Up Hydro LLC v. Daniel Artibee

CourtMichigan Court of Appeals
DecidedDecember 29, 2016
Docket329710
StatusUnpublished

This text of Up Hydro LLC v. Daniel Artibee (Up Hydro LLC v. Daniel Artibee) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Up Hydro LLC v. Daniel Artibee, (Mich. Ct. App. 2016).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

UP HYDRO, LLC, UNPUBLISHED December 29, 2016 Plaintiff/Cross Defendant-Appellee,

v No. 329710 Alger Circuit Court DANIEL ARTIBEE, LC No. 2013-007306-CH

Defendant/Cross Plaintiff- Appellant.

Before: MARKEY, P.J., and MURPHY and KRAUSE, JJ.

PER CURIAM.

Defendant appeals by right the trial court’s order granting plaintiff’s motion for summary disposition under MCR 2.116(C)(10) (no genuine issue of material fact) on defendant’s counterclaims for breach of contract and to quiet title. We reverse and remand for further proceedings consistent with this opinion.

Defendant and his wife purchased a home and garage in Michigan’s Upper Peninsula in 1988 that was situated on leased land. The land was at the time owned by the Cleveland Cliffs Iron Company. By 2002, the land had been transferred to the Upper Peninsula Power Company, from whom defendant and his wife leased three separate parcels, including the parcel on which their home and garage were located. The land and leases were transferred to plaintiff in 2010.

On May 28, 2013, defendant received a letter from plaintiff that stated as follows:

Dear Mr. Artibee:

This letter is sent on behalf of UP Hydro, LLC (“UP Hydro”), lessor under the above referenced lease or leases (whether one or more, the “Lease”).

UP Hydro is prepared to offer you, pursuant to the terms and conditions of a separate offer agreement to be signed by us, the following in regard to the Lease:

1) UP Hydro will sell you the land your home and garage occupy (subject to survey and creation of a legal description[] acceptable to both parties) for Ten thousand dollars ($10,000.00), including the old school house/VFW building located on UP Hydro’s land.

-1- Please confirm in writing to the address below before June 15, 2013 whether the above general terms are acceptable to you. If we receive notice from you on or before June 15, 2013 that these terms are acceptable to you, then we will immediately prepare and send you a form of offer for your review. If you reject these terms or fail to notify us on or before June 15, 2013, then we will assume that you have rejected these terms and will proceed accordingly with our rights under the Lease.

On June 6, 2013, defendant responded with the following handwritten letter addressed to plaintiff’s representative, Tom Berutti:

Dear Mr. Berutti:

Pursuant to the terms as defined in this letter and per our personal conversation(s), I and my wife Gloria Artibee Accept said terms as stated pending survey and legal description(s) acceptable to both parties.

We eagerly await your response and action(s) so we can at last finalize our concerns over this matter.

Defendant and Berutti walked around the property with defendant, flagging the presumed boundary lines, though defendant acknowledged that Berutti informed him that that boundary was subject to the survey. Defendant also acknowledged his concern that had he later rejected the survey, “probably the contract would have been negated, but we accepted it.”

Plaintiff contracted with a surveyor, who created a survey and legal description of the property that varied in some respects from where defendant and Berutti had presumed the boundary lines to exactly be when they had walked around the property. The surveyor testified that the change was necessary so that the property line would lie a certain distance from a Federal Energy Regulatory Commission (FERC) line. The surveyor testified that this move then brought one of the boundary lines very close to defendant’s garage, perhaps even touching it. While defendant initially expressed his disapproval, he eventually found the survey and resulting legal descriptions acceptable.

Plaintiff, however, refused to consummate the sale, and less than a month after the survey and legal description were created, plaintiff served defendant with a notice to quit. Plaintiff sought to reclaim possession of the property under the lease agreements. Plaintiff then filed in the district court an action to recover real property. Defendant brought counterclaims for breach of contract and to quiet title. The action was then removed to circuit court, which granted plaintiff summary disposition on defendant’s counterclaims, finding that no contract to sell the property had been formed because no formal purchase agreement had been created and because a mutually acceptable legal description of the property had not been obtained. The court explained that plaintiff could pursue its remedies under the lease agreements with defendant.

