Universal Refining Products Co. v. Whitcomb Farms, Inc.

6 Mass. App. Div. 96
CourtMassachusetts District Court, Appellate Division
DecidedMarch 31, 1941
StatusPublished

This text of 6 Mass. App. Div. 96 (Universal Refining Products Co. v. Whitcomb Farms, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Refining Products Co. v. Whitcomb Farms, Inc., 6 Mass. App. Div. 96 (Mass. Ct. App. 1941).

Opinion

Pettingell, J.

Action of contract for merchandise sold and delivered. The plaintiff’s agent visited the defendant and received an order in writing for certain products sold by the plaintiff, which had to do with the removal or prevention of rust, scale or other deposits in steam boilers and piping. The merchandise thus ordered was admittedly delivered to the defendant.

By the terms of the written order the defendant was to use the plaintiff’s product as directed. If so used for sixty days, and found not to be satisfactory, the defendant was to notify the plaintiff by letter of the unsatisfactory result, in which case, no charge was to be made for the goods ac[97]*97tually used; the remaining goods, not used, were to be held subject to the plaintiff’s order,. So far as the report shows, the defendant did not within sixty days, notify the plaintiff by letter that the merchandise was not satisfactory. The defendant’s answer was a general denial and payment.

There was a finding for the defendant. The trial judge filed a “Findings” which is hereafter discussed.

The plaintiff’s contentions may be summarized as follows:

(1) There was error in the disposition made by the trial judge of the plaintiff’s requests for rulings.
(2) There was error in the trial judge’s ruling with regard to the nature and effect of the contract between the parties.
(3) There was error in the trial judge’s rulings with regard to the nature and effect of the clause in the contract requiring the defendant to notify the plaintiff by letter at the end of sixty days if the material delivered was not satisfactory.
(4) The finding of a waiver of the plaintiff’s rights under the foregoing clause was not warranted by the evidence and was improper on the pleadings.

In his “Findings”, the trial judge specifically found that the goods were ordered on a written order signed by the defendant, that the plaintiff duly accepted the order and shipped the merchandise, which was received by the defendant; that some of the merchandise was used with unsatisfactory results; that the plaintiff’s agent was several times notified by telephone of the unsatisfactory results within two months after the merchandise was received; and that the agent wrote the plaintiff’s New York office communicating the information that the results had been [98]*98unsatisfactory and that the defendant refused to accept the merchandise.

The trial judge analyzed the contract between the parties as follows:

“7. I find in conclusion that the contract in question was one in which the buyer made known to the seller the particular purpose for which the goods were required and relied on the seller’s judgment and selection of materials; that the contract as made was neither an agreement for a present sale nor a definite agreement for an absolute sale in the future. The evidence was not sufficient to prove that the materials sent by the plaintiff were of the particular kind and quality required by the contract of purchase. The defendant was not bound to accept the goods sent and it gave timely and .sufficient notice of its refusal to accept them. The provision for notice of dissatisfaction contained in the order for the goods in question was for the plaintiff’s benefit and literal compliance therewith could be waived by it. I find that it was waived by the plaintiff by the course of dealings actually had after the plaintiff’s dissatisfaction was communicated to it and that there was neither an actual acceptance of the goods in dispute or the legal equivalent thereof.”

We are of opinion that there was error in his ruling that the contract as made was “neither an agreement for a present sale nor a definite agreement for an absolute sale in the future.” The evidence shows definitely a present sale to become absolute in sixty days unless the defendant should perform a condition subsequent, the giving of a notice to the plaintiff by letter stating that the results of the sixty-day test were unsatisfactory.

The case before us is directly within the facts and the law to be found in Pennsylvania Iron Works Co. v. Hygeian Ice &c. Co., 185 Mass. 366. In that case the plaintiff agreed [99]*99to install certain apparatus in the plant of the defendant, which, on its part, agreed to pay the plaintiff, within one month of the delivery, the amount of $1500, “unless, within that time, it notified the plaintiff that the apparatus had failed to accomplish the results guaranteed (by a third party) and requested its removal.” The period of a month, before the payment was to be made, was provided so that the defendant might have an opportunity to determine whether the capacity of the apparatus was as represented (by the third party). The court said, at pages 370 and 371,

