Upton v. BNFL, Inc.

646 F. App'x 421
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 22, 2016
DocketNo. 15-5751
StatusPublished
Cited by1 cases

This text of 646 F. App'x 421 (Upton v. BNFL, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Upton v. BNFL, Inc., 646 F. App'x 421 (6th Cir. 2016).

Opinion

PER CURIAM.

Leslie D. Jones, Jeffrey L. Keylon, James D. Parten, Timothy E. Robbins, and Paul S. Vance (collectively “Appellants”) are independent subcontractors who claim they were exposed to asbestos containing material (“ACM”) as a result of demolition and salvage work they performed for R & R Electric Corporation (“R & R”) at R & R’s worksite in Oak Ridge, Tennessee. That work had its genesis in 1997 when BNFL, Inc., now known as TSB Nuclear Energy Services, Inc. (hereinafter “BNFL”), entered into a prime contract with the United States Department of Energy (“DOE”) to decontaminate, decommission, and recycle three former uranium processing buildings at DOE’s East Tennessee Technology Park (“ETTP”) in Oak Ridge. The contract included demolition of the associated switchyards (identified as K792 and K-762), which required removal of eight synchronous condensers — four of which were located inside each of the K-792 and K-762 switchyards.'

In 2012, in Civil Action No. 3:12cv295, Appellants sued BNFL, among others, asserting claims for outrageous conduct, battery, negligence, negligence per se, negligent failure to warn, reckless infliction of emotional distress, fraud, negligent and fraudulent misrepresentation, strict liability for ultrahazardous activity, strict products liability, and civil conspiracy. The district court granted summary judgment to BNFL on all claims. We affirm.

I

BNFL’s prime contract with DOE included removal of the four synchronous condensers located inside ETTP’s K-762 switchyard. Each of these condensers [423]*423contained two contiguous components, an exciter and the main condenser, both of which were encased together within one outer shell. The condensers were constructed in the 1950s, weighed approximately two hundred pounds, and contained significant amounts of various metals, including copper wiring, some of which was wrapped in insulating material.

BNFL’s business was nuclear remediation. Because nuclear remediation was not involved in the switchyard demolition, BNFL entered into subcontracts for most of the switchyard work. BNFL also entered into sales agreements with salvage companies that wanted to purchase electrical equipment or infrastructure items as they were being removed from the switch-yards. Under one such sales agreement (the “Electrical Enterprise Agreement”), BNFL sold to American Technologies, Inc. (“ATI”), various kinds of electrical gear, including the four synchronous condensers located in the K-762 switchyard. BNFL provided no warranty as to the condition or operability of any of the equipment or condensers being sold to ATI, and ATI acknowledged that the electrical gear and condensers were being sold “as is.” ATI was responsible for preparing the condensers for removal from BNFL’s worksite at ETTP.

When they entered into the Electrical Enterprise Agreement, neither BNFL nor ATI knew for certain that the condensers contained hazardous materials. They were both well aware, however, that hazardous materials — ACMs, lead paint, PCBs (polychlorinated biphenyls) — could be encountered during the demolition process. David Miller, ATI’s project manager, knew that asbestos, PCBs, and lead were commonly used materials in the 1950s when the condensers were built. ATI specifically agreed that, if hazardous materials were found in the materials it purchased from BNFL, it was “prepared to remove the hazardous material at our K-1415 site, package the material, and return the material to BNFL for proper disposal.” BNFL required ATI to certify that it would comply with all environmental regulations when managing the disposition of the materials purchased from BNFL. Miller assured BNFL that ATI (1) had successfully performed a large number of projects for DOE, among others, in compliance with all environmental regulations, and (2) would “exercise reasonable and prudent oversight of its subcontractors, vendors, and others dispositioning electrical enterprise materials on behalf of ATI.” •

To help with the recycling and resale of the equipment it purchased from BNFL, ATI entered into a separate agreement with R & R, a salvage business owned by Gerald Reese. BNFL had no contractual relationship with R & R or with any of its subcontractors, including Appellants. Appellants, moreover, did not work at BNFL’s worksite in any capacity before and while ATI’s condensers were being readied for removal from BNFL’s work-site.

In February 2000, representatives from BNFL and ATI, as well as Gerald Reese from R & R, met to prepare an Enhanced Work Plan (“EWP”) to define the process for removing ATI’s four condensers from the K-762 switchyard. The EWP detailed the procedures for removing the outer shell from the interior components of the condensers and lifting those components— still intact — onto railcars to be carried to R & R’s worksite, known as the K-1415 site, for further disposition. The EWP was not intended to — and did not — extend to demolition of the component parts for recycling once those components left the BNFL ■ worksite. ATI hired Technology Fabrication, Inc. (“Tech Fab”), to perform [424]*424the work under the EWP. All of the work at BNFL’s worksite was performed in compliance with OSHA and BNFL’s own health and safety procedures. None of the work at BFNL’s worksite involved R • & R’s employees or subcontractors.

The hazards associated with the work at the BNFL worksite were listed as bounding conditions in the EWP. One of those bounding conditions warned of the potential presence of ACM located on piping in the pit underneath the condensers. This potential for ACM was discovered by BNFL’s sampler, Brady Riggs, when — in preparation for the removal of the condensers — he was asked by BNFL to test for hazardous materials on accessible, points in and around the outer shell of the condensers. At the time the EWP was created, BNFL had no information that ACM was inside the condensers.

At or about the same time that it was preparing for the removal of ATI’s condensers from the K-762 switchyard, BNFL was also preparing for the removal of the four condensers from the K.-792 switchyard. The Coy/Superior Team (“Coy”) had subcontracted to remove the condensers from K-792. Like ATI, Coy intended to remove the condensers to its own worksite for scrap recycling. After executing its subcontract but before the condensers had been removed from BNFL’s worksite, Coy learned from reading recently discovered operating manuals that there might be ACM in the exciters attached to the main condensers. When Coy passed this information on to BNFL, BNFL immediately stopped all work on both the Coy and the ATI condensers. BNFL then took samples from the exciters and had them tested for ACM. The tests indicated that ACM was present on the lead wires of the exciters. Using its own abatement contractor, BNFL had the asbestos on the lead wires abated for all eight exciters. When the abatement process was completed, ATI and Coy resumed work on their respective condensers. In late May or early June 2000, ATI and Coy loaded their condenser components onto railcars, and moved the components to their own respective worksites.

ATI, through Tech Fab, had its condenser components moved to R & R’s K-1415 worksite, where R & R’s crew of workers — including Appellants — began disassembling the condenser components. BNFL employees did not oversee and did not participate in the work conducted at R & R’s worksite.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jefferson v. Certain Underwriters at Lloyd's London
658 F. App'x 738 (Fifth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
646 F. App'x 421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/upton-v-bnfl-inc-ca6-2016.