US West Inc v. Aetna Casualty

Court of Appeals for the Fourth Circuit·Decided July 16, 1997·No. 96-1698·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

U.S. WEST, INCORPORATED; KIEWIT CONSTRUCTION COMPANY; DYNALECTRIC COMPANY, Plaintiffs-Appellees, No. 96-1698

v.

AETNA CASUALTY & SURETY COMPANY, Defendant-Appellant.

Appeal from the United States District Court for the Eastern District of Virginia, at Alexandria. James C. Cacheris, Chief District Judge. (CA-95-879-A)

Argued: January 28, 1997

Decided: July 16, 1997

Before ERVIN and HAMILTON, Circuit Judges, and PHILLIPS, Senior Circuit Judge.

Affirmed by unpublished opinion. Senior Judge Phillips wrote the opinion, in which Judge Ervin and Judge Hamilton joined.

COUNSEL

ARGUED: R. Daniel Lindahl, BULLIVANT, HOUSER, BAILEY, PENDERGRASS & HOFFMAN, P.C., Portland, Oregon, for Appellant . Douglas Leo Patin, SPRIGGS & HOLLINGSWORTH, Wash-

ington, D.C., for Appellees. ON BRIEF: Douglas G. Houser, BULLIVANT, HOUSER, BAILEY, PENDERGRASS & HOFF- MAN, P.C., Portland, Oregon; Roger S. Mackey, LAW OFFICES OF WILLIAM C.E. ROBINSON, Fairfax, Virginia, for Appellant. Andrew Bramnick, SPRIGGS & HOLLINGSWORTH, Washington, D.C., for Appellees.

Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).

OPINION

PHILLIPS, Senior Circuit Judge:

This is a diversity action in which a building owner, a general contractor , and a subcontractor sued Aetna Casualty & Surety Company (Aetna) under an "all-risk" property insurance policy for losses incurred when large storage batteries installed by the subcontractor in the owner's building were damaged during installation and had to be replaced. The dispositive issue is whether the losses were excluded from coverage under the policy. The district court, following a bench trial, concluded that they were covered, rejecting Aetna's contention that they were excluded under the policy's terms. On Aetna's appeal, we affirm.

I.

In September 1988, U.S. West (Owner) and Kiewit Construction Company (General Contractor) entered into a contract for the construction of the Landmark Center in Omaha, Nebraska, a project that included a five-story data center. Integral to the data center was an uninterruptible power system (UPS) which was to serve as an emergency power source for the Owner's data equipment. Dynaelectric Company (Electrical Subcontractor) subcontracted to install the UPS along with other electrical work. Critical to the UPS were 1,880 electrical storage batteries. Each battery consisted of a large plastic jar

filled with sulphuric acid in which the battery plates were submerged; each battery then weighed around 400 pounds. The data center design called for locating the batteries on racks with several tiers of shelves. The Electrical Subcontractor used a two-step process in installing them. The batteries were first lifted by a hydraulically-powered cart to the desired shelf level. They were then slid from the end of the rack down the shelf to their intended location on the shelf. Each shelf consisted of two parallel metal rails covered with plastic casings. To aid in the sliding process, the Electrical Subcontractor covered the rails with a lubricant, Aqua Gel II, that was designed primarily for use in pulling wire through conduits and pipes. The Electrical Subcontractor had previously used other wire-pulling lubricants to install batteries, but had not before used Aqua Gel II for that purpose.

The batteries were all installed by this process between December 1990 and April 1991. In October 1991, it was discovered that some of the batteries were cracking on their bottom surfaces and leaking acid. Upon this discovery, the Owner invoked a warranty provision in the general contract which bound the General Contractor to correct all work by it or its subcontractors that was rejected by the Owner as defective under the General Contractor's warranty. Following negotiations between the General Contractor and the Electrical Subcontractor , those two agreed to share the cost of replacing all the plastic jars, whether or not leaks had developed in particular ones. All the jars were then removed and replaced with new ones into which the battery plates were put, and the whole then re-installed by another company than the Electrical Subcontractor. The total cost of replacing the batteries was $626,279.95 which was fully shared, per their agreement, by the General Contractor and the Electrical Subcontractor.

Analysis of the cracked and leaking battery jars revealed that the combined effect of sliding the batteries and using Aqua Gel II as a lubricant caused stress corrosion that resulted in the cracks. In particular , it was revealed that the chemical composition of Aqua Gel II was such as to constitute a corroding agent in its interaction with the plastic battery jars. The sliding process created scratches in the bottom surfaces of the jars which made them then more susceptible to cracking by the corrosive agent in the Aqua Gel II.

At the critical times in issue, the construction project was insured by the "All Risk" property insurance policies issued by Aetna whose coverage is the dispositive issue in this case. In December 1991, the Owner, as an insured under the policies, filed with Aetna a claim for the battery-replacement expenses. Aetna ultimately denied the claim, taking the position that the losses involved were expressly excluded under both the "faulty workmanship" and "latent defect" exclusion provisions of the policies. The Owner, the General Contractor, and the Electrical Subcontractor, each asserting that it was an insured under the policy, then jointly brought this action to recover on the claim denied by Aetna.1 Following a two-day bench trial, the district court made findings of fact respecting the cause of the losses incurred and on their basis concluded that they were excluded by neither of the exclusion provisions relied upon by Aetna, hence were covered by the policies' basic coverage provision, and gave judgment accordingly against Aetna for the full amount of the claim.

This appeal by Aetna followed. Aetna challenges the district court's interpretation of the critical exclusion provisions and certain of the factual findings upon which the court based its application of the provisions as so interpreted.

II.

The critical provisions of the policies are those defining their basic coverage, the perils insured against, and two of the perils excluded, as follows:

6. COVERAGE

Except as hereinafter excluded, this policy covers:

1 Following replacement of the batteries at the shared expense of the General Contractor and the Electrical Subcontractor, the Owner assigned to them jointly its right to receive payment under the insurance policies. In the district court, Aetna contested the two contractors' status as insureds under the policies, but does not challenge on this appeal the district court's determination that each was an insured.

(1) The interest of the Insured in all Real and Personal Property, including improvements and betterments, owned or used by the Insured, or hereafter constructed, erected, installed, or acquired, including while in course of construction, erection, installation, and assembly.

The perils that the property is insured against are described in section 7:

7. PERILS INSURED AGAINST

This policy insures against all risks of direct physical loss or damage to property described herein . . . except as hereinafter excluded.

The perils excluded from coverage are stated in section 8, which states in pertinent part:

8. PERILS EXCLUDED

This policy does not insure:

***

B. Against loss or damage caused by .. . inherent vice, latent defect, wear, tear, or gradual deterioration . . . .

***

Free access — add to your briefcase to read the full text and ask questions with AI

US West Inc v. Aetna Casualty, (4th Cir. 1997).

US West Inc v. Aetna Casualty (US West Inc v. Aetna Casualty) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related