Ursin Seafoods, Inc. v. Keener Packing Co.

741 P.2d 1175, 1987 Alas. LEXIS 296
CourtAlaska Supreme Court
DecidedSeptember 4, 1987
DocketS-1584
StatusPublished
Cited by13 cases

This text of 741 P.2d 1175 (Ursin Seafoods, Inc. v. Keener Packing Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ursin Seafoods, Inc. v. Keener Packing Co., 741 P.2d 1175, 1987 Alas. LEXIS 296 (Ala. 1987).

Opinion

OPINION

COMPTON, Justice.

This appeal is from a judgment entered after a trial awarding damages to Keener Packing Co., Inc. (Keener) in compensation for the breakdown of a fish processing barge it had chartered from Ursin Sea-foods, Inc. (Ursin). The issues presented by this appeal are the proper interpretation to be given the language of the charter agreement and the propriety of the attorney’s fees and costs award. We affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

In 1984 Keener entered a contract to purchase salmon in Bristol Bay which it planned to process using a floating processor and its plant in Kenai. Keener entered agreements with Ursin to charter a fish processing barge, the Great Alaskan, and to purchase a landing craft, the Miss Piggy. In addition, the parties reached collateral agreements with regard to repair and preparation work which was to be done on the Great Alaskan before the charter began.

The charter was for a period of 90 days, beginning around June 5, 1984, at a rate of $2,000 per day.

Three of the charter agreement provisions are particularly relevant. First, the charter agreement provided that before the charter began Ursin and Keener would “thoroughly inspect the vessel including whatever [Keener] feels is necessary to determine that all equipment is operational to [Keener's] satisfaction,” that Ursin would “have a maximum of 10 days to remedy any deficiencies noted during this inspection,” and that the charter period would begin after correction of deficiencies.

The agreement also provided:

Charterer warrants that as of the signing of this agreement, he has inspected the vessel and deems it in all respects adequate for his intended purposes and holds owner harmless regarding all claims and disputes that might arise from representations as to the performance and or suitability of the vessel.

An additional provision of the charter agreement here in question provides:

In the event a major breakdown occurs where it becomes impossible to continue operating, charterer will do everything possible to put the equipment back in working order and owner agrees to assist as necessary. If 48 hours after owner is notified, vessel is still inoperable and the cause of the breakdown is determined by a qualified marine surveyor, selected by owner, to have occurred by no fault of the charterer, charter fee will cease to accrue from the time the 48 hour period lapses until the repairs are made. Charterer will present expenses incurred to owner at end of charter for settlement. If it is determined that the breakdown is a result of an accident or negligence on the part of the charterer, the charter fee will continue to accrue uninterrupted [sic] and charterer will bear all repair expenses.

Arthur Amys, Keener’s President, inspected the Great Alaskan prior to executing the charter agreement.

*1177 Keener and Ursin also entered a side oral agreement that Keener personnel would repair storm damage to the Great Alaskan to prepare it for the charter. The main damage to be repaired by Keener was to the mobile homes on the deck that were to serve as the crew’s living quarters. Keener personnel began making repairs in late May, after the charter agreement had been executed.

Keener also hired a chief engineer, Gary Flatt, who had been Ursin’s chief engineer on the Great Alaskan the previous fishing season. Beginning around May 20, Flatt worked on the vessel’s engines, preparing them for the charter. He found the starboard engine to be weak and strongly recommended that it be overhauled. Keener employee Michael Sawinski expressed this concern to Ursin’s Kodiak general manager Charles Beach.

Beach suggested that Sawinski get a written bid on the cost of the repair to the starboard engine. Sawinski obtained a bid from Ben Everidge, a diesel mechanic who was working on the port engine. Everidge recommended that an in-frame overhaul be done, and prepared an estimate.

Beach was himself concerned and called Ursin’s Seattle office since he did not have authority to go forward with such a major repair. He told Mike Samsel, Ursin’s Vice President, that the engine needed work. Samsel said they would consider the request but denied it the next day. Sawinski testified that Beach told him Ursin did “not want to do anything about it. They will fix it when it breaks.” 1 Norman Ursin, Ur-sin’s president, testified that he had no knowledge of the request that the starboard engine be rebuilt and that he had heard only of a vague request for an engine rebuild kit. Norman Ursin stated that the request was denied because in the event such a kit were needed, someone else would have to go out to the barge to do the work anyway, “and at that time [Ursin] would do it.”

The Great Alaskan left Kodiak for Bristol Bay on June 10, 1984. The repair work had not been completed and was continued en route to Bristol Bay. The trip to Bristol Bay took ten or eleven days. Keener then spent two days setting up its processing operation.

A few days after arrival in Bristol Bay, the Great Alaskan’s generators began to experience repeated failures. First, the port generator began throwing sparks and the port engine was shut down so that Flatt could make repairs. Once Flatt got the port generator running, the starboard generator failed. Flatt and Sawinski spent 48 hours attempting to repair the starboard generator but were unsuccessful. Sawin-ski then flew to Kenai in an unsuccessful attempt to obtain a standby generator. Meanwhile, the turbo charger on the port engine failed and Flatt took the turbo charger from the non-functioning starboard engine and used it to get the port engine running again.

After Sawinski returned from Kenai, the port generator broke down and the Great Alaskan was without power for processing from June 30,1984 until July 3,1984. During this time, only the auxiliary generator was operational. It was too small to operate the fish processing equipment.

Keener notified Ursin of the generator breakdowns. A specialist, Forrest Hayden, was flown out to the vessel on July 2,1984. Hayden determined that the port generator was defective. He also concluded that the generators had suffered mechanical damage due to improper long term maintenance. Not until the next day, July 3, was Hayden able to get the starboard engine and two of the three compressors running.

After Hayden’s inspection, the parties decided to purchase two new generators. The port engine was brought on line on July 6. Finally, on July 8, both engines were back running three compressors at full power. But the generator problems *1178 had seriously disrupted Keener’s processing operations.

The starboard engine failed completely that evening (July 8). Flatt determined that the engine seized due to a mechanical failure, as opposed to loss of oil, and concluded that the engine needed an overhaul.

Amys informed Ursin of the breakdown and that Keener would fly someone out to examine the engine. James Neff, a diesel mechanic, flew out to the vessel on July 10. Neff examined the engine and concluded that it needed a major overhaul.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'CONNELL v. Will
263 P.3d 41 (Alaska Supreme Court, 2011)
Rockstad v. Erikson
113 P.3d 1215 (Alaska Supreme Court, 2005)
Tufco, Inc. v. Pacific Environmental Corp.
113 P.3d 668 (Alaska Supreme Court, 2005)
Rockstad v. Global Finance & Investment Co.
41 P.3d 583 (Alaska Supreme Court, 2002)
Krossa v. All Alaskan Seafoods, Inc.
37 P.3d 411 (Alaska Supreme Court, 2001)
Gamble v. Northstore Partnership
28 P.3d 286 (Alaska Supreme Court, 2001)
Klosterman v. Hickel Investment Co.
821 P.2d 118 (Alaska Supreme Court, 1991)
S & B Mining Co. v. Northern Commercial Co.
813 P.2d 264 (Alaska Supreme Court, 1991)
Horace Mann Insurance Co. v. Colonial Penn Insurance Co.
777 P.2d 1162 (Alaska Supreme Court, 1989)
Jackson v. Barbero
776 P.2d 786 (Alaska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
741 P.2d 1175, 1987 Alas. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ursin-seafoods-inc-v-keener-packing-co-alaska-1987.