We review the trial court’s order granting plaintiff summary disposition de novo. See Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999). “A motion under MCR 2.116(C)(10) tests the factual sufficiency of the complaint.” Maiden, 461 Mich at 120. “In presenting a motion for summary disposition, the moving party has the initial burden of -2- supporting its position by affidavits, depositions, admissions, or other documentary evidence.” Quinto v Cross & Peters Co, 451 Mich 358, 362; 547 NW2d 314 (1996). The burden then shifts to the party opposing the motion “to establish that a genuine issue of disputed fact exists.” Id. A court deliberating on the motion considers the evidence submitted in a light most favorable to the non-moving party. Maiden, 461 Mich at 120. A mere pledge to establish an issue of fact at trial is insufficient to survive summary disposition under MCR 2.116(C)(10). Id. at 121.

The existence and interpretation of a contract are questions of law that we review de novo. Kloian v Domino’s Pizza LLC, 273 Mich App 449, 452; 733 NW2d 766 (2006), citing Bandit Industries, Inc v Hobbs Int’l, Inc (After Remand), 463 Mich 504, 511; 620 NW2d 531 (2001). Where a contract has been formed, it must be interpreted according to the plain and ordinary meaning of its terms. Rory v Cont’l Ins Co, 473 Mich 457, 464; 703 NW2d 23 (2005); Alpha Capital Mgt Inc v Rentenbach, 287 Mich App 589, 611; 792 NW2d 344 (2010). “If the contractual language is unambiguous, courts must interpret and enforce the contract as written.” In re Smith Trust, 480 Mich 19, 24; 745 NW2d 754 (2008); see also Rory, 473 Mich at 468.

Plaintiff’s offer clearly states that it would sell defendant the land his home and garage occupy for $10,000 but conditions the offer on the conducting of a “survey and [the] creation of a legal description[] acceptable to both parties.” Defendant promptly responded in writing and advised that he and his wife accept “said terms as stated pending survey and legal description(s) acceptable to both parties.” The clear and unambiguous language of the writings show the parties’ intent to enter a contract for the sale of the land that defendant’s house and garage were on for $10,000, but only if a legal description acceptable to both parties could be created following a survey. The record shows a survey was in fact prepared that varied somewhat from the parties’ understanding of where the property boundaries lay: a legal requirement pertaining to another entity in turn required that a property line be moved closer to defendant’s garage.

Plaintiff argues that no binding contract ever existed between the parties because its offer stated it was “pursuant to the terms and conditions of a separate offer agreement to be signed by us.” Plaintiff argues that this renders its initial offer letter and defendant’s acceptance nothing more than an unenforceable agreement to negotiate. While we agree that the writings may be construed as a contract to enter into a subsequent agreement, “[a] contract to make a subsequent contract is not per se unenforceable; in fact, it may be just as valid as any other contract.” Opdyke Investment Co v Norris Grain Co, 413 Mich 354, 359; 320 NW2d 836 (1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Bandit Industries, Inc. v. Hobbs International, Inc.
620 N.W.2d 531 (Michigan Supreme Court, 2001)
Harbor Park Market, Inc v. Gronda
743 N.W.2d 585 (Michigan Court of Appeals, 2008)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Opdyke Investment v. NORRIS GRAIN COMPANY
320 N.W.2d 836 (Michigan Supreme Court, 1982)
Quinto v. Cross and Peters Co.
547 N.W.2d 314 (Michigan Supreme Court, 1996)
Hansen v. Catsman
123 N.W.2d 265 (Michigan Supreme Court, 1963)
Kloian v. Domino's Pizza, LLC
733 N.W.2d 766 (Michigan Court of Appeals, 2007)
Zurcher v. Herveat
605 N.W.2d 329 (Michigan Court of Appeals, 2000)
Stanton v. Dachille
463 N.W.2d 479 (Michigan Court of Appeals, 1990)
Hammond v. United of Oakland, Inc
483 N.W.2d 652 (Michigan Court of Appeals, 1992)
Hayes v. Beyer
278 N.W. 764 (Michigan Supreme Court, 1938)
Alpha Capital Management, Inc. v. Rentenbach
792 N.W.2d 344 (Michigan Court of Appeals, 2010)
In re Leix Estate
797 N.W.2d 673 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Up Hydro LLC v. Daniel Artibee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/up-hydro-llc-v-daniel-artibee-michctapp-2016.