USA Manufacturing Corp. v. Perfection-Schwank, Inc.

610 S.E.2d 600, 271 Ga. App. 636, 2005 Fulton County D. Rep. 494, 2005 Ga. App. LEXIS 120
CourtCourt of Appeals of Georgia
DecidedFebruary 15, 2005
DocketA04A1902
StatusPublished
Cited by4 cases

This text of 610 S.E.2d 600 (USA Manufacturing Corp. v. Perfection-Schwank, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
USA Manufacturing Corp. v. Perfection-Schwank, Inc., 610 S.E.2d 600, 271 Ga. App. 636, 2005 Fulton County D. Rep. 494, 2005 Ga. App. LEXIS 120 (Ga. Ct. App. 2005).

Opinion

MlKELL, Judge.

Defendant USA Manufacturing Corporation (“USA”) appeals from the trial court’s grant of partial summary judgment to plaintiff Perfection-Schwank, Inc. (“Schwank”), in the underlying breach of contract action. For reasons explained below, we affirm.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.

(Citation omitted.) Matjoulis v. Integon Gen. Ins. Corp., 226 Ga. App. 459 (1) (486 SE2d 684) (1997).

So viewed, the record shows that on or about November 20, 2001, USA executed a promissory note for $284,325, which was the amount that it owed Schwank in connection with the purchase of residential heaters. Under the terms of the note, payment was due in full by the maturity date, May 14, 2002; however, USAfailedto satisfy the note. There is evidence in the record that as of September 11, 2002, the balance on the note was $200,267.35.

On June 18, 2002, Schwank filed suit against USA alleging breach of contract. In its answer, USA admitted liability but disputed the amount of damages owed. Schwank moved for judgment on the [637]*637pleadings on October 18, 2002, but a hearing was not held until one year later, on October 27, 2003. During the time between the filing of the motion and the hearing, the parties attempted to reach a settlement. George Horich, the president and general manager of Schwank, sent a proposed settlement agreement to William E. Daniels, the president of USA, dated August 14, 2003. Under the proposed agreement, USA would pay Schwank the total sum of $167,642.79 in monthly payments of $10,000 each, with the entire amount to be fully paid by November 5, 2004. The proposed agreement required USA’s consent to the entry of judgment against it in Georgia and Indiana for any outstanding indebtedness if it did not strictly adhere to the terms of the settlement agreement.1 It further provided that Schwank would provide fuel change-over kits, also called “conversion kits,” to USA, the cost of which was included in the $167,642.79 owed to Schwank. Horich’s signature appeared on the third page of the three-page document. In a letter accompanying the proposed agreement, Horich directed Daniels to sign the agreement and to provide two checks: the August 2003 payment of $10,000 and another in the amount of $3,785.85 to cover the cost of the conversion kits.

Daniels did not agree with all of the terms in Schwank’s proposed agreement. Instead, he altered the first two pages of the agreement, reducing the total indebtedness to $161,455.19, changing the monthly interest rate from 1.0 percent to 0.4 percent, and changing the dates of the monthly payments. The changes to the agreement were made in such a way that the second page matched up perfectly with the unaltered third page containing Horich’s signature. On August 25, 2003, Daniels returned the signed agreement to Horich without commenting on the changes. He also sent two checks in the amounts of $10,000 and $3,785.85.

On behalf of Schwank, Horich sent a letter to Daniels on September 2, 2003, refusing to accept the changes to the proposed settlement agreement. The letter expressly stated that “[t]he contract will not be considered executed until the enclosed original pages are initialed by yourself and the September payment is received.” It is undisputed that Daniels never initialed the original pages of Schwank’s proposed agreement and that USA never provided the September payment. Schwank negotiated the two checks provided by USA on or about September 8,2003. According to Daniels, USAnever received the conversion kits from Schwank.

On October 27, 2003, USA amended its answer to raise the defense of accord and satisfaction. After a hearing on October 27, [638]*6382003, the trial court converted Schwank’s motion for judgment on the pleadings to a motion for summary judgment, granted partial summary judgment to Schwank on the issue of liability, and denied the motion as to the amount of damages owed under the note. The court found that there was no meeting of the minds during the parties’ settlement negotiations and, therefore, no settlement agreement was reached. The court further concluded that no accord and satisfaction resulted from Schwank’s acceptance of the two checks, finding that the checks “were merely payments to be applied to the total amount owed under the note at issue in this case.” It is from this order that USA appeals.

1. USA argues that the trial court erred in granting summary judgment on the issue of liability because there was a genuine issue of material fact about whether the parties reached an accord and satisfaction. USA contends that the revised settlement agreement amounted to a satisfaction of the promissory note. We disagree.

“Whether a settlement is an enforceable agreement is a question of law for the trial court to decide.” (Citation omitted.) Auto-Owners Ins. Co. v. Crawford, 240 Ga. App. 748, 749 (1) (525 SE2d 118) (1999). USA is correct that “[a]s a general rule, whether there is an accord and satisfaction is a question for the jury.” (Punctuation and footnote omitted.) Withington v. Valuation Group, 249 Ga. App. 8, 13 (547 SE2d 594) (2001). However, there are cases where the issue of accord and satisfaction has been properly decided on summary judgment. See, e.g., Kendrick v. Kalmanson, 244 Ga. App. 363, 364 (534 SE2d 884) (2000); Rabenstein v. Cannizzo, 244 Ga. App. 107 (534 SE2d 847) (2000); Mitchell v. W. S. Badcock Corp., 230 Ga. App. 352, 356 (4) (496 SE2d 502) (1998). Thus, as a preliminary matter, the trial court did not err in considering the motion.

An accord and satisfaction occurs when “the parties to an agreement, by a subsequent agreement, have satisfied the former agreement, and the latter agreement has been executed.” OCGA § 13-4-101. “An accord and satisfaction is a contract, which requires a meeting of the minds to render it valid and binding. A definite offer and complete acceptance, for consideration, create a binding contract.” (Citations omitted.) Moreno v. Strickland, 255 Ga. App. 850, 852 (1) (567 SE2d 90) (2002). See also Georgialina Enterprises v. Frakes, 250 Ga. App. 250, 253 (551 SE2d 95) (2001). Under OCGA § 13-3-1, one of the essential requirements of a valid contract is “the assent of the parties to the terms of the contract.” It is clear from the record that there was no meeting of the minds during the settlement negotiations between Schwank and USA. Neither party accepted the terms of the other’s proposed settlement agreement.

The only evidence in support of USA’s argument of the existence of an accord and satisfaction is Schwank’s negotiation of the two [639]*639checks. However, there is nothing in the record demonstrating that USA conditioned acceptance of the checks on the satisfaction of the note. In fact, it was not unreasonable for Schwank to treat the two checks as partial payment for the debt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Pilot Insurance v. CECS, Inc.
52 F. Supp. 3d 1240 (N.D. Georgia, 2014)
Old Peachtree Partners, LLC v. Gwinnett County
726 S.E.2d 437 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
610 S.E.2d 600, 271 Ga. App. 636, 2005 Fulton County D. Rep. 494, 2005 Ga. App. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/usa-manufacturing-corp-v-perfection-schwank-inc-gactapp-2005.