palos Verdes v. Abrams
544 U.S. 113 (Supreme Court, 2005)
Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Bituminous Materials, Inc. v. Rice County, Minnesota
126 F.3d 1068 (Eighth Circuit, 1997)
Margaret Mary Martin v. City of Brentwood, Missouri
200 F.3d 1205 (Eighth Circuit, 2000)
Kenneth Harold Swipies v. Frank Kofka
419 F.3d 709 (Eighth Circuit, 2005)
Town of Castle Rock v. Gonzales
545 U.S. 748 (Supreme Court, 2005)
Sprint Telephony PCS, L.P. v. County of San Diego
543 F.3d 571 (Ninth Circuit, 2008)
Ogden Fire Co. No. 1 v. Upper Chichester Township
504 F.3d 370 (Third Circuit, 2007)
USCOC of New Hampshire RSA 2, Inc. v. Town of Bow
493 F. Supp. 2d 199 (D. New Hampshire, 2007)
Wolfner v. Board of Adjustment
672 S.W.2d 147 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
618 F. Supp. 2d 1055, 2009 U.S. Dist. LEXIS 36410, 2009 WL 1176282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uscoc-of-greater-missouri-v-vill-of-marlborough-moed-2009.