US Securities Associates, Inc. v. United States

123 Fed. Cl. 663, 2015 WL 7175754
United States Court of Federal Claims·Decided November 13, 2015·No. 15-1197C·Published·Cited by 2 cases

Opinion

Post-award bid protest; preliminary injunction; likelihood of success on the merits; fixed price; lowest priced technically acceptable offer.

ORDER AND OPINION

BRUGGINK, Judge.

Pending in this bid protest is plaintiffs motion for preliminary injunctive relief. 2 The matter is fully briefed. Subsequently, plaintiff filed a notice of voluntary dismissal' under RCFC 41(a)(1) along with a motion for relief from the protective order in place in this ease, in order for plaintiff to file a new protest at the Government Accountability Office (“GAO”). 3 The motion indicates that, because access to the administrative record in this case suggests what plaintiffs counsel considers to be additional grounds beyond those of which plaintiff was aware at the time of the GAO protest, it wishes dispensation from the protective order here in order to return to GAO to advance those new arguments there. Oral argument on both motions was scheduled for October 29, 2015. At the beginning of oral argument, plaintiff notified the court that it intended to withdraw its notice of dismissal and proceed with the present suit. After oral argument, plaintiff affirmed that intent by filing a notice of withdrawal of its notice of dismissal and withdrawal of its motion for relief from the protective order. As announced at oral argument, and for the reasons set out below, we deny the request for a preliminary injunction.

PROCEDURAL AND FACTUAL BACKGROUND 4

Plaintiff, U.S. Security Associates, Inc., was one of several holders of a Schedule 84 contract for security services with the General Services Administration (“GSA”). On June 19, 2015, the Administrative Office of the United States Courts (“AO”), acting under that contract, issued a Request for Quotations (Solicitation No. 061915) for security services at the Thurgood Marshall Building in Washington, DC. Those services are currently, and were in the recent past, subject of a different contract issued by the Architect of the United States Capital, which has authority to act with respect to the Marshall Building. The incumbent on that contract is CMI Management, Inc. (“CMI”). Plaintiff is the primary subcontractor for CMI under the incumbent contract. After an extension triggered by plaintiff’s protest at GAO, the incumbent contract is currently scheduled to expire on October 31, 2015.

The RFQ proceeds under Federal Acquisition Regulation (“FAR”) Subpart 8.4, which permits GSA to set up blanket purchase agreements (“BPA”) and for authorized enti *665 ties, such as the AO, to place task orders under the BPA. The task orders can be competed among the holders of the BPA, as the AO did here. The RFQ contemplated award of a fixed price task order to a single awardee for one year with options potentially extending another four and a half years. The award would be made to the “lowest price technically acceptable” (“LPTA”) offer- or. Offerors were asked to submit .their quotations in two volumes, one setting out them price proposal and the second in a technical proposal. The procurement would then proceed in three steps. All offerors who had self-certified that they had “at least 5 years security service experience in a Level IV facility,” AR 43, were permitted to proceed to step two. In step two, the overall lowest price offer was identified. Then in step three, only that lowest price offer was evaluated to determine if the offeror’s technical proposal was acceptable as measured against three evaluation factors by the Technical Evaluation Team (“TET”): Key Personnel, Staffing Plan, and Past Performance. If the lowest price proposal was acceptable, the search was over and a contract awarded. If not, then the TET advanced to consideration of the next lowest price offer.

With respect to key personnel, offerors were required to submit at least one resume for two senior positions: On-Site Security Manager and Captain. The staffing plan needed to reflect how the staff would be recruited, selected, and allocated over the required posts. In order to satisfy the past performance requirement, offerors were to submit information concerning five contracts of similar size, scope and complexity in a comparable facility that had been performed within the past three years or were being currently performed.

. The AO received quotations from [] entities, including plaintiff and the intervenor, Securiguard, Inc. All [ ] met the requirement of certifying five years of security experience. The contracting officer then determined that Securiguard offered the lowest proposed price. The TET therefore evaluated Seeuriguard’s proposal and concluded that it was technically acceptable in all areas and had no deficiencies. Securiguard was awarded the task order on September 8, 2015.

Plaintiff filed a protest with GAO on September 14, and the statutory stay attached. In order to maintain security services under the incumbent contract, the Architect of the Capitol extended the contract with CMI through the end of October. When the GAO, denied the protest on October 8, the AO instructed Securiguard to begin transition preparation with the goal of commencing performance on November 1, 2015. Plaintiff filed its complaint in this court on October 13, 2015, along with a motion for a temporary restraining order and permanent injunction.

DISCUSSION

To obtain preliminary injunctive relief pursuant to Rule 65 of the Rules of the United States Court of Federal Claims (“RCFC”), plaintiff must persuade the court that it is likely to succeed on the merits of the protest, that it will be irreparably harmed if an injunction is not awarded, that the harm to it exceeds the harm to the United States and interested third parties if an injunction is not granted, and that the public interest militates in favor of an injunction. Because the matter is before us on a request for a preliminary injunction, even if we deny the request, plaintiff may still proceed to seek a permanent injunction. Similarly, if we grant the injunction now, -the government and intervenor may still argue that a permanent injunction is unwarranted. There is no prejudicial effect to a grant or denial. 5 Nevertheless, while the harm and public interest considerations obviously will differ in considering preliminary or permanent relief, there is no blinking the fact that, with respect to the merits, consideration of the likelihood of success now requires the court to look at the same arguments it likely will consider when the request for permanent relief is addressed.

Defendant’s opposition to the request for a preliminary injunction raises a subject matter jurisdiction defense and a defense of lack of standing, which, in this context, also implicates jurisdiction. Normally we would have *666 to satisfy ourselves of subject matter jurisdiction and plaintiffs standing in order to proceed. Three factors persuade us that it is unnecessary to resolve those questions now, however. First, we are confronted with an issue of whether interim relief is appropriate, not a permanent resolution of the merits of the case. Second, the question of subject matter jurisdiction, as even defendant concedes, is not entirely straight forward.

Free access — add to your briefcase to read the full text and ask questions with AI

US Securities Associates, Inc. v. United States, 123 Fed. Cl. 663, 2015 WL 7175754 (uscfc 2015).

123 Fed. Cl. 663 (US Securities Associates, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omran Holding Group v. United States
128 Fed. Cl. 273 (Federal Claims, 2016)
US Securities Associates, Inc. v. United States
124 Fed. Cl. 433 (Federal Claims, 2016)