Urbana Construction Co. v. Webster County-Calhoun County Joint Drainage District No. 16-31

169 Iowa 351
CourtSupreme Court of Iowa
DecidedMarch 11, 1915
StatusPublished

This text of 169 Iowa 351 (Urbana Construction Co. v. Webster County-Calhoun County Joint Drainage District No. 16-31) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urbana Construction Co. v. Webster County-Calhoun County Joint Drainage District No. 16-31, 169 Iowa 351 (iowa 1915).

Opinion

Evans, J.

[352]*3521. Contracts: engineering terms: flexible meaning: oral understanding : practical construction. [351]*351The plaintiff was a partnership consisting of one Stewart and Van Wegen. It is represented herein by [352]*352Stewart alone, who acquired the interest of his co-partner. The defendants are the supervisors of the two counties comprising the joint drainage board which entered into the contract sued on. In May, 1909, the plaintiff entered into a written contract with the defendants for the construction of the main tile drain for the joint district. The contract was based upon a bid which the plaintiff had filed about a year prior. This bid and the contract in pursuance thereto provided for the payment to the plaintiff of a lump sum of $32,200.00. Plaintiff’s bid- contained the following notation or qualification: “For what is considered rock work $3.00 per cubic yard.” The present action is based upon this proviso in the bid. The claim is that plaintiff did 1,121 cubic yards of rock work and that he is entitled to recover $3,363.00 therefor. The defendants deny that any “rock work” was done within the contemplation of the contract as the same was understood and construed by both parties by mutual oral agreement and as the same was construed by the parties by their conduct throughout the entire period of performance.

By the testimony for the plaintiff, it is made to appear that in the course of the work he encountered many large rocks or boulders, the removal of which involved great labor and expense, and that the same was rock work within the meaning of the contract.

By the testimony for the defendants, it is made to appear that while the bid was under consideration by the drainage board, he was asked to state what he “considered rock work.” Objection was also made by the board to having the term applied to boulders, which were conceded to be present upon and in the ground to a greater or less extent. That the plaintiff thereupon stated that he did not consider boulders as rock work and that the term as used in his bid was intended to apply only to solid or ledge rock. In engineering parlance, “rock work” is concededly a flexible term and may be applied [353]*353to loose rock or to solid rock. The cost of removing solid rock, however, is usually double that of removing loose rock. The term, however, is not usually applied to small stones of smaller dimensions than a cubic yard. The performance of the contract occupied a period of about two years, beginning in October, 1909. The alleged rock was encountered in the fall of 1910 and continued through the winter and until May or June. The engineer in charge furnished the plaintiff with the monthly estimates of the amount of work done, as provided by Sec. 1989-a9. These were filed by the plaintiff with the auditor and he drew thereon the "80% of the value of the work done according to the estimate,” as provided in said section. These estimates never contained any reference to rock work and no member of the drainage board knew that the plaintiff was doing any rock work or claiming to do any at any time during the period of performance. Their first knowledge of such claim was in December, 1911, when the claim was presented. The claim then made, however, was so made upon the estimates and favorable recommendation of the engineer. Upon the trial the engineer was a witness for the plaintiff. The testimony of the plaintiff and the engineer is in harmony as to the fact that rock work was done and is in harmony also as to the reasons why it was never included in any of the current estimates. This reason was that the engineer .believed and so informed the plaintiff that if a claim were made, the board would reject it. It was also said that the members of the board would probably want to examine such work for themselves and would not accept the report of the engineer thereon. It was, therefore, mutually agreed between the plaintiff and the engineer that it would'be better for the plaintiff to defer making any claim until’after the job was completed. This was the course pursued. The yardage which is now claimed for as rock work was included in the estimates as earth work and its value was estimated at the contract price of 36c per linear foot, which would amount to a little more than $1.00 per yard. At the time that the [354]*354claim was first brought to the attention of the drainage board, the drain had been fully covered and most of it was plowed and cropped for the season of 1911. The testimony of the engineer Freimuth is important and we here set forth sufficient thereof to indicate its general character:

I think both Mr. Stewart and I were too easy, too slow. I made many reports during the construction of that improvement, concerning changes, and changes in the laterals, and things of that sort. I don’t know how many, but there was a lot of them. When I said that we had been too easy, I meant to be understood that we had been too easy with ourselves, by us not giving any estimates on those rock while it was due. The Board were in the habit of holding up or rejecting my reports. I had never made an estimate on rock work before. I never had charge of rock work before that called for an estimate. I did not know that if I made a report or estimate on rock work that the Board would examine the work. I thought they would reject my statement, and that they would make an investigation, and my reason in not making that report was the belief that the joint Boards would reject it, but I expected and I had in mind that when the end came and I covered the whole matter in one estimate, that they would accept it. I expected they would accept an estimate covering the entire work, but would reject the monthly estimates. My final report was made after the work was finished, the ditch, filled in, and part of the land broken up, I did not have in mind of destroying the evidence of the condition of the work. I thought it was as proper a time to make the final report then as at any other time before. I think so far as the district was concerned that the parties all knew it and examined it that were interested. I talked to them a good deal, yes. I talked to D. S. Coughlan, a member of the Board. I never met him on the work. I was before the joint meeting during the progress of the work probably' a time or two. I talked over with the Board about the work not being pro-[355]*355grossing. That the work was not going very rapidly. I did not speak of rock work. The subject we talked of was the bulkhead. There was a washout at the upper end of the ditch. They made the ditch very wide, and we couldn’t get started until we got a bigger bulkhead than was planned in the preliminaries. I was out on the work about twice a week during this progress from Knierim. I found that the tile was laid, and the ditch immediately filled in on top of the tile from about eighteen inches to four feet in. It varied. That was the condition of this ditch the various times I saw it, but it was not filled up to the rock line, not filled up as high as the rock came. I saw the rock and assumed that it extended to the bottom.

Q. And it is upon that basis that you have made your report for this thirty-three or thirty-four hundred dollars for work, on the fact that you could see a little of the rock, and assumed that it extended down to the bottom of the ditch ?

A. Well, in inspecting the tile, I could hardly find places I could get through to the tile with my sounding rod, is how I know that the rock extended all the way down.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
169 Iowa 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urbana-construction-co-v-webster-county-calhoun-county-joint-drainage-iowa-1915.