U.S. For and on Behalf of Atlantic Hot Seal, Inc. v. Greenwall Const. Service, Inc.

940 F.2d 654, 1991 WL 146796
CourtCourt of Appeals for the Third Circuit
DecidedAugust 5, 1991
Docket90-1013
StatusUnpublished

This text of 940 F.2d 654 (U.S. For and on Behalf of Atlantic Hot Seal, Inc. v. Greenwall Const. Service, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. For and on Behalf of Atlantic Hot Seal, Inc. v. Greenwall Const. Service, Inc., 940 F.2d 654, 1991 WL 146796 (3d Cir. 1991).

Opinion

940 F.2d 654

20 Fed.R.Serv.3d 875

Unpublished Disposition
NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
UNITED STATES of America, for and on behalf of ATLANTIC HOT
SEAL, INCORPORATED, Plaintiff-Appellee,
v.
GREENWALL CONSTRUCTION SERVICE, INCORPORATED, St. Paul
Mercury Insurance Company, Defendants-Appellants,
v.
The TRAVELERS INDEMNITY COMPANY, Third Party Defendant.

No. 90-1013.

United States Court of Appeals, Fourth Circuit.

Argued March 7, 1991.
Decided Aug. 5, 1991.

Appeal from the United States District Court for the District of South Carolina, at Florence. C. Weston Houck, District Judge. (CA-88-1252-4-2)

James Barr Van Osdell, Van Osdell, Lester, Howe & Rice, P.A., Myrtle Beach, S.C. (Argued), for appellants; Cynthia Graham Howe, Van Osdell, Lester, Howe & Rice, P.A., Myrtle Beach, S.C., on briefs.

Linda Weeks Gwin, Thompson, Henry, Gwin, Brittain & Stevens, P.A., Conway, S.C., for appellee.

D.S.C.

AFFIRMED.

Before CHAPMAN, Senior Circuit Judge, JAMES C. HILL, Senior United States Circuit Judge for the Eleventh Circuit, sitting by designation, and JOHN A. MACKENZIE, Senior United States District Judge for the Eastern District of Virginia, sitting by designation.

OPINION

PER CURIAM:

Defendant-appellant Greenwall Construction Service, Inc. ("Greenwall") appeals two orders arising out of a breach of contract action brought under the Miller Act, 40 U.S.C. Secs. 270 et seq., by Atlantic Hot Seal, Inc. ("Atlantic"). The first order which followed a trial to the bench found that Greenwall had materially breached its subcontract with Atlantic, and the district court awarded damages of $32,633.83 plus prejudgment interest to Atlantic. The second order denied Greenwall's motion to amend the first order to consider Greenwall's counterclaim for damages relating to warranty work. The district court found that the counterclaim had not been previously asserted and that because it was compulsory, it was time-barred. Greenwall appeals, and we affirm.

I.

On September 30, 1986, Greenwall contracted with the United States to repair airfield pavement at the Myrtle Beach Air Force Base. Greenwall and Atlantic thereafter entered into a subcontract whereby Atlantic agreed to perform the sealing portion of the proposed work. All terms of the prime contract between Greenwall and the government were made part of the subcontract between Greenwall and Atlantic. Time was of the essence, with liquidated damages to be assessed for unexcused delays. Greenwall and Atlantic each posted the required bonds pursuant to the Miller Act.

The work was to be completed in seven phases. Phases I through IV progressed without delays. Phase V began on July 1, 1987 and was originally scheduled to be completed on October 24, 1987. Due to an excessive number of bad weather days, the government extended the time for completion until December 10, 1987. On December 10, 1987, the government notified Greenwall that it would be assessing liquidated damages for unexcused delays at approximately five hundred dollars a day. Greenwall then notified Atlantic that it considered the liquidated damages to be Atlantic's responsibility. Atlantic objected to the imposition of these damages against it.

In mid-January 1988, the government accepted phase V of the project. The government then assessed approximately forty days or $20,000 in liquidated damages which was withheld from Greenwall's final installment on phase V. Greenwall informed Atlantic on the same day that the liquidated damages had been withheld.

About a month later, Atlantic demanded full payment for its work on phase V. Greenwall then wrote Atlantic stating that it owed Atlantic only $6,328, which was the remaining contract amount less the total amount of liquidated damages withheld by the government. Greenwall also enclosed a phase V final lien release for Atlantic's signature which stated that Atlantic was due $6,328. Greenwall stated that it would pay Atlantic only after this lien release was executed and returned.

Atlantic did not sign the release. Subsequently, the government reduced the amount of liquidated damages by $9,500. Greenwall notified Atlantic of this reduction but did not offer to pay any of it to Atlantic. Again, Atlantic demanded full payment for its phase V work, but no payments were made. Atlantic then refused to return to complete work on the remaining phases of the project or to perform corrections to any defective work on the prior phases. Greenwall contracted with a new subcontractor to complete the work.

Atlantic filed suit against Greenwall to collect the money owed under the subcontract. The case was tried to the court which found that Atlantic was responsible for one-third of the liquidated damages and that Greenwall materially breached its subcontract when it did not pay Atlantic all monies it owed on a timely basis. The district court also found that Atlantic was not required to present a signed release before being entitled to the money. The district court ordered Greenwall to pay all monies owed to Atlantic for the phase V work less one-third of the liquidated damages.1 Greenwall then made a motion for a new trial, or in the alternative, to alter or amend the district court's order. Greenwall asserted, inter alia, that the district court erred in failing to address Greenwall's counterclaim which alleged damages because of the defective sealing work of Atlantic. The district court denied the motion, and Greenwall appeals both orders. We affirm.

II.

An action on a contractor's bond under the Miller Act is a proceeding at law. Our review is limited to a correction of errors of law and a determination of whether the factual findings of the trial judge are not clearly erroneous. Fed.R.Civ.P. 52. While jurisdiction is conferred on this court by the Miller Act, South Carolina law governs where construction of the statute is not at issue and all acts relevant to the breach of contract action occurred within South Carolina. United States v. Citizens & Southern Nat'l Bank of Atlanta, Ga., 367 F.2d 473, 477 (4th Cir.1966).

III.

The district court found that Greenwall materially breached its subcontract with Atlantic when it failed to pay Atlantic the final phase V installment. According to the subcontract, Greenwall was required to pay Atlantic three days after receiving payment from the government. It is undisputed that Greenwall did not remit the money owed to Atlantic within three days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
940 F.2d 654, 1991 WL 146796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-and-on-behalf-of-atlantic-hot-seal-inc-v-greenwall-const-ca3-1991.