This text of 124 A.D. 587 (Urbach v. Pye) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urbach v. Pye, 124 A.D. 587, 109 N.Y.S. 207, 1908 N.Y. App. Div. LEXIS 2158 (N.Y. Ct. App. 1908).

Opinion

Laughlin, J.:

This is an action by a vendee of certain real property to-, enforce specific performance of the contract or to recover the down payment and expenses of examining tlie title, and ¡have the amount thereof declared a Hen upon and enforced against the land. The trial court has found that the deed tendered by the vendor was not a substantial compliance with the contract in that there was a material difference between the quantity of' land described in the contract and the land described in the deed-,, to which only defendant had. title. We are of opinion that' the proper construction of the contract shows that.the purchase was not according to the quantity of land, but of three lots, already built upon, with fixed boundaries open and obvious, in bulk, for a gross sum, and that there is not.such; a variance between the figures' in the contract indicating the. dimensions and the actual dimensions as shown by the survey and described in the deed tendered as justified the purchaser in refusing to. accept the title. . The contract was made on the 18th day .of June, 1906. The witness clause-recites that the defendant agreed to convey arid the plaintiff agreed to purchase All that lot or parcel of land, in the County of New York, 346-348-350 [St-.] Nicholas Ave., with the buildings and improvements thereon, described as follows :* Party of the first part agrees to sell and' convey [to] the party ’ of the second part $346-348-350 St. Nicholas Ave., plot being size 25-3x81, 25-2x101) and 25-2x97, all parcels being the same size both front and rear more or less.” The purchase price was $76,500. The words 5t'more .or less ” in the contract, qualifying the dimensions, must be given force and effect. There can be no force given to them if the owner is to be held to tendering title to property of the precise dimensions specified in the contract. Of course, if there should be quite a material variance between the measurements specified in the contract and the actual measurements, this might in effect constitute' a misrepresentation, notwithstanding the insertion of the clause “ more . or less,” and in such case a court of equity would not enforce perforrriance. These words, however, fairly construed,-qualify all of the dimensions an/l not merely the dimensions across the front and rear, as contended by the learned counsel for the respondent. It is quite clear, I think, that this was an entire, indivisible purchase of the three' parcels/ and I do not understand that [589]*589this is controverted. We come now to a consideration of a difference between the measurements specified and thus qualified in the contract, and the actual dimensions of the property. We find at the outset that the frontage, which is the most important dimension, was greater by three-quarters of an inch than that specified in the contract. The total width across the rear is nine and one-quarter inches less than that called for by that provision of the contract which is to the effect that the lots are “ the same size both front and rear.” It is conceded that the words “more or less” qualify the dimensions as to width. The side lines evidently are straight lines, so that the three parcels, taken as one, gradually diminish in width from the-front, which is three-quarters of an inch wider than called for by the contract, to nine and one-quarter inches at the rear. The lines of the lot are nearly parallel with One Hundred and Twenty-eighth street, which lies about fifty feet to the north; but.they do not run at right angles to-St. Hicholas avenue, on which they front. The southerly lot, being Ho. 346, described in the contract as eighty-one feet in depth, is in fact eighty feet one and three-quarters inches on the southerly line, and seventy-six feet five inches on the northerly line, making a shortage on the southerly line of ten and one-quarter inches and on the northerly line. four.feet seven inches. The middle lot, being Ho. 3.48, is described in the contract as one hundred and one feet in depth, and. it is in fact one: hundred and one feet two and one-quarter inches on the southerly line and ninety-seven |eet five and oiie-half inches on the northerly line, making a surplus of two and one-quarter inches in the length of the southerly line and a shortage of three feet six and one-half inches on the northerly line. The northerly lot, being Ho..350, which is described in the contractas ninety-seven ■ feet in depth, is in fact ninety-seven-feet five and one-half inches on the southerly line and ninety-three feet nine inches on tlie northerly line, making a surplus in the length of the southerly line of five and one-half inches and a shortage in the length of the northerly line of three feet three inches. The evidence does not show to what extent the buildings cover the premises or that the plaintiff had any knowledge of the facts other than as indicated in the contract. By the provisions of the contract, however, she had notice that there had been a practical location of the lots by buildings [590]*590thereon and that their depth varied. There is no evidence to show the difference in value between the lots as they existed and their, value if they had been of the precise dimensions specified in the contract. It may he that the extra three-quarters of an inch in frontage width adds to the value as much- as the irregular shortage in the depth takes from it. 2sTo foundation was laid by the plaintiff for an abatement of any part of the purchase price upon the theory of a difference between the value of the lots as shown by the survey and the value if they had been of the dimensions specified fin the contract, and the question as to whether an allowance could-be made and the defendant at the same time be compelled to convey is not presented for decision. The defendant appears to have been ready and willing to convey,. according to the description in his title deeds and according to the survey, but'the plaintiff refused to take title unless the defendant would allow her vendee a deduction from the purchase price of $500 for each lot. As already observed, the bare facts showing the difference between the actual measurements and those contained in the contract, which is all that has been shown, were not sufficient to justify the plaintiff in refusing to accept the title. We are influenced in reaching this con-. elusion by the conduct of the plaintiff after discovering the shortage in the measurements, which tends to show; a waiver of the objection. After the contract was signed, a survey of the lots.was made and the plaintiff thereby ascertained the actual measurements. Prior to the time for passing tjtle under the contract, she had also entered into a contract to sell the premises ■ to another, but whether before or after'-the survey was made does not appear. It does appear, however, that after a survey was procured by. her or through her attorney for her vendee, from which she discovered the shortage in the measurements, she made a formal application, in writing, to an attorney for a loan upon the premises and therein described them as being seventy-five feet in width and having a depth of from eighty to one hundred feet.

e

On the day for closing the title the. defendant failed to appear at the time and place specified, but appeared three days later and excused his failure, and negotiations were resumed as if at the time agreed upon. The attorney, for the plaintiff at this time stated that lie had discovered a shortage in the measurements and desired time [591]*591to adjust the matter with the plaiiitiff’s vendee. The defendant acquiesced in this suggestion. Five days later, on the 12th day of September, 1906, the attorneys for the parties met.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bargen v. Ginsberg
126 Misc. 702 (New York Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
124 A.D. 587, 109 N.Y.S. 207, 1908 N.Y. App. Div. LEXIS 2158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urbach-v-pye-nyappdiv-1908.