U.S. Builders, Inc. v. Atlantic Louetta, L.P.

95 S.W.3d 585, 2002 WL 31729053, 2002 Tex. App. LEXIS 8892
CourtCourt of Appeals of Texas
DecidedDecember 12, 2002
Docket11-02-00035-CV
StatusPublished
Cited by5 cases

This text of 95 S.W.3d 585 (U.S. Builders, Inc. v. Atlantic Louetta, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Builders, Inc. v. Atlantic Louetta, L.P., 95 S.W.3d 585, 2002 WL 31729053, 2002 Tex. App. LEXIS 8892 (Tex. Ct. App. 2002).

Opinion

Opinion

TERRY McCALL, Justice.

Our former opinion and judgment dated December 5, 2002, are withdrawn, and our opinion and judgment dated December 12, 2002, are substituted therefor.

U.S. Builders, Inc. (USBI) asserts that the trial court did not enter a final judgment in this severed action. 1 On March 9, 2001, the trial court entered a judgment and order for deposit of funds (judgment). On August 24, 2001, the trial court entered an order granting defendant’s motion for summary judgment (summary judgment order). On that same day, the trial court entered its severance order. Because the trial court’s judgment and summary judgment order did not dispose of all of the parties and issues, there is no final judgment in this severed action. Therefore, we dismiss this appeal for want of jurisdiction.

The Suit

USBI and Atlantic Louetta, L.P. (Atlantic Louetta) entered into a construction contract. USBI, as the general contractor, agreed to construct a building and certain improvements, including a parking lot, for Atlantic Louetta, the owner of the property, for the contract price of $1,073,000.00. USBI filed this action against Atlantic Louetta, Wade Construction Company, R.L. Wade, Chicago Title Company, and Continental Casualty Company, alleging that, although it had substantially completed the work required under the contract, the defendants owed USBI $232,285.82, plus interest and attorney’s fees. USBI asserted breach of con *587 tract claims against Atlantic Louetta and Wade Construction Company, the construction manager for the project. USBI alleged that R.L. Wade was the alter ego of Atlantic Louetta and was individually liable for the alleged damages. USBI sought to recover on a bond that Continental Casualty Company issued to secure payment by Atlantic Louetta. USBI also sought to recover funds that Chicago Title Company was holding in an escrow account relating to possible repairs to the parking lot. Atlantic Louetta filed a counterclaim alleging that USBI had breached the contract by failing to complete the work required under the contract; Atlantic Louetta sought to recover damages for USBI’s alleged breach of contract. Chicago Title Company interpled the amount held in escrow, a total of $106,687.76, into the registry of the court.

USBI’s and Atlantic Louetta’s Arbitration

USBI and Atlantic Louetta entered into a binding arbitration agreement and submitted the claims between them to arbitration. In the award of arbitration, the arbitrator concluded that “[t]he net result of this Award is that Atlantic Louetta, L.P. shall pay to U.S. Builders, Inc. the sum of $128,795.02.” Atlantic Louetta filed a motion to enter judgment for it to pay USBI $123,795.02 based on the arbitrator’s award. Atlantic Louetta asserted that the escrow funds in the registry of the court should be used as partial satisfaction of the judgment. USBI claimed that it was entitled to recover more than $123,795.02 under the arbitrator’s award.

The Judgment

On March 9, 2001, the trial court awarded judgment to USBI against Atlantic Louetta for $123,795.02 based on the arbitration award. The trial court found that Atlantic Louetta had tendered this amount, including the deposited escrow funds, to the registry of the court. The trial court ordered that “all obligations incurred by Atlantic Louetta, L.P. with regard to the judgment which is the subject of this case shall be deemed to have concluded.” The trial court further ordered that Chicago Title Company, the interpleader, “shall receive judgment in its favor with regard to the interpleader and shall be released from any further obligation regarding this matter.” The trial court did not mention Wade Construction Company or R.L. Wade or address USBI’s claims against them in the judgment. The trial court did not include a “Mother Hubbard” clause in the judgment or any other language demonstrating an intent to dispose of all of the parties and claims. See Ritzell v. Espeche, 87 S.W.3d 536, 537-38 (Tex.2002).

The Subcontractors’ Post-Arbitration Interventions

Shockley Electric Corporation and Frontier Materials, Inc., two subcontractors on the construction project, intervened in the suit. They alleged that USBI owed them money for work performed on the construction project. USBI answered the subcontractors’ interventions and filed a cross-claim against Atlantic Louetta and Wade Construction Company for contribution and indemnity for the subcontractors’ claims. In their answer to the cross-claim, Atlantic Louetta and Wade Construction Company asserted that USBI could not recover contribution and indemnity from them because USBI had litigated all potential claims against them in the arbitration proceeding. They alleged that, as a result of the arbitration proceeding, “all claims and requests for relief were resolved between Atlantic Louetta, Wade Construction Company and U.S. Builders, Inc.” Atlantic Louetta and Wade Construe *588 tion Company also filed a counterclaim against USBI for attorney’s fees relating to the defense of USBI’s contribution and indemnity claims.

The Severance Order

Atlantic Louetta, Richard Wade, Wade Construction Company, and Chicago Title Company asserted that the arbitrator’s award and the trial court’s judgment confirming the award resolved all of the issues and claims between USBI and them. They requested that the trial court sever the arbitrated claims from the subcontractors’ claims against USBI. The trial court granted the motion to sever and ordered:

[TJhat the claims involving U.S. Builders, Inc. versus Atlantic Louetta, L.P., R.L. Wade, Richard L. Wade and Wade Construction Company, as well as the Interpleader filed by Chicago Title Company, are hereby severed from this cause and shall maintain cause number 99-37037-A.

The Summary Judgment Order

Wade Construction Company moved for summary judgment on USBI’s contribution and indemnity cross-claim for the subcontractors’ claims. Wade Construction Company asserted that, because the arbitration resolved all of USBI’s possible claims against it, the doctrine of res judica-ta barred USBI’s contribution and indemnity claims. On August 24, 2001, the trial court entered its summary judgment order granting Wade Construction Company’s motion for summary judgment. 2

Did the Trial Court Enter a Final Judgment ?

In its first issue, USBI asserts that the trial court did not enter a final judgment in this cause. The issue is whether the trial court’s judgment and later summary judgment order constitute a final judgment in the severed action. A final judgment is the judgment or order that disposes of all of the parties and issues in the suit, including any counterclaims and cross-claims. See Houston Health Clubs, Inc. v. First Court of Appeals, 722 S.W.2d 692, 693 (Tex.1986); Baker v. Hansen, 679 S.W.2d 480

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K.H. v. J.R.
826 A.2d 863 (Supreme Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
95 S.W.3d 585, 2002 WL 31729053, 2002 Tex. App. LEXIS 8892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-builders-inc-v-atlantic-louetta-lp-texapp-2002.