“All that the plaintiff was required to do was to deliver the apparatus upon the defendant’s premises . . . In view of the uncontradicted evidence that it was delivered as required, evidence that it was not accepted was immaterial . . .. The fact, if it was a fact, which the defendant offered to show, that the apparatus produced bad ice was immaterial. If the defendant was dissatisfied with the apparatus, it was bound, under the contract, to notify the plaintiff within a month after the delivery and request its removal. There was nothing to show that it did so, or that those provisions of the contract were waived by the plaintiff, or that anything occurred to excuse the defendant from complying with them. It is true that the defendant expressed dissatisfaction and that efforts were made to improve the apparatus so that it would produce better ice, but this fell far short of the notice and request required by the contract, or of establishing a waiver on the part of the plaintiff, or of furnishing a valid excuse on the part of the defendant for not complying with the provisions of the contract.”

For other cases, in which a failure to perform a condition subsequent has made absolute a promise to pay for goods delivered, see Frank Herscovits Inc. vs. Dorn, 260 Mass. 532, at 534, 535, Siegel v. J & H Goodwin, Ltd. 264 Mass. 65, [100]*100at 67, 68. In the first of these cases, goods were delivered under an agreement which gave the buyer a right to return the g’oods within five days. Failure so to return them made the sale absolute. In the other case the buyer had the right to refuse acceptance if, within tw'enty-four hours after the merchandise was placed where inspection was practicable, he gave notice to the seller of a refusal to accept. The court held that an instruction to the jury that the buyer was not liable if he gave “seasonable” notice of his refusal was error as the evidence did not justify a finding “that the notice was given in compliance with the terms of the contract.”

In the case at bar, the written order was for a definite amount of merchandise of a definite weight, at definite prices. If it were not for the addition to the order of what is included under the heading, “CONDITIONS COVERING SPECIAL ORDER,” the contract would be nothing more than one for present delivery. No terms of payment are stated, either as to time or discount. It would be, in that case, a contract for payment upon delivery. Stephenson v. Cady, 117 Mass. 6, at 9. Morton v. Clark, 181 Mass. 134, at 135. National Contracting Co. v. Vulcanite &c Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schwoerer v. Boylston Market Ass'n
99 Mass. 285 (Massachusetts Supreme Judicial Court, 1868)
Stephenson v. Cady
117 Mass. 6 (Massachusetts Supreme Judicial Court, 1875)
Searle v. Dwelling House Insurance
25 N.E. 290 (Massachusetts Supreme Judicial Court, 1890)
Moore v. Wildey Casualty Co.
57 N.E. 673 (Massachusetts Supreme Judicial Court, 1900)
Cook v. North British & Mercantile Insurance
62 N.E. 1049 (Massachusetts Supreme Judicial Court, 1902)
Morton v. Clark
63 N.E. 409 (Massachusetts Supreme Judicial Court, 1902)
Pennsylvania Iron Works Co. v. Hygeian Ice & Cold Storage Co.
70 N.E. 427 (Massachusetts Supreme Judicial Court, 1904)
National Contracting Co. v. Vulcanite Portland Cement Co.
78 N.E. 414 (Massachusetts Supreme Judicial Court, 1906)
Wheelock v. Postal Telegraph Cable Co.
83 N.E. 313 (Massachusetts Supreme Judicial Court, 1908)
McCord v. Masonic Casualty Co.
88 N.E. 6 (Massachusetts Supreme Judicial Court, 1909)
Clarke v. Massachusetts Title Insurance
100 N.E. 1089 (Massachusetts Supreme Judicial Court, 1913)
De Young v. Frank A. Andrews Co.
100 N.E. 1080 (Massachusetts Supreme Judicial Court, 1913)
Kaufmann v. Sydeman
146 N.E. 365 (Massachusetts Supreme Judicial Court, 1925)
Frank Herskovitz, Inc. v. Dorn
157 N.E. 593 (Massachusetts Supreme Judicial Court, 1927)
Siegel v. J. & H. Goodwin, Ltd.
161 N.E. 818 (Massachusetts Supreme Judicial Court, 1928)
Fitchburg Savings Bank v. Massachusetts Bonding & Insurance
174 N.E. 324 (Massachusetts Supreme Judicial Court, 1931)
Minsk v. Pitaro
187 N.E. 224 (Massachusetts Supreme Judicial Court, 1933)
Markiewicz v. Toton
198 N.E. 659 (Massachusetts Supreme Judicial Court, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
6 Mass. App. Div. 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-refining-products-co-v-whitcomb-farms-inc-massdistctapp-1